STAFF SUMMARY FOR Z18-19
CONDITIONAL USE ZONING DISTRICT APPLICATION
APPLICATION SUMMARY
Case Number: Z18-19
Request:
A) Rezoning to a Conditional Use I-2 Zoning District
B) Special Use Permit for a high intensity mining operation
Applicant: Property Owner(s):
Stephen D. Coggins – Rountree Losee LLP Hilton Properties Limited Partnership
Location: Acreage:
4117 Castle Hayne Road/Sledge Road 63.02
PID(s): Comp Plan Place Type:
R00900-001-002-000 Commerce Zone
Existing Land Use: Proposed Land Use:
Undeveloped High intensity mining operation
Current Zoning: Proposed Zoning:
RA (CUD) I-2
SURROUNDING AREA
LAND USE ZONING
North Undeveloped RA
East Undeveloped RA
South Manufacturing (GE), Undeveloped I-2
West Undeveloped RA
Z18-19 Staff Summary PB 3.7.2019 Page 2 of 11
ZONING HISTORY
July 1, 1985 Initially zoned RA (Castle Hayne)
COMMUNITY SERVICES
Water/Sewer Water and sewer services are not proposed for the operation. CFPUA
services are not available in this area.
Fire Protection New Hanover County Fire Services, New Hanover County Northern Fire
District, New Hanover County Station Castle Hayne
Schools The proposed mining operation will not generate students.
Recreation Northern Regional Park
CONSERVATION, HISTORIC, & ARCHAEOLOGICAL RESOURCES
Conservation No known conservation resources
Historic No known historic resources
Archaeological No known archaeological resources
PROPOSED SITE PLAN
The application proposes to develop a high intensity sand mine located in Castle Hayne,
approximately two miles west of NC 133.
The Zoning Ordinance classifies mining operations under two categories: low intensity and
high intensity. Low intensity mining operations are limited to no more than 20 acres of
area, cannot use on-site processing equipment or explosives, and have a maximum
excavation depth of 35 feet if dewatering. The proposed mine is classified as high intensity
due to its permitted size (28.10 acres). No use of explosives, on-site processing, or
Z18-19 Staff Summary PB 3.7.2019 Page 3 of 11
dewatering are proposed by the applicant. Both low and high intensity mining operations
require a special use permit in the I-2 zoning district.
The North Carolina Department of Environmental Quality (DEQ), Division of Energy, Mineral
and Land Resources (DEMLR) issued a mining permit for the proposed operation on
December 15, 2015. The permit allows for a mining operation of 28.10 acres to take
place on the western portion of the property. The permit expires on February 5, 2024.
The state permit includes operation conditions for the proposed mine. Those conditions
include, but are not limited to:
o Maintaining a 50-foot undisturbed buffer between any affected land and any
adjoining waterway or wetland;
o Utilizing water trucks or other appropriate method to prevent dust from leaving the
permitted area (including the access road);
o Prohibiting dewatering activities; and
o Requiring the area east of the mining operation (shown as phase 2 on the site plan)
to remain as an undisturbed buffer. Per DEQ, no activities associated with the
mining operation (outside of the access road) can take place within the undisturbed
buffer including the placement of structures or the parking of vehicles. Any future
mining activities in the phase 2 area would require revision of the DEQ permit and
also a modification of the special use permit.
The issuance of the state permit on December 15, 2015 was a modification of a permit
initially issued in February 2014 to “address concerns of groundwater contamination on
the neighboring General Electric property.” The modification reduced the size of the mining
operation (from 56.63 acres to 28.10), and required monitoring wells to be installed near
the contaminated area. The permit states that “mining shall cease immediately upon
notification that regulatory limits have been exceeded” at the monitoring wells.
The proposed mine will excavate sand from its highest elevation point of approximately
39 feet down to about zero feet (Mean Sea Level). The applicant estimates the mine will
go below the water table at about four to six feet, and a seven-foot-deep lake will be
left at the completion of the excavation.
Proposed Site Plan
Z18-19 Staff Summary PB 3.7.2019 Page 4 of 11
TRANSPORTATION
Access is provided to the subject property by Castle Hayne Road (NC 133) via Sledge
Road (private).
Sledge Road is a private gravel road, approximately 10 feet in width, that runs about
two miles from the subject site to Castle Hayne Road. About a half mile of the road is
adjacent to a residential neighborhood (Wooden Shoe Subdivision). The subdivision
contains 68 lots with nine existing single-family dwellings and an equestrian facility directly
abutting Sledge Road.
Concerns have been raised by the adjacent residents regarding potential noise, vibration,
and dust impacts generated by the trucks traveling to and from the mine.
The number of trips generated by the mine will vary based on the demand, however
according to the applicant, the mine will average 60-80 truckloads a day while it is in
operation.
The Institute of Transportation Engineers (ITE) does not provide trip generation estimates
for mining operations. Based on the applicant’s estimate and the hours of operation, it is
expected that the proposed mine will not exceed 100 trips in the peak hours. Staff
consulted with NCDOT staff regarding the trip generation for this proposal and they concur
based on the information provided by the applicant.
A driveway permit from NCDOT is required for access to Castle Hayne Road. NCDOT has
reviewed the proposal and provided preliminary comments. The comments indicate
modifications must be made to the Sledge Road driveway, but did not define the specific
improvements at this time.
Traffic Counts – January 2018
Road Location Volume Capacity V/C
Castle Hayne Road Near the 4100 Block 10,232 16,200 0.63
Z18-19 Staff Summary PB 3.7.2019 Page 5 of 11
Nearby Planned Transportation Improvements and Traffic Impact Analyses
No TIAs are currently being drafted or have been completed for projects within a one-mile radius from
the subject site within the last five years, or in the general vicinity of the site in the Castle Hayne area.
Regional Transportation Plans:
STIP Project U-5863
o Project to widen Castle Hayne Road to multi-lanes from I-140 to MLK Parkway.
Construction is expected to begin in 2023.
Z18-19 Staff Summary PB 3.7.2019 Page 6 of 11
ENVIRONMENTAL
Portions of the property along the northern property line are within an AE Special Flood
Hazard Area.
The property is not within a Natural Heritage Area.
The site is classified as Wetland Resource Protection on the 2006 CAMA Land Classification
MAP. Per Section 72-42: Mining, of the Zoning Ordinance, high intensity mining operations
are permitted in this classification.
The US Army Corps of Engineers determined in 2013 that the proposed mine will not impact
jurisdictional waters or wetlands. However, this determination is no longer valid and a new
determination must be issued by the Corps prior to commencing of the mining operation.
The property is within the Cape Fear River (C;Sw) and Prince Georges Creek (C;Sw)
watersheds.
Per the Classification of Soils in New Hanover County for Septic Tank Suitability, soils on
the property consist of Class I (suitable/slight limitation) soils.
The issuance of the state mining permit on December 15, 2015 was a modification of a
permit initially issued in February 2014 to “address concerns of groundwater contamination
on the neighboring General Electric property.” The modification reduced the size of the
mining operation (from 56.63 acres to 28.10), and required monitoring wells to be installed
near the contaminated area. The permit states that “mining shall cease immediately upon
notification that regulatory limits have been exceeded” at the monitoring wells.
2016 COMPREHENSIVE LAND USE PLAN
The New Hanover County Future Land Use Map provides a general representation of the
vision for New Hanover County’s future land use, as designated by place types describing
the character and function of the different types of development that make up the
community. Specific goals of the comprehensive plan are designated to be promoted in
each place type, and other goals may be relevant for particular properties.
Future Land Use
Map Place Type Commerce Zone
Z18-19 Staff Summary PB 3.7.2019 Page 7 of 11
Place Type
Description
Serves to provide areas for employment and production hubs,
predominantly composed of light and heavy industrial uses, though office
and complementary commercial uses are also allowed. Densities are
dependent, in part, on the type of industry, and residential uses are
discouraged.
Analysis
The subject property, located to the northwest of the GE site, was
designated Commerce Zone on the Future Land Use Map to allow for future
GE expansions and/or other industrial uses. The County’s industrial zoning
districts are compatible with this place type. Mining is classified as intensive
manufacturing in the Zoning Ordinance and is permitted in industrial districts.
Consistency
Recommendation
The proposed sand mine is generally CONSISTENT with the intent of the
Commerce Zone place type to provide areas for industrial uses.
STAFF PRELIMINARY CONCLUSIONS AND FINDINGS OF FACT:
Staff has conducted an analysis of the proposed use and the information provided as part of the
application package and has created preliminary findings of fact for each of the conclusions
required to be reached to approve the special use permit request. These preliminary findings of
fact and conclusions are based solely on the information provided to date, prior to any information
or testimony in support or opposition to the request that may be presented at the upcoming public
hearing at the Board meeting.
Finding 1: The Board must find that the use will not materially endanger the public health or
safety where proposed and developed according to the plan as submitted and approved.
A. The site is accessed from Castle Hayne Road, an arterial street and North Carolina highway
(NC 133).
B. The subject property is located in the New Hanover County North Fire Service District.
C. Traffic impacts are reviewed by NCDOT through the driveway permitting process, and any
required roadway improvements must be installed in accordance with NCDOT’s standards
prior to the mine being in operation.
D. According to the applicant, the mine will average 60-80 truckloads a day while it is in
operation.
E. The proposed operation obtained a mining permit from the North Carolina Department of
Environmental Quality. The permit allows for up to 28.10 acres to be utilized for the mining
operation.
F. The state mining permit, initially issued in February 2014, was modified on December 15,
2015 to “address concerns of groundwater contamination on the neighboring General Electric
property.” The permit set operating conditions for the mine, including utilizing monitoring
wells and leaving the portion of the property around the contaminated area as an
Z18-19 Staff Summary PB 3.7.2019 Page 8 of 11
undisturbed buffer. The state mining permit also requires that the mining cease immediately
upon notification that regulatory limits have been exceeded at the monitoring wells.
G. The state mining permit requires that a water truck or other appropriate means be utilized
during mining operations to prevent dust from leaving the permitted area including the
access road.
H. The operation will use wet mining techniques. No detwatering will occur at the site.
Staff Suggestion: Evidence provided by the applicant at this time supports a finding that the use will not
materially endanger the public health or safety in the location proposed. The state mining permit
includes operational conditions to mitigate the environmental impacts of the nearby groundwater
contamination.
Finding 2: The Board must find that the use meets all required conditions and specifications of
the Zoning Ordinance.
A. The site is proposed to be zoned I-2, Heavy Industrial.
B. High intensity mining operation are allowed by special use permit in the I-2 zoning districts.
C. The site plan complies with all applicable County technical standards including Zoning
Ordinance Section 72-42: Mining.
D. The site is classified as Wetland Resource Protection on the 2006 CAMA Land Classification
MAP. Per Section 72-42: Mining, of the Zoning Ordinance, high intensity mining operations
are permitted in this classification.
Staff Suggestion: Evidence in the record at this time supports a finding that the use meets all of the
required conditions and specifications of the Zoning Ordinance.
Finding 3: The Board must find that the use will not substantially injure the value of adjoining
or abutting property or that the use is a public necessity.
A. The surrounding area is mostly undeveloped.
B. The property abuts an approximate 1,600-acre parcel of land that is zoned 1-2, Heavy
Industrial.
C. The access road to the mine (Sledge Road) runs along nine existing single-family dwellings
and an equestrian facility located in the Wooden Shoe subdivision, and a total of 68 lots
are located within the neighborhood.
D. The applicant provided an analysis of the impacts an active sand mine will have on single-
family residential property values within a close proximity to the mining operations
(Proposed Sane Mine – What impact does the presence of an active sand mine have on home
values in the adjacent neighborhoods? – Prepared by Trevor Tarleton & F. Blynn Beall,
Streamline Evaluation Services). The analysis examined three sand mines located near
residential neighborhoods and found “no significant economic impacts to home values as
result of an active sand mine in close proximity to each neighborhood.”
Staff Suggestion: Evidence provided by the applicant at this time supports a finding that the use will not
substantially injure the value of adjoining or abutting property.
Z18-19 Staff Summary PB 3.7.2019 Page 9 of 11
Finding 4: The Board must find that the location and character of the use if developed according
to the plan as submitted and approved will be in harmony with the area in which it is to be
located and in general conformity with the plan of development for New Hanover County.
A. The property is located in the Commerce Zone place type, as classified in the 2016
Comprehensive Plan.
B. The Commerce Zone place type areas serve as employment and production hubs,
predominantly composed of light and heavy industrial uses.
C. The proposal is consistent with the recommended uses of the Commerce Zone place type.
D. The property abuts an approximate 1,600-acre parcel of land that is zoned 1-2, Heavy
Industrial and an approximate 4,000-acre parcel of land that is zoned RA, Rural
Agricultural.
E. The access road to the mine (Sledge Road) runs along nine existing single-family dwellings
and an equestrian facility located in the Wooden Shoe subdivision, and a total of 68 lots
are located within the neighborhood.
F. The number of trips generated by the mine will vary based on the demand, however
according to the applicant, the mine will average 60-80 truckloads a day while it is in
operation.
Staff Suggestion: The proposed location of the mining operation is generally consistent with
Comprehensive Plan and the Commerce Zone place type. However, the access road to the mine may
generate impacts to the abutting residential neighborhood. Without improvements along this section
of the road to mitigate those impacts, the potential truck traffic may not be in harmony with the area.
PLANNING BOARD ACTION
The Planning Board considered this application at their January 10, 2019 meeting. At the meeting,
the Board recommended approval of the rezoning of the property (5-1), finding it to be:
1. Consistent with the purposes and intent of the 2016 Comprehensive Plan because the
property is classified as Commerce Zone, a place type that encourages light and heavy
industrial uses.
2. Reasonable and in the public interest because the proposed mining operation site is located
adjacent to existing heavy industrial zoning and will provide employment opportunities.
Additionally, the mining operation site is located approximately 1.5 miles from an existing
single-family subdivision. However, truck traffic generated by the operation could be heavy
at times and without sufficient mitigation could impact the nearby homes.
However, the Board continued the item (6-0) to their March 7, 2019 meeting prior to taking action
on the companion special use permit for the mining operation. The Board suggested that the
applicant meet with the residents of the properties adjacent to Sledge Road and requested that
the applicant provide specific details regarding the improvements proposed for that portion of
Sledge Road.
Z18-19 Staff Summary PB 3.7.2019 Page 10 of 11
RESIDENT MEETING AND APPLICANT RESPONSE
In accordance with the direction of the Planning Board, staff organized a meeting on February 19th
between the applicant and the owners of the properties directly abutting Sledge Road, with
approximately 12 residents attending. At the meeting, the applicant provided a site plan showing
the specific improvements they proposed to install along Sledge Road (Exhibit A). The residents
discussed the plan and suggested the following modifications:
1. Planting vegetation along the section of the road near the existing equestrian facility;
2. Extending the paved section of the road by 300 feet to the northwest;
3. Increasing the height of the fence to 10-12 feet;
4. Adding a berm to help increase the height of the fence;
5. Selecting materials for the fence that are better suited to reduce noise;
6. Selecting vegetation that grows taller and faster;
7. Constructing the paved road to a better standard that supports truck traffic;
8. Ensuring that area drinking water and testing wells will not be damaged or will be repaired
if damaged by the impacts of the construction and use of the road;
9. Relocating the front eastern gate on Sledge Road further west into the site to prevent any
stacking of trucks into Castle Hayne Road.
10. Ensuring both access to test wells located along the road and sufficient screening can be
provided; and
11. Ensuring the road has a proper drainage system to handle the stormwater generated from
the additional pavement.
In response to the meeting, the applicant revised the proposed improvements, which are explained
in a letter to staff (Exhibit B) and illustrated on an updated site plan (Exhibit C). The following
revisions were made to the proposed site plan:
1. Using a different type and thicker asphalt for the pavement;
2. Extending the pavement of the road by 200 feet to the northwest;
3. Increasing the height of the fence to 10 feet;
4. Providing a gate/door in the fence to allow access to existing testing wells; and
5. Planting a single row of vegetation along section of the road near the existing equestrian
facility.
In addition, the applicant has provided updated conditions of approval noted below.
POTENTIAL CONDITIONS
The Planning Board can recommend reasonable and appropriate conditions be added to the
special use permit. The applicant has proposed and agrees to the following conditions:
1. The existing entrance gate off Castle Hayne Road will be moved further up Sledge Road
in order to prevent a “back-up” of queuing trucks attempting to gain access to Sledge Road
from Castle Hayne Road.
2. Hours of operation will be Monday through Friday, 8:00 a.m. to 5:00 p.m., closed on New
Year’s Day, MLK Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day,
and Christmas Day.
3. Speed limit will be 15 MPH along the section of Sledge Road behind the residences. There
will be speed limit signs along the road and the mine operator will be required to implement
Z18-19 Staff Summary PB 3.7.2019 Page 11 of 11
procedures for enforcing the speed. Currently, for our loggers, Hilton Properties has a “3
strikes” policy for violators of rules and policy on our property. Hilton Properties is
encouraging the mine operator to implement a similar policy for the truck drivers entering
and exiting the sand mine.
4. Hilton Properties will comply with applicable stormwater rules and can install the slope of
the pavement so that it drains to the existing ditch along the southwestern edge of Sledge
Road and that will fulfill stormwater requirements.
5. Hilton Properties will maintain the culvert underneath Sledge Road.