HomeMy WebLinkAbout2020.08.11 FINAL Sidbury and Greenview Water and Sewer PER FINALTable of Contents
Sidbury and Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 1 -
Technical Memoranda - Table of Contents
• Executive Summary
• Technical Memorandum 1.0 Introduction & Background
• Technical Memorandum 2.0 Demand Projections
• Technical Memorandum 3.0 Planning Approach
• Technical Memorandum 4.0 Hydraulic Modeling Methodology & Results
• Technical Memorandum 5.0 Wastewater Offsite Analysis
• Technical Memorandum 6.0 Water & Wastewater Infrastructure Recommendations
Figures
• Executive Summary Figure 0.1 – Recommended Water System Improvements
• Executive Summary Figure 0.2 – Recommended Wastewater System Improvements
with Relative Diameter, Length, & Cost
• Executive Summary Figure 0.3 – Recommended Water System Improvements with
Relative Diameter, Length, & Cost
• TM 1.0 Figure 1.1 – Project Area
• TM 2.0 Figure 2.1 – Known Developments & Other Large Developable Tracts
• TM 3.0 Figure 3.1 – Existing Wastewater Infrastructure
• TM 3.0 Figure 3.2 – Existing Water Infrastructure
• TM 3.0 Figure 3.3 – Recommended Wastewater System Improvements
• TM 3.0 Figure 3.4 – Recommended Wastewater System Improvements SA-1
• TM 3.0 Figure 3.5 – Recommended Wastewater System Improvements SA-2
• TM 3.0 Figure 3.6 – Recommended Wastewater System Improvements SA-3
• TM 3.0 Figure 3.7 – Overview Proposed Water Mains
• TM 3.0 Figure 3.8 – Castle Hayne Rd South Proposed Water Mains
• TM 3.0 Figure 3.9 – North College Rd Proposed Water Mains
• TM 3.0 Figure 3.10 – Holly Shelter Rd 2030 Proposed Water Mains
• TM 3.0 Figure 3.11 – Sidbury Rd West Proposed Water Mains
• TM 3.0 Figure 3.12 – Sidbury Rd East Proposed Water Mains
• TM 3.0 Figure 3.13 – Plantation Rd West Proposed Water Mains
Table of Contents
Sidbury and Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 2 -
• TM 3.0 Figure 3.14 – Plantation Rd East Proposed Water Mains
• TM 3.0 Figure 3.15 – Castle Mayne Rd North Proposed Water Mains
• TM 3.0 Figure 3.16 – Holly Shelter Rd 2040 Connection Proposed Water Mains
• TM 3.0 Figure 3.17 – Blue Clay Rd 2040 Proposed Water Mains
• TM 3.0 Figure 3.18 – Blue Clay Rd 2050 Proposed Water Mains
Appendices
• Appendix A – Master Plans Provided by NHC
• Appendix B – Available Capacity of Existing Water Facilities
• Appendix C – Water System Analysis
• Appendix D – Detailed Opinions of Probable Construction Costs
Executive Summary
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 1 -
EXECUTIVE SUMMARY
This Preliminary Engineering Report (PER) was developed to evaluate the feasibility of
constructing public water and wastewater infrastructure throughout the Sidbury-Greenview area.
The project area represents significant potential growth and future development in New Hanover
County. Water and wastewater flow projections were developed by utilizing both conceptual
development plans and current zoning to determine the probable development mixture in the
project area. The probable development mixture was used to determine the required infrastructure
improvements that will be necessary to meet projected future demands.
This PER utilized County-provided master plans for known developments to create the probable
development mixture, based on land use, that would likely populate the area if sufficient public
utilities were available. The overall project area development mixture is comprised of:
• 70% Residential
• 17% Industrial
• 8% Recreational
• 5% Commercial
Hazen-Sawyer recently completed the Water Master Plan, with a flow factor of 211 GPD/REU,
which was derived from historical usage data. The historical data method for projecting water
demands was evaluated and compared to two other methods used for demand projections. The
geographical relevance and historical basis made it favorable for generating design water and
wastewater demands for the project area.
The projected water and wastewater demands for the Sidbury-Greenview area, in 10-year
increments, through year 2050 are in Table 1 and are broken down into seven service areas
detailed in TM 2.0:
Table 1 – Recommended Design Demands for Planning & Modeling Purposes
Wastewater Projected Total Flow (Build-Out) Water Projected Total Flow (Build-Out)
5.22 5.75
Recommended Design Demands for Planning & Modeling Purposes
(MGD)
2030 2040 2050 2030 2040 2050
1.04 2.09 3.13 1.15 2.30 3.44
Executive Summary
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 2 -
WASTEWATER
The general approach to provide wastewater infrastructure in the project area was based upon a
primary force main configuration. In this configuration, newly generated wastewater flow is
conveyed to the existing system. Developers intending to establish new developments in the
Sidbury-Greenview area are responsible for their own local wastewater collection system, which
would be accomplished by a combination of conventional gravity sewer and pump station with
sewer force main that manifolds into the corresponding primary sewer force main.
The primary sewer force mains and connection points to the existing system were evaluated for
strategic locations to utilize the area topography, accommodate local collection infrastructure, and
ultimately optimize the service areas for future growth. The Cape Fear Public Utility Authority
(CFPUA) would ultimately own and maintain such infrastructure. Hydraulic modeling was
conducted to determine infrastructure sizing, phasing, and hydraulic impacts.
The following recommendation for wastewater was developed based on the hydraulic modeling
results and findings. The phased implementation of the infrastructure improvements is broken
down into 10-year increments through the 30-year planning horizon. Off-site improvements to
existing infrastructure were also evaluated based on current available capacity of the facilities and
the projected demands. Cost estimates were also provided for each phased improvement as
required to meet the projected demands for the recommended system.
As detailed in TM 3.0, SA-1 will require a parallel 12-inch sewer force main when the projected
wastewater demands reach 1.12 MGD. The recommended wastewater infrastructure
improvements, with relative diameters, lengths, and costs, are shown in Figure 0.2 and are
summarized in Table 2.
Table 2 – Summary of the Wastewater Recommendation
Location Diameter Cost Per Linear Foot
SA-1
12” Single $140
12” Parallel $140
SA-2
12” $98
8” $78
Executive Summary
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 3 -
Location Diameter Cost Per Linear Foot
SA-3
SA-3
8” $78
6” $65
SA-4 8” $78
SA-5 4” $52
SA-6 12” $125
SA-7 8” $78
WATER
The hydraulic analysis performed evaluated a proposed growth for the Sidbury and Greenview
areas of 1.15 MGD every 10 years. The goal of this study was to recommend improvements to
meet the additional demand and the following goals:
• Hydraulically balance elevated storage tanks
• Ensure adequate AFF of 1,500 GPM within Sidbury and Greenview
• Maintain peak hour pressures above 40 PSI
• Maintain reasonable water age
• Provide adequate storage, pump and treatment capacity through 2050
The hydraulic analysis found that 11 main water line projects would be needed to meet the goals
above, as shown in Figure 0.1. Five of these projects are outside of the Sidbury and Greenview
area. The preliminary cost estimates for these projects are included in Table 3. Figure 0.3 shows
the recommended water system improvements with relative diameters, lengths, and costs.
The proposed 2030 water lines include a 12-inch along Castle Hayne Rd South and a 16-inch along
North College Rd. It was determined that as the average day demand along Sidbury Rd
approaches 230 GPM, the Castle Hayne Rd improvement will be needed. This will allow the full
2030 growth along Sidbury Rd to be meet. As demand approaches an additional 75 GPM on Holly
Shelter Rd, the North College Rd improvement will be needed.
Executive Summary
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 4 -
The 2030 plant capacity analysis confirmed CFPUA’s current plan of increasing Sweeney and
Richardson plant and well field capacity from 35 MGD and 6 MGD to 44 MGD and 9.6 MGD,
respectively. This analysis also determined that as demand in the future Sweeney/Richardson
zone reaches 42 MGD (80% of the WTP joined capacities), WTP expansion planning should be
initiated.
The hydraulic modeling results as shown above meet the project goals. It is, however,
recommended that the system be reevaluated as developments are built and more refined
proposed numbers are understood.
Table 3 - Water Distribution System Improvement Preliminary Cost
Year Projects Total Cost
2030
Castle Hayne Rd south: 9,280 ft – 12” $1.82 MM
Holly Shelter Rd: 15,450 ft – 12” $2.55 MM
North College RD: 9,630 ft – 16” $1.85 MM
Plantation Rd west: 18,120 ft – 12” & 780 ft – 16” $3.21 MM
Plantation Rd east: 14,600 ft – 16” $2.68 MM
Sidbury Rd west: 17,770 ft – 16” $3.51 MM
Sidbury Rd east: 20,650 ft – 12” & 1,000 ft – 16” $3.54 MM
2040
Castle Hayne Rd north: 13,970 ft – 16” $2.85 MM
Holly Shelter Rd Connection: 60 ft – 12” $47,000
Blue Clay Rd 2040: 12,340 ft – 12” $1.87 MM
2050 Blue Clay Rd 2050: 6,000 ft – 12” $1.23 MM
Total $25.16 MM
END OF EXECUTIVE SUMMARY
Technical Memorandum 1.0
Introduction & Background
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 1 -
INTRODUCTION & BACKGROUND
The purpose of this study is to evaluate the feasibility of constructing public water and
wastewater infrastructure throughout the Sidbury-Greenview area of New Hanover County. The
project area represents an area of significant potential growth and future development in New
Hanover county. The Ogden/Porters Neck area (south and east of the project boundaries) has
experienced tremendous growth in the past decade and continues to expand both residential and
commercial interests. Access to this area continues to improve with the recently completed
opening of I-140 to US 17 in Brunswick County, and the on-going Hampstead bypass that will
streamline access from Military Cut-Off to Pender County. Growth and infill continue to occur
west of I-40, which marks the western most boundary of the proposed study area (see Figure 1.1).
As the areas surrounding the project area continue to grow, it will likely create additional pressure
for growth in the Sidbury area for residential, commercial and industrial interests. Sidbury Farms
is one development that has been approved by the Technical Review Committee (TRC) and will
add 750 homes on Sidbury Road. Sidbury Farms is primarily residential and will utilize CFPUA
infrastructure for water and wastewater service. In addition to Sidbury Farms, several other large
tracts are poised for development including the Cameron Holdings (4,200 acres), Corbett Holdings
(1,265 acres), Trask Holdings (822 acres), and several other smaller tracts intended for residential
development (361 acres).
Given the development interests noted above, the study boundary is effectively surrounded by
areas of on-going growth, planned growth, and known potential growth. The purpose of the PER
is to evaluate the study area and develop a proactive and flexible/adaptive plan to accommodate
growth for a 30-year planning horizon and ultimately the buildout of the Sidbury-Greenview
Area.
GENERAL DEVELOPMENT MIXTURE
New Hanover County and Cape Fear Public Utility Authority staff provided master plans, known
development interests, population projections, and county growth rates to aid in the production of
flow projections in the project area. The project area was broken down into service areas
delineated by major road ways and property boundaries.
Based on information provided by New Hanover County (provided Appendix A), the
development mixture for Cameron Holdings is provided in Table 1 below:
Technical Memorandum 1.0
Introduction & Background
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 2 -
Table 1 – Development Mixture of Cameron Holdings
Commercial Industrial Residential Recreational
Cameron
Holdings 10% 17% 56% 17%
The Cameron Holdings development mixture was used as a basis for estimating the probable
development mixture for Corbett Holdings and the unplanned portion of Trask Holdings.
Similarly, the Sidbury Farms master plan (provided in Appendix A) was used as a basis for
estimating the probable development mixture for similar tracts with known development interest
for residential use such as:
o Charleston Lakes
o Island Creek
o Lee Hills Subdivision
o Murrayville Road
o Northern NHC Tracts
o Blanton Property
o Stephens Church Road
o Blake Tracts
o Rock Church
PRIMARY GOALS AND DRIVERS
GOALS
1. Project water and wastewater demands for 10, 20, and 30-year increments
2. Develop approach to meet water and wastewater demands for project area
3. Provide recommendations for infrastructure planning
4. Communicate findings with CFPUA staff, NHC staff, and Respective Boards (as required)
to streamline planning and coordination of project area development
DRIVERS
1. Significant development interests within the project area
2. Current lack of infrastructure within the project area is hindering development
END OF TECHNICAL MEMORANDUM
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 1 -
2.1 INTRODUCTION
The purpose of Technical Memorandum (TM) 2.0 is to provide an evaluation of demand
projections for water and wastewater needs in the Sidbury-Greenview Area in New Hanover
County. The evaluation is based on a 30-year planning period and stratified in 10-year increments
through the year 2050. Projections have been derived by utilizing data and information provided
by New Hanover County staff and Cape Fear Public Utility Authority staff.
New Hanover County and Cape Fear Public Utility Authority staff provided master plans, known
development interests, population projections, and county growth rates to aid in the production of
flow projections in the project area. The project area was broken down into service areas
delineated by major road ways and property boundaries. Table 1 summarizes the projected land
use and developable acreage for each service area (Figure 3.1).
Table 1 – Sidbury-Greenview Area Developable Acreage and Potential Land Use
Service Area Zone Developable Acres Land Use (%)
1 880 100% Residential
2 1,920
60% Residential
19% Recreational
16% Commercial
5% Industrial
3 2,040
70% Residential
14% Industrial
13% Recreational
3% Commercial
4 1,180
79% Residential
8% Recreational
7% Industrial
6% Commercial
5 1,170 100% Residential
6 1,510 77% Industrial
19% Residential
4% Recreational
7 730 93% Residential
7% Commercial
Total Developable Acreage 9,430 Acres
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 2 -
The probable land use composition for the entire project area is as follows:
• 69% Residential
• 17% Industrial
• 8% Recreational
• 6% Commercial
Further, the information provides descriptions of land uses in the service areas with relative
acreages and unit counts. This information was used to project probable land use composition for
surrounding areas with similar plans for development. Table 2 shows the flow factors assigned to
each land use description.
Table 2 – Sidbury-Greenview Area Land Use Descriptions and Assigned Flow Factors for Water
and Wastewater
Land Use Description
*Wastewater Flow
Factor Assigned
(GPD/Unit)
**Water Flow
Factor Assigned
(GPD/Unit)
Units
Office/Flex Space/Technology Hub 25 28 Employees/shift
Medical campus with a variety of
medical office, research, and
ambulatory care facilities
880 978 Acre
Residential/Independent Living
Amenity 50 56 100 SF
Parks 250 278 Plumbing
Fixture
Single Family/Multi
Family/Independent Living 360 400 Residence
Age-in-place community including
assisted living and skilled nursing
facility
880 978 Acre
Neighborhood Commercial
with Grocery and other
Neighborhood Services with
Restaurants
130 144 1000 SF
Retail/Office 100 111 1,000 SF
Sports Facilities 50 56 100 SF
Regional Commercial Center 130 144 1,000 SF
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 3 -
Baseball Stadium surrounded by
condominiums over retail on first
floor
880 978 Acre
Light Industrial 880 978 Acre
*The wastewater flow factors and units in Table 2 were taken from 15A NCAC 02T .0114 WASTEWATER
DESIGN FLOW RATES. Proposed non-residential developments where the specific types of use and
occupancy are unknown are given a design flow factor of 880 gallons per acre, as recommended in 15A
NCAC 02T .0114 WASTEWATER DESIGN FLOW RATES.
**The water flow factors in Table 2 were developed by converting each land use into residential equivalent
units based on 15A NCAC 18C .0409 SERVICE CONNECTIONS Daily Flow Requirements.
The projected water and wastewater needs within the project area are anticipated to be generated
mainly from the following major tracts:
1. Cameron Holdings
2. Corbett Holdings
3. Trask Holdings
4. Sidbury Farms
5. Residential Tracts of Interest
6. Other Large Developable Tracts
The “Residential Tracts of Interest” (No. 5 above) are areas that will be developed as residential
communities in various location throughout the project corridor and are assumed to have density,
composition, and features similar to Sidbury Farms. The residential tracts of interest are
geographically depicted in Figure 2.1. Table 3 is a list of the residential tracts of interest with
relative acreages:
Table 3 – Residential Tracts of Interest
Name Developable Acreage
Hanover Reserve 80
Charleston Lakes 60
Island Creek 130
Lee Hills Subdivision 90
Northern NHC Tracts 200
Blanton Property 30
4908 Blue Clay Road 20
The Walk at Porters Neck 70
Yvonne Road 20
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 4 -
Name Developable Acreage
Wild Magnolia 10
Murrayville Road 70
Stephens Church Road 20
Blake Tracts 60
Total Developable Acreage 860
“Other Large Developable Tracts” (No. 6 above) are areas that can be developed depending on
their zoning designation. The large developable tracts are geographically depicted in Figure 2.1.
Table 4 is a list of the large developable tracts with relative acreages.
Table 4 – Other Large Developable Tracts and Relative Developable Acreages
Name Developable Acreage
Hanpin Land Co. 120
Seagreen LLC Tracts 410
Elementis Chromium 330
Martin Marrietta Materials 410
Skipper Properties 100
Hynda Dalton Tract 260
Total Developable Acreage 1,630
Table 5 shows the likely development mixtures of the major tracts of land based on current zoning
and the concept plans provided by New Hanover County Planning Department for Cameron
Holdings, Trask Holdings, and Sidbury Farms.
Table 5 – Potential Development Mixtures of Major Tracts of Land Within the Project Corridor
Land Use Cameron
Holdings
Corbett
Holdings
Trask
Holdings
Sidbury
Farms
Residential
Tracts of
Interest
Other Large
Developable
Tracts
Commercial 290 110 60 0 0 0
Industrial 550 170 90 0 0 830
Residential 1,620 540 450 310 940 800
Recreational 500 190 100 0 0 0
Total 2960 1,010 700 310 940 1,630
Total Developable Acreage = 7,550 acres
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 5 -
NCDEQ Demand projections presented herein for water and wastewater needs are based on the
data provided in Tables 1, 2, 3, 4, and 5 of this TM.
2.2 NCDEQ WASTEWATER DEMAND PROJECTIONS
Total Build-Out NCDEQ demand projections are shown in the following Table 6.
Table 6 – NCDEQ Wastewater Flow Projections Designated by Drainage Zones and Land Use
(MGD)
Service Area
Zone
Commercial
Demand
Industrial
Demand
Residential
Demand
Recreational
Demand
Build-Out
Demand
1 - - 1.14 - 1.14
2 0.59 0.20 2.19 0.70 3.68
3 0.05 0.36 1.73 0.33 2.46
4 0.09 0.13 1.39 0.15 1.75
5 - - 0.88
- 0.88
6 - 1.50
..5
0.38 0.07 1.96
7 0.11 - 1.36 - 1.47
Total Demand = 13.3 MGD
13.91
Table 7 provides a uniform projection of demands over the 30-year project planning period within
the project area. Based on information provided by New Hanover County Planning Department,
the ultimate build-out for the area will occur in 2070.
Table 7 - Projected Incremental Total Flow for NCDEQ Wastewater Demands
Service Area Zone 2030 2040 2050
1 0.22 0.46 0.68
2 0.74 1.47 2.21
3 0.49 0.99 1.48
4 0.35 0.70 1.05
5 0.18 0.35 0.53
6 0.39 0.78 1.17
7 0.29 0.59 0.88
Totals 2.67 MGD 5.34 MGD 8.00 MGD
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 6 -
2.3 NCDEQ WATER DEMAND PROJECTIONS
Total Build-Out demand projections are shown in the following Table 8 for water.
Table 8 – NCDEQ Drinking Water Flow Projections Designated by Service Area and Land Use
Service Area
Zone
Commercial
Demand
Industrial
Demand
Residential
Demand
Recreational
Demand
Total
Demand
1 - - 1.27 - 1.27
2 0.65 0.22 2.44 0.77 4.08
3 0.05 0.40 1.92 0.36 2.74
4 0.09 0.14 1.55 0.16 1.95
5 - - 1.0 - 1.0
6 - 1.67 0.42 0.08 2.17
7 0.12 - 1.51 - 1.64
Total MGD 0.91 2.43 10.1 1.38 14.85 MGD
Table 9 provides a uniform projection of demands over the 30-year project planning period within
the project corridor. Based on information provided by New Hanover County Planning
Department, the ultimate buildout for the area would occur by 2070.
Table 9 – NCDEQ Projected Incremental Total Flow for Drinking Water Demands
Service Area Zone 2030 2040 2050
1 0.25
0.51
0.76
2 0.82 1.63 2.45
3 0.55 1.09 1.64
4 0.39 0.78 1.17
5 0.20 0.39 0.59
6 0.44 0.87 1.30
7 0.33 0.65 0.98
Totals (MGD) 2.53 5.92 8.89
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 7 -
2.4 WATER AND WASTEWATER PROJECTION ALTERNATIVES
Two additional methods were used to develop water and wastewater projections:
1. Metcalf & Eddy Method
2. Historical Data Method
METCALF & EDDY METHOD
The Metcalf & Eddy method is a per capita approach used to develop water demand projections.
A flow factor of 70 GPDc is used for water. Wastewater projections are based on 90% recovery and
2.49 persons per household. Table 10 shows the incremental water and wastewater projections for
the Metcalf & Eddy method.
Table 10 - Metcalf & Eddy Method - Incremental Water and Wastewater Projections (MGD)
Years Total Water Demand (MGD) 90% Recovery Wastewater
(MGD) 2030 1.0 0.9
2040 2.0 1.8
2050 2.9 2.6
HISTORICAL DATA METHOD
The Historical Data method is based on information provided in the Hazen-Sawyer Northern
Water Mains Master Plan. A flow factor of 211 GPD/REU was derived from historical usage data
and used for water projections. Wastewater projections are based on 90% recovery of the 211
GPD/REU. Table 11 shows the incremental water and wastewater projections for the Historical
Data method:
Table 11 - Historical Data Method - Incremental Water and Wastewater Projections (MGD)
Years Total GPD Water (MGD) 90% Recovery Wastewater (MGD)
2030 1.2 1.1
2040 2.3 2.1
2050 3.5 3.2
Build-Out 6.0 5.4
The water and wastewater projections presented in Graphs 1 and 2 as follows:
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 8 -
Graph 1 – Water Projections Comparison: Metcalf & Eddy, Historical Data, NCDEQ Flow
Factors
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 9 -
Graph 2 – Water Projections Comparison: Metcalf & Eddy, Historical Data, NCDEQ Flow
Factors
2.5 SUMMARY AND CONCLUSIONS
The NCDEQ method for projecting water and wastewater needs is required when permitting
flows but does not always accurately reflect the actual flows measured. As seen in Graphs 1 and 2,
this method results in high projections that may not accurately represent the actual flows that
would be measured in the project area; therefore, the NCDEQ method is not recommended for
infrastructure planning purposes.
The Metcalf & Eddy method utilizes the per capita approach to produce water and wastewater
planning projections and is a comparative benchmark. When compared to the Historical Data
method, Graphs 1 and 2 show that the Metcalf & Eddy method projections are slightly lower.
Technical Memorandum 2.0
Demand Projections
Sidbury-Greenview Area Water and Sewer Utilities
Preliminary Engineering Report - 10 -
The Historical Data method is based on real data gathered from areas surrounding the project
corridor. The data was used to project the probable flows that will be seen within the Sidbury-
Greenview Area. Graphs 1 and 2 show that the Historical Data method projections are slightly
higher than the Metcalf & Eddy method and substantially lower than the NCDEQ method. The
Historical Data method is favorable for generating design water demands and wastewater
demands for the project area due to its geographical relevance, historical basis, and the
conservative and comparative results shown in Graphs 1 and 2.
Based on the information presented in the TM, it is recommended that the CFPUA and New
Hanover County plan infrastructure improvements for the Sidbury-Greenview corridor based on
the demands as summarized in the Table 12 below:
Table 12 – Summary of Projected Wastewater and Water Demands (MGD)
Wastewater Projected Total Flow (Build-Out) Water Projected Total Flow (Build-Out)
5.22 5.75
Recommended Design Demands for Planning & Modeling Purposes
(MGD)
2030 2040 2050 2030 2040 2050
1.04 2.09 3.13 1.15 2.30 3.44
END OF TECHNICAL MEMORANDUM
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 1 -
3.1 INTRODUCTION
Technical Memorandum 3.0 (TM 3.0) provides a basic approach to infrastructure planning and
location. General concepts for wastewater infrastructure collection and conveyance as well as
water infrastructure to include storage and distribution system mains are identified and provided
in a graphical format.
3.2 WASTEWATER EXISTING FACILITIES
The Sidbury-Greenview area has been broken into seven service area (SA) zones based on major
highways, interstates and large parcel boundaries. The wastewater flow generated from each
service area will be collected and conveyed through primary force mains along major roads,
allowing developers to tie-in to the system at centralized locations as development progresses.
Based on review of available CFPUA information, the following public utility infrastructure exists
around the Sidbury-Greenview area. See Figure 3.1 for a geographical depiction of the
surrounding wastewater infrastructure.
o RPS1 Outfall
o RPS1
o College Road Force Main
o Blue Clay Road Force Main
o Laney Outfall to Smith
Creek Pump Station 89
o Country Haven Pump
Station 95
o Kirkland Pump Station 135
Table 1 shows the current available pumping capacity of existing wastewater infrastructure.
Table 1 – Current Available Capacity of Existing CFPUA Wastewater Infrastructure Surrounding
Sidbury-Greenview Area (GPD)
Name Available Capacity (GPD)
RPS1 292,000
Country Haven (PS 95) 265,000
Kirkland (PS 135) 69,000
Smith Creek (PS 89) 567,000****
**** Based on diverting 317,000 GPD from PS 77 to PS 35 and flow from RPS1 to Blue Clay Rd FM.
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 2 -
Preliminary routing of the proposed infrastructure was included as part of this evaluation.
However, a more detailed analysis would be required as part of detailed design to ascertain a
more definitive location of utilities and incorporate into design of infrastructure construction in
the project corridor.
3.3 WASTEWATER CORRIDOR PLANNING APPROACH
The general approach to provide wastewater infrastructure in the corridor was based upon a
primary force main configuration, whereby newly generated wastewater flow would be conveyed
to the existing system. Developers intending to establish new developments in the Sidbury-
Greenview area are responsible for their own local wastewater collection system. This would be
accomplished by a combination of conventional gravity sewer and pump station with sewer force
main that would manifold into the corresponding primary sewer force main. Developers would
also be responsible for constructing a section of primary sewer force main to connect their local
wastewater collection system to the existing infrastructure or paying into a cost sharing agreement
for off-site infrastructure that is already in place. The primary sewer force mains and connection
points to the existing system were evaluated for strategic locations to utilize the area topography,
accommodate local collection infrastructure, and ultimately optimize the service areas for future
growth. For conveyance to the existing CFPUA wastewater system, five primary force mains and
five primary connection points to the existing system were identified as feasible to accommodate
the projected wastewater flows generated in the project area through year 2050 (see Figure 3.3):
3.4 WASTEWATER COLLECTION AND CONVEYANCE
Each primary force main and connection point to the existing system are described in detail in as
follows:
Sidbury Road Force Main
The Sidbury Road FM would convey flows generated from SA-1, SA-2, and the northern portion
of SA-3. DR Horton’s new residential development, Sidbury Farms, will generate the initial
wastewater flow for SA-1. This development is currently under design and will provide
approximately 14,000 LF of 12-inch sewer FM connecting the new development to the existing
system through Blue Clay Road Force Main Connection (See below). The 14,000 LF of 12-inch
force main is considered the “Initial Phase” of the Sidbury Road Force Main, stimulating interest
for future development in the area. The “Future Phase” of the Sidbury Road Force Main is an
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 3 -
extension of the 12-inch FM down Sidbury Road to handle wastewater flow from the future
development of the Cameron and Corbett Holdings and an 8-inch FM to serve Lee Hills
Subdivision and other development interests east of the Future Hampstead Bypass. See Figures
3.3, 3.4, 3.5, 3.6 for a geographic depiction of the proposed Sidbury Road Force Main phasing and
known development interests.
Blue Clay Road Force Main Connection
Blue Clay Road FM intersects the N College Road FM in northern New Hanover County and
conveys wastewater to NSWWTP. Initial investigation of this connection point yielded the
following:
• Blue Clay Road FM is the most feasible connection point for SA-1, 2, and the northern
portion of SA-3.
• The Blue Clay Road FM has sufficient capacity to accommodate the projected demands
until 2035 but when demand reaches 1 MGD of average daily flow, it would require a
parallel force main to NSWWTP to meet the total projected 2050 demands.
• A crossing of I-40 would be required via horizontal directional drill and is estimated at
approximately 1,800 feet in length.
Stephens Church Road Force Main
The Stephens Church Road force main would convey wastewater flow generated from the eastern
portion of SA-3 to the existing Stephens Church Road gravity sewer outfall (See below).
Development in the eastern portion of SA-3 can be served by a 6-inch sewer force main. Based on
projected demands, the downstream pump station (Kirkland PS-135) reaches capacity in 2030
(69,000 GPD). At this point, any future development would send flow North towards the Sibury
Road force main.
Stephens Church Road Outfall
Stephens Church Road Outfall is a gravity sewer system near the intersection of Stephens Church
Road and Market Street. The gravity sewer conveys wastewater to Kirkland PS 135. Initial
investigation of this connection point yielded the following:
• Kirkland PS 135 has sufficient capacity to serve flow generated in this service area through
year 2030 (69,000 GPD).
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 4 -
• Gravity sewer connecting Stephens Church Road Outfall to PS 135 appears to have
sufficient capacity to convey these projected flows.
• After the flow surpasses the current available capacity at Kirkland PS 135 (69,000 GPD),
additional flow would be sent North to the Sidbury Road force main.
Plantation Road Force Main - West
The Plantation Road FM - West would convey wastewater flow generated from SA-4 and connect
to the existing system through Laney Outfall (See below). Based on the projected demands, SA-4
can be served by an 8-inch sewer force main through year 2050.
Laney Outfall
Laney Outfall is a major gravity sewer outfall near Murrayville Road and Olsen Park. The gravity
sewer conveys wastewater to Smith Creek Pump Station, which ultimately is treated at NSWWTP.
Initial investigation of this connection point yielded the following:
• Gravity sewer connecting Laney Outfall to PS 89 appears to have sufficient capacity to
collect 2050 projected demands generated by SA-4 without improvements.
• If flow from PS 77 is permanently diverted, then PS 89 would require an upgrade in 2045
based on the projected flows (336,100 GPD) and the current available capacity at the
station.
• If flow from PS 77 is sent to PS 89, then PS 89 will require an upgrade in 2025 based on the
projected flows (67,150 GPD) and the current available capacity at the station.
Plantation Road Force Main – East
Plantation Road FM - East shall convey wastewater flow generated from SA-5 and connect to the
existing system through Country Haven Outfall (see below). Based on the projected demands, SA-
5 can be served by a 4-inch sewer force main through year 2050.
Country Haven Outfall
Country Haven Outfall is a gravity sewer system in the Country Haven neighborhood in
northeastern New Hanover County. Country Haven Outfall conveys waste water to Country
Haven PS 95. Initial investigation of this connection point yielded the following:
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 5 -
• Gravity sewer connecting Country Haven Outfall and PS 95 appears to have sufficient
capacity to collect and convey 2050 projected demands generated by SA-5 without
improvements.
• Country Haven PS 95 has sufficient capacity to convey wastewater flow through year 2050
without additional improvements.
Holly Shelter Road Force Main
The Holly Shelter Road FM would convey wastewater flow generated from SA-6 and SA-7 and
connect to the existing system through the RPS1 Outfall (See below). SA-6 and SA-7 wastewater
flows are expected to be served by 12-inch and 8-inch sewer force mains, respectively, through
year 2050.
RPS1 Outfall
The RPS1 Outfall is located to the North of RPS1 and conveys waste water to RPS1. A portion of
the RPS1 is 24” and the connection from Holly Shelter Road force main would drop into the 24”
gravity. Initial investigation of this connection point yielded the following:
• Gravity sewer connecting RPS1 Outfall to RPS1 has sufficient capacity to collect and
convey 2050 projected demands (775,200 GPD) generated by SA-6 and SA-7 without
improvements.
• RPS1 is projected to exceed its capacity to convey wastewater flow in year 2035 (387,600
GPD) and will require a pump station and force main upgrade to serve the area based on
projected demands.
• A crossing of I-40 would be required via horizontal directional drill and is estimated at
approximately 1,800 feet in length.
3.5 WATER EXISTING FACILITIES
For a geographic depiction of the existing water infrastructure surrounding the project area, see
Figure 3.2.
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 6 -
3.6 WATER CORRIDOR PLANNING APPROACH
The proposed water mains were divided into 11 individual projects, based on the location and
project year: 2030, 2040, or 2050. Developers intending to establish new developments in the
Sidbury-Greenview area are responsible for their own local water distribution system. This would
be accomplished by a combination of water service lines and water mains that would manifold
into the corresponding primary water transmission main. Developers would also be responsible
for constructing a section of primary water transmission main to connect their local water
distribution system to the existing infrastructure or paying into a cost sharing agreement for off-
site infrastructure that is already in place.. Route evaluation included a detailed review of
locations requiring trenchless installation, areas containing wetlands, locations presenting
environmental impacts during construction, boundaries of public rights-of-way to minimize
easements, and sites containing hazardous materials. Water lines not within public right of ways
will require private property easements. This section of the report describes each of the 11
proposed projects. Figure 3.7 identifies the proposed routes.
3.7 PROPOSED WATER TRANSMISSION ROUTING - 2030
Castle Hayne Road South
The Castle Hayne Road South 2030 proposed 12-inch water main begins near the Sweeney Water
Treatment Plant (WTP), parallel to Cornelius Harnett Road heading north to Castle Hayne Road,
crossing under the Cape Fear River. The water main continues north parallel to Castle Hayne
Road ending at the intersection of Hanover Lakes Drive and Castle Hayne Road. The total length
of 12-inch water main is approximately 9,280 linear feet. The route requires a total of six trenchless
crossings: five bore and jack trenchless crossings under Arlington Drive, Yorktown Drive, Victoria
Drive, Glendale Drive, and Brentwood Drive, and one horizontal directional drill (HDD)
trenchless crossing under the Cape Fear River. Figure 3.8 depicts the Castle Hayne Road South
2030 proposed route.
North College Road
The North College Road 2030 proposed 16-inch water main starts at the Holly Shelter School Tank
near Roger Haynes Drive. From the water tower, the water main heads west following a parcel
boundary before turning south paralleling an existing powerline easement to North College Road.
The water main continues south along North College Road and ends at the intersection of
Huntsman Court and North College Road. The total length of 16-inch water main is
approximately 9,630 linear feet. The route requires a total of two bore and jack trenchless
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 7 -
crossings: one under North College Road as well as one under Parmele Road. Figure 3.9 depicts
the North College Road 2030 proposed route.
Holly Shelter Road 2030
The Holly Shelter Road 2030 proposed 12-inch water main starts at the corner of Barbados
Boulevard and then crosses Holly Shelter Road, turning east. The route continues along Holly
Shelter Road past the intersection of Ideal Cement Road ending before the road bends and
changes to Island Creek Road. The total length of 12-inch water main is approximately 15,450
linear feet. The route requires a total of four trenchless crossings: three bore and jack trenchless
crossings under Holly Shelter Road, Diamond Shamrock Road, and Ideal Cement Road, and one
HDD trenchless crossing under a stream. Figure 3.10 depicts the Holly Shelter Road 2030
proposed route.
Sidbury Road West
The Sidbury Road West 2030 proposed 16-inch water main starts at the intersection of Blue Clay
Road and Sidbury Road. The route continues east along Sidbury Road until it ends before the
intersection of Crooked Pine Road and Sidbury Road. The total length of 16-inch water main is
approximately 17,770 linear feet. The route requires a total of four bore and jack trenchless
crossings: under I-40, Old Dairy Farm Road, Buck Drive, and Edna Buck Road. Figure 3.11 depicts
the Sidbury Road West 2030 proposed route.
Sidbury Road East
The Sidbury Road East 2030 proposed 12-inch starts at the end of the Sidbury Road West 2030
route near the intersection of Crooked Pine Road and Sidbury Road. The route heads east along
Sidbury Road where it turns south to Farm Road. The route follows Farm Road for approximately
4,000 linear feet before crossing many private parcels prior to ending at Market Street near Scotts
Hill Medial Drive. Easements will be required for most of the route as shown, or the route can
follow new public streets as development occurs. The total length of 12-inch water main is
approximately 20,650 linear feet with 1,000 linear feet of 16-inch water main at the future Military
Cutoff Hampstead Bypass. The route requires a total of four bore and jack trenchless crossings:
under Island Creek Drive, the Military Cutoff Hampstead Bypass, Farm Road, and Market Street.
Figure 3.12 depicts the Sidbury Road East 2030 proposed route.
Plantation Road West
The Plantation Road West 2030 proposed 12-inch water main starts at the intersection of North
College Road and Southeast Northchase Parkway. The route crosses North College Road and then
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 8 -
continues east along Southeast Northchase Parkway to the end of the road where it then crosses a
commercial parcel. The route continues east across I-40 through several parcels to Plantation
Road, then east along Plantation Road ending 2,000 linear feet after the intersection of the Military
Cutoff Hampstead Bypass and Plantation Road. Easement will likely be required for the segments
of the route along private properties. The total length of 12-inch water main is approximately
18,120 linear feet of 12-inch water main with 780 linear feet of 16-inch water main at the I-40 and
future Military Cutoff Hampstead Bypass crossings. The route requires three bore and jack
trenchless crossings: under North College Road, I-40, and the Military Cutoff Bypass. Figure 3.13
depicts the Plantation Road West 2030 proposed route.
Plantation Road East
The Plantation Road East 2030 proposed 16-inch water main starts at the Richardson WTP heading
north to Plantation Road, then east to Market Street. The total length of proposed water main is
approximately 14,600 feet of 16-inch PVC. Figure 3.12 depicts the Plantation Road West 2030
proposed route.
3.8 PROPOSED WATER TRANSMISSION ROUTING - 2040
Castle Hayne Road North
The majority of the Castle Hayne Road North proposed route is projected for 2040; however, there
is a small percentage of the route proposed for 2030. For simplicity, the entire segment of pipe
along the Castle Hayne Road North proposed route is grouped as one project in 2040. The route
starts at the northeast corner of the Holly Shelter Road and Castle Hayne Road intersection and
then crosses Castle Hayne Road where it turns south. The route continues along Castle Hayne
Road on the west side of the road. After the roundabout with Garden Place Drive and North
College Road, the route crosses Castle Hayne Road and continues along the east side of the road
until it ends after crossing Hermitage Road. The total length of proposed 16-inch water main is
approximately 13,970 linear feet. The route requires a total of nine trenchless crossings: eight bore
and jack trenchless crossings under Castle Hayne Road at the intersection with Holly Shelter
Road, Prince George Avenue, Garden Place Drive, Castle Hayne Road where the proposed water
main crosses from the west side to the east side of the road, Parmele Road, Crowatan Road, Goff
Drive, and Hermitage Road, and one HDD trenchless crossing under a stream. Figure 3.15 depicts
the Castle Hayne Road North 2040 proposed route.
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 9 -
Holly Shelter Road 2040 Connection
The proposed Holly Shelter Road 2040 Connection includes 60 linear feet of a bore and jack
trenchless crossing under Holly Shelter Road approximately 1,000 linear feet east of Diamond
Shamrock Road. This proposed pipe segment will connect the existing water main to the proposed
Holly Shelter Road 2030 water main. Figure 3.16 depicts the Holly Shelter Road 2040 Connection.
Blue Clay Road 2040
The Blue Clay Road 2040 proposed 12-inch water main starts at a connection to the existing water
main at the corner of Juvenile Center Road and Blue Clay Road. The route continues southwest
along Blue Clay Road and ends at a connection with the existing water main north of North Kerr
Avenue. The total length of proposed 12-inch water main is approximately 12,340 linear feet. The
route requires three bore and jack trenchless crossings: under I-140, the railroad crossing, and Old
Mill Road. Figure 3.17 depicts the Blue Clay Road 2040 proposed route.
3.9 PROPOSED WATER TRANSMISSION ROUTING - 2050
Blue Clay Road 2050
The Blue Clay Road 2050 proposed 12-inch water main starts at the end of the Blue Clay Road
2040 proposed route. The route continues south along Blue Clay Road and parallel with the
railroad. The route ends at a connection to the existing water main near the intersection of Hall
Drive and Blue Clay Road. The total length of proposed 12-inch water main is approximately 6,000
linear feet. The route requires one bore and jack trenchless crossing under North Kerr Avenue.
Figure 3.18 depicts the Blue Clay Road 2050 proposed route.
3.10 STORAGE CAPACITY EVALUATION
Water storage is required for equalizing demand, providing fire protection and supplying the
system in an emergency. Equalizing storage allows water to be supplied from the water
production facilities at a rate equal to the average demand for the day. Fire storage ensures water
is available for the defined duration while production sources and pump stations supply the
projected maximum day demand. Emergency storage is used during pipe breaks, equipment
failures, power outages, contamination of raw water supplies, or natural disasters that disrupt
normal service.
Storage requirements were evaluated for the CFPUA distribution system using two criteria. The
Technical Memorandum 3.0
Planning Approach & Routing Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 10 -
first criterion is that the storage capacity should exceed the combined storage requirements for
firefighting and equalizing. For firefighting, a maximum required fire flow of 3,500 GPM with a
duration of three hours was assumed (per American Water Works Association Manual M31),
which corresponds to a fire storage volume of 0.63 MG. For equalization, sufficient storage volume
is required to allow the system to supply diurnally varying demand on a maximum demand day
while supply is pumped into the system at a constant rate. Equalization requirements are
normally expressed as a percentage of maximum day demand and depend on the extent to which
demand varies diurnally. The second criterion is defined by the North Carolina Department of
Environmental Quality (NCDEQ). Storage in the system should exceed half the demand for an
average day. Emergency storage can include distributed storage (e.g., elevated in the distribution
system) and clearwell storage.
END OF TECHNICAL MEMORANDUM
Technical Memorandum 4.0
Hydraulic Modeling Methodology & Results
Sidbury-Greenview Area
Preliminary Engineering Report - 1 -
4.1 INTRODUCTION
Technical Memorandum 4.0 (TM 4.0) provides detailed information related to hydraulic modeling
of water and wastewater systems in the project area and surrounding areas. The hydraulic
modeling results include sizing of facilities, resultant hydraulic impacts, and collection and
conveyance sizing for projected demands. The water system modeling also includes data related
to water age.
4.2 WASTEWATER HYDRAULIC MODELING METHODOLOGY
The hydraulic approach is based on the 30-year projections for ultimate system configuration and
phased in 10-year increments.
The wastewater flow projections were developed using the methodology detailed in TM 2.0 of this
preliminary engineering report and are summarized in Table 4.1 as follows, for each service area:
Table 4.1 – Wastewater flow projection of the Sidbury-Greenview Area for a 30-year planning
horizon, designated by service area (GPD).
Modeling Assumptions
The following modeling assumptions were made:
1. Topography: Pipe elevations are set to equal to the ground elevation minus three feet of
cover.
2. Friction Loss: Pipe material is PVC (Hazen Williams Coefficient = 130)
Year SA-1 SA-2 SA-3 SA-4 SA-5 SA-6 SA-7
2030 117,200 279,300 200,200 134,400 43,500 147,500 110,900
2040 234,400 558,600 400,300 268,900 87,100 295,000 221,800
2050 351,500 837,900 600,500 403,300 130,600 442,500 332,700
Technical Memorandum 4.0
Hydraulic Modeling Methodology & Results
Sidbury-Greenview Area
Preliminary Engineering Report - 2 -
4.3 WASTEWATER MODELING RESULTS
Utilizing the suggested alternative configuration, hydraulic modeling was conducted to determine
viable pipe diameters required to meet the projected demands for the project area through 2050.
Table 4.2 provides the hydraulic modeling results of the proposed primary force mains to serve
the Sidbury-Greenview area through 2050.
Table 4.2 – Hydraulic Results of Proposed Primary Force Mains 2050
Force Main Pipe Segment Pipe Diameter
Evaluated
Flow Rate Maximum
Velocity
Blue Clay Road Outfall to Sidbury
Farms
12” Single 1,380 GPM 4.0 FPS
12” Parallel 1,380 GPM 4.0 FPS
Sidbury Farms to Island Creek
Subdivision 12” 2,140 GPM 6.0 FPS
Island Creek Subdivision to Lee Hills
Subdivision 8” 720 GPM 4.6 FPS
Stephens Church Road Force Main 6” 360 GPM 4.0 FPS
Plantation Road Force Main - West 8” 760 GPM 4.8 FPS
Plantation Road Force Main - East 4” 230 GPM 5.8 FPS
Holly Shelter Road Force Main -
West 12” 1,350 GPM 3.8 FPS
Holly Shelter Road Force Main - East 8” 580 GPM 3.7 FPS
The pipe diameters in Table 4.2 meet the criteria for minimum velocity of 2 feet per second and are
within the pressure rating of the CFPUA standard C900 DR 18 (235 psi).
4.4 WATER HYDRAULIC MODELING METHODOLOGY
Hazen performed the modeling analysis utilizing the calibrated master plan model. The demands
in the model were updated to reflect the 2019 production rate of 19.33 MGD.
Technical Memorandum 4.0
Hydraulic Modeling Methodology & Results
Sidbury-Greenview Area
Preliminary Engineering Report - 3 -
Demand growth and future demand projections were broken down into different user categories
for use in the hydraulic model as shown in Table 4.3. The domestic growth numbers included
residential, commercial, institutional, large users, and irrigation. 2016 industrial demand is
included in large user demand, but future industrial demand (summarized in Table 4.4) is shown
in a new category. A new demand category was also created for bulk customers and potential
expansion areas that CFPUA expects to add by 2050. Those customers are summarized in Table
4.5.
The Sidbury and Greenview Area are projected to grow by 1.15 MGD every 10 years. Water
quality flushing demand is expected to decrease due to operational improvements and overall
growth. The total average day demand by 2050 is 28.90 MGD with a maximum day demand of
47.35 MGD.
Table 4.3 – Estimated Future Demand by Category
Demand
Category
2019 Average
Day Demand
(MGD)
2030 Average
Day Demand
(MGD)
2040 Average
Day Demand
(MGD)
2050 Average
Day Demand
(MGD)
Domestic 11.86 17.59 19.25 20.94
Large Users 1.31 1.31 1.31 1.31
Industry 0.00 0.43 0.82 0.82
Bulk Customers
and Potential
Expansion Areas
0.00 1.56 1.56 1.56
Sidbury Growth 0.00 1.15 2.30 3.44
Non-Revenue
Water (including
flushing)
1.99 0.71 0.73 0.82
Total 19.33 22.75 25.97 28.90
Table 4.4 – Estimated Industrial Demand Growth from Current Day to 2040
Industrial User(s) Average Day Demand (gpd)
Elementis Chromium (growth demand) 71,000
GE (new customer) 78,000
Highway 421 Corridor (new customer) 676,000
Total 825,000
Technical Memorandum 4.0
Hydraulic Modeling Methodology & Results
Sidbury-Greenview Area
Preliminary Engineering Report - 4 -
Table 4.5 – Estimated 2040 Demands from Bulk Customers and Potential Expansion Areas
Bulk Customer Average Day Demand (gpd)
Figure 8 Island 500,000
Middle Sound 99,000
Bayshore Area 102,000
Treasure Cove 64,000
Wrightsville Beach* 800,000
Total 1,565,000
* Based on current 12-hour supply of 1.59 MGD (from Wrightsville Beach PER)
Water System Assessment – with Sidbury and Greenview Demands
After the hydraulic model demand was updated, it was used to assess future conditions in the
CFPUA system with the Sidbury and Greenview demands. Storage, pumping capacity, tank
performance, available fire flow, peak hour pressure and water age were evaluated. The modeling
analysis assumed that the Monterey Heights Boundaries would be moved, so that the Tarin
Woods and Congleton developments would be served by the Sweeney Zone. The 2030 analysis
maintained the three pressure zones. However, it was assumed that by 2040 the Sweeney and
Richardson Zone would be merged. The assessment focused mainly on the CFPUA system north
of the 17th Street Tank.
4.5 WATER MODELING RESULTS
CFPUA currently has a total ground storage capacity of 18 million gallons (MG) and a total
elevated storage capacity of 8.90 MG. Storage requirements are calculated and compared to
existing storage capacity in Tables 4.6 through 4.8.
Fire flow and equalization storage are analyzed separately for each zone for 2030 because the
zones are isolated from each other. To improve water age the Wrightsboro Tank can be
temporarily removed in 2030 without effecting the Sweeney storage capacity. The Sweeney,
Richardson and Monterey Heights zones each have a storage surplus of approximately 0.13 MG,
0.66 MG and 0.08 MG respectively.
For 2040 and 2050 the fire flow and equalization storage were calculated for the combined
Sweeney/Richardson Zone and for Monterey Heights. The Wrightsboro Tank will need to be
returned to service when maximum day demands exceed 42.5 MGD. Therefore, the 2040 analysis
was done with the tank left offline, to continue to provide better water quality in the surrounding
Technical Memorandum 4.0
Hydraulic Modeling Methodology & Results
Sidbury-Greenview Area
Preliminary Engineering Report - 5 -
area. The Sweeney/Richardson and Monterey Heights zones 2040 storage surplus capacity of
approximately 0.22 MG and 0.07 MG, respectively.
When maximum day demand approaches 45.5 MGD in the Sweeney/Richardson Zone, new
storage should be evaluated. As the maximum day demand by 2050 is projected to be 46 MGD, the
storage capacity in Sweeney/Richardson Zone is deficient by 0.06 MG.
Emergency storage is analyzed globally across the three zones, because the zones can be
interconnected in case of emergency. CFPUA requested that the evaluated emergency storage
capacity be based on 75% of average day demand, which is more stringent than the DEQ
requirement. The Dawson and Porters Neck Plantation tanks were not included in the emergency
storage as they are booster pump stations. Due to the large capacity of the Sweeney WTP
clearwell, the combined system has an emergency storage excess in 2030, 2040 and 2050 of 7.04
MG. 4.62 MG, and 2.95 MG, respectively.
Table 4.6 – Comparison of Required and Existing Elevated Storage – 2030
Sweeney Richardson Monterey Heights
Required Elevated Storage
(Equalizing + Fire Storage) (MG) 5.87 1.24 0.42
Total existing capacity 6.00 1.90 0.50
Excess (or deficit) capacity (MG) 0.13 0.66 0.08
Table 4.7 – Comparison of Required and Existing Elevated Storage - 2040
Sweeney/ Richardson Monterey Heights
Required Elevated Storage
(Equalizing + Fire Storage) (MG) 7.68 0.43
Total existing capacity 7.90 0.50
Excess (or deficit) capacity (MG) 0.22 0.07
Table 4.8 – Comparison of Required and Existing Elevated Storage – 2050
Sweeney/ Richardson Monterey Heights
Required Elevated Storage
(Equalizing + Fire Storage) (MG) 8.46 0.44
Total existing capacity 8.40 0.50
Excess (or deficit) capacity (MG) (0.06) 0.06
Technical Memorandum 4.0
Hydraulic Modeling Methodology & Results
Sidbury-Greenview Area
Preliminary Engineering Report - 6 -
Table 4.9: Comparison of Required and Existing Emergency Storage: 2030-2050
Capacity (MG) 2030 2040 2050
Average Day Demand (MGD) 22.75 25.97 28.87
Total Emergency Storage Required
(75% of Average Day Demand) 17.06 19.48 21.65
Total Existing Capacity 24.10 24.10 24.60
Total Elevated Storage Excess or (Deficit) 7.04 4.62 2.95
For a detailed breakdown of Tables 4.6-4.9, see Appendix B.
Pumping and Treatment Capacity Evaluation
Pumping and treatment capacity for 2030 through 2050 were evaluated for each of the zones in the
CFPUA distribution system. Required firm pumping capacity is equal to maximum day demand.
Pumps do not need to meet peak hour demand if enough elevated equalizing storage capacity is
available. Results are shown in Tables 4.10 and 4.11. Monterey Heights was not evaluated for this
analysis.
The Sweeney Water Treatment Plant (WTP) currently has a permitted capacity of 35 MGD and
Richardson WTP has a permitted capacity of 6 MGD. In both these situations, the 2030 maximum
day has exceeded 80% of the plant capacities. CFPUA is currently in the process of increasing the
plant capacities and the well field capacity at Richardson.
The 2040 and 2050 capacity evaluation are based on the 44 MGD Sweeney WTP capacity and 9.6
MGD Richardson WTP capacity.
The 2050 maximum day demand exceed 80% of the two plant capacities, it is recommended that
planning be initiated once maximum demand exceed 42 MGD.
Table 4.10: Existing Pump and Treatment Capacity Assessment – 2030
Sweeney Richardson
Excess (Deficit) Pumping Capacity (MGD) 19.98 3.42
Excess (Deficit) Plant Capacity (MGD) 4.18 0.44
Technical Memorandum 4.0
Hydraulic Modeling Methodology & Results
Sidbury-Greenview Area
Preliminary Engineering Report - 7 -
Table 4.11: Existing Pump and Treatment Capacity Assessment – 2040 & 2050
2040 2050
Excess (Deficit) Pumping Capacity (MGD) 18.5 13.8
Excess (Deficit) Plant Capacity (MGD) 12.3 7.6
For a detailed breakdown of Tables 4.10-4.11, see Appendix B.
END OF TECHNICAL MEMORANDUM
Technical Memorandum 5.0
Wastewater Offsite Analysis
Sidbury-Greenview Area
Preliminary Engineering Report - 1 -
The analysis of offsite wastewater infrastructure improvements was reserved to be
utilized as needed while the technical memorandum was being developed. Based on
current available capacity and projected wastewater flows for the Sidbury Greenview
area, offsite wastewater infrastructure improvements are not anticipated to be required
until approximately 2035. Therefore, no analysis of offsite wastewater infrastructure is
included in this technical memorandum. It is recommended that subsequent master
plans revisit the need for improvements as development progresses in the region.
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 1 -
6.1 INTRODUCTION
Technical Memorandum 6.0 (TM 6.0) details the water and wastewater recommendations. The
recommendations will be segmented by phased implementation configuration and final
configuration for the 30-year planning period for water and wastewater. Opinions of probable
project costs are included.
6.2 WASTEWATER RECOMMENDATIONS
In order to provide public wastewater service to the Sidbury-Greenview area for the projected
demands, a number of alternatives were evaluated. The alternatives were developed to provide
public wastewater service and access utilizing existing CFPUA infrastructure for conveyance and
treatment, which will be accomplished at Northside WWTP.
For the purposes of this summary, the preferred alternative has been broken down into an “Initial
Phase” and a “Future Phase” for the Sidbury Road Force Main and by Service Area for the project
area. The force main and water main for Service Area 1 is currently in the design phase and is
expected to be in construction in 2021. As development progresses in the project area, the
wastewater demand projections should be re-evaluated based on development specific factors.
The phased development of the recommended wastewater system to serve the projected flows
generated in the project area is detailed in the following section. See Figure 3.1 for a geographical
depiction of the recommendations.
6.3 WASTEWATER PHASED IMPLEMENTATION
The planning approach is detailed in TM 3.0. Table 6.1 below outlines the phased implementation
of the recommendations for the wastewater system that will be required to serve projected
demands through year 2050.
Sidbury Road Force Main - Initial Phase
DR Horton’s Sidbury Farms and other developments in SA-1 will be served by a single 12-inch
force main that manifolds to the Blue Clay Road force main through the year 2040 (1.12 MGD).
The installation of the 12-inch force main is expected to stimulate development along Sidbury
Road, prompting the construction of the “Future Phase.”
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 2 -
Sidbury Road Force Main – Future Phase
Additional flow from SA-1, SA-2, and SA-3 is expected to be generated by known development
interests along Sidbury Road. The addition of a parallel 12-inch force main, single 12-inch force
main, and an 8-inch force main will serve the projected flows through 2050 along Sidbury Road.
The addition of a parallel 12-inch force main will be required to serve 2040 demands generated
along Sidbury Road. A summary of the phased implementation of infrastructure improvements
and their associated costs are outlined in the following Table 6.1.
Table 6.1 – Summary of phased implementation of infrastructure improvements and associated
costs.
Infrastructure Improvements
Year Location Diameter Length Cost
2030 SA-1 12” Single 13,960 LF $1.95 M
SA-2 12” 8,400 LF $819,000
8” 1,600 LF $124,800
SA-3 8” 9,070 LF $708,200
6” 3,420 LF $223,000
SA-4 8” 14,720 LF $1.15 M
SA-5 4” 7,340 LF $381,600
SA-6 12” 21,100 LF $2.64 M
SA-7 8” 5,920 LF $461,200
2040 SA-1 12” Parallel 13,960 LF $ 1.95 M
2050 None
Detailed opinions of probable construction cost can be found in Appendix B
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 3 -
Based on projected demands, a parallel force main along Blue Clay Road and an upgrade to RPS1
will be required to convey wastewater to NSWWTP in year 2035 (1 MGD and 387,600 GPD,
respectively). Smith Creek PS will also require an upgrade to meet 2040 demands. A summary of
the phased implementation of infrastructure improvements to the existing system are outlined in
Table 6.2.
Table 6.2 – Phased Improvements to Existing Infrastructure
Year Description
2035 Parallel Blue Clay Road FM to NSWWTP
RPS1 Upgrade
2040 Smith Creek PS Upgrade****
**** Based on diverting 317,000 GPD from PS 77 to PS 35 and flow from RPS1 to Blue Clay Rd FM.
6.4 WATER PREFERRED ALTERNATIVE
The proposed water mains, detailed in TM 3.0, were divided into 11 individual projects, based on
the location and project year: 2030, 2040, or 2050. Figure 3.5 identifies the proposed routes of the
preferred alternative.
6.5 WATER PHASED IMPLEMENTATION
Proposed Improvements for 2030
The modeling analysis included the recommendations made in the 2019 Master Plan for 2030 and
2040. One of the recommendations included the Northern Service Line. Additional water mains
will be needed to meet the 2030 Sidbury and Greenview growth demands and are shown in
Figure 6.0.
Phasing of Water Lines West of I-40
The 2030 average day demand projected for The Sidbury and Greenview development can be
broken down into these main water service line:
• Sidbury Rd West (16-inch): 291 GPM
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 4 -
• Holly Shelter Rd (12-inch): 218 GPM
• Plantation Rd West (12-inch): 80 GPM
• Richardson Area: 208 GPM
Total 2030 average day: 797 GPM (1.15 MGD)
Two water mains west of I-40, Castle Hayne Rd South and North College Rd are needed to meet
the full demand of 1.15 MGD growth in Sidbury and Greenview. However, these projects can be
phased in. The capacity evaluation was done under a maximum day demand EPS with the goal of
maintaining Holly Shelter Tank level above 45% for fire demand. When the additional 16-inch
water line is built to the tank, the tank level can drop to 35% and the system is still capable of
supplying 2,000 GPM for 2 hours of fire protection at the school where the Holly Shelter Tank is
located.
The Northern Service Line, currently under construction can supply 230 GPM average day
demand. Table 6.3 lists the required demand, the provided demand and the difference.
Table 6.3: Capacity of the Northern Service Line
2030 Sidbury/ Greenview
Total Demand (GPM)
Northern Service
Line (GPM)
Remaining
Need (GPM)
Sidbury Rd West (16-inch): 291 230 61
Holly Shelter Rd (12-inch): 218 5 213
Plantation Rd West (12-inch) 80 80
With the addition of the Castle Hayne Rd South, another 61 gpm can be provided along Sidbury
Rd West and 70 GPM along Holly Shelter Rd, as shown in Table 6.4.
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 5 -
Table 6.4: Capacity of the Castle Hayne Rd South
2030 Sidbury/ Greenview
Total Demand (GPM)
Northern Service
Line (GPM)
Remaining
Need (GPM)
Sidbury Rd West (16-inch): 291 291 -
Holly Shelter Rd (12-inch): 218 75 143
Plantation Rd West (12-inch) 80 80 -
The North College Road water main was modeled to demonstrate phasing. With the same
additional demand provided as what the Castle Hayne Rd South water main could provide, the
Holly Shelter tank could drop below 33%. This does not meet the fire flow requirement.
Therefore, the Castle Hayne Rd South should be constructed first and be initiated as the Northern
Service Line reaches capacity.
The Castle Hayne Rd South and the North College Rd water mains are necessary to meet the 2030
Sidbury Greenview demand and to achieve 2,000 GPM for 2 hours of fire flow at the school
located adjacent to the Holly Shelter Tank.
Elevated Storage Tank Performance: 2030
Proposed pipe improvements were designed to maintain hydraulic balance within each of the
different zones. When a zone is hydraulically balanced, the HGLs at all elevated storage tanks
within the zone should be within approximately 6 feet of one another. Ideally, tanks levels will
fluctuate between approximately 100% full and 50% full throughout the day. This turnover
reduces water age. Maximum day demand conditions are modeled to evaluate tank balance and
level fluctuation, since MDD conditions can result in more headloss and hydraulic imbalance
across the distribution network.
Figures 6.1 and 6.2 in Appendix C show variation in tank levels and HGLs in the Sweeney zone
during a maximum day demand EPS simulation with proposed improvements for 2030. No tanks
drop below 40% full or reach 100% full for an extended period. The tanks fluctuate between 52%
and 97%. Apart from the Dawson Tank, the HGLs of the Sweeney tanks are within 9 feet of each
other at any given time throughout the day. The level in the Dawson tank does not follow the
same pattern as the other tanks because its level is controlled by a booster pump across most of the
system pressures.
The two tanks in the Richardson system (Ogden and Porter’s Neck) fluctuate between 48% and
98% full (Figure 6.3 in Appendix C). The Ogden and Porters Neck tanks HGLs are within 8 feet of
each other throughout the day (Figure 6.4 in Appendix C).
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 6 -
Available Fire Flow: 2030
The Available Fire Flow (AFF) goal for existing hydrants is 500 GPM at 20 PSI, maximum day
demand, and with tanks at their lowest expected level. However, the AFF goal for hydrants on all
future pipes within the Sidbury and Greenview is 1,500 GPM. AFF with proposed 2030
improvements is shown in Figure 6.5 in Appendix C. As discussed above, the Northern Service
Area Water Main improvements and the recommended connections of 10- and 8-inch pipes must
be in place before the Wrightsboro tank is taken offline in order to meet the AFF goal in that area.
The goal of 1,500 GPM could not be met at the end of the Sidbury Road line in the Richardson
Zone in the 2030 analysis. However, once the Sweeney and Richardson zones are merged and the
development systems include the appropriate pipe looping, the fire goal can be met.
Peak Hour Pressure and Velocity: 2030
Peak hour pressures in 2030 with the recommended improvements are shown in Figure 6.6 in
Appendix C. All nodes have a peak hour pressure of 41 PSI or greater, complying with CFPUA’s
minimum pressure goal of 40 PSI. Peak velocities under 2030 maximum day demand do not
exceed 6 feet per second, outside of WTPs, Booster Pump Stations and the Kerr Waterline
connection (4 to 7.2 FPS) to the 36 & 30-inch cross country connection feeder.
Water Age Evaluation: 2030
The 2030 water age evaluation assumes a significant decrease in flushing. However, several
automatic flushing locations are still needed and are shown in Figure 6.7 in Appendix C. Water
age improves in the area near the Wrightsboro tank improves as the tank is taken offline
temporarily. Water age in the Sidbury and Greenview areas are reasonable, except at the end of
Sidbury Rd where the Sweeney and Richardson Zone boundaries meet. Actual water age may
differ significantly from these predictions depending on the timing and location of new demand.
It will be important for CFPUA to closely monitor demand patterns, and potentially alter the
phasing of distribution system improvements to manage water age and quality. In the model, this
location had a flusher placed at it to reduce water age.
Proposed Improvements for 2040
To meet the 2040 Sidbury and Greenview growth demands, additional water mains (beyond the
Master Plan recommendations) are needed. These are shown in Figure 6.8 in Appendix C. This
includes the Blue Clay Rd North of Kerr Ave and Castle Hayne Rd North water mains.
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 7 -
Elevated Storage Tank Performance: 2040
Figures 6.9 and 6.10 in Appendix C show variation in tank levels and HGLs in the
Sweeney/Richardson zone during a maximum day demand EPS simulation with proposed
improvements for 2040. Holly Shelter Tank dropped as low as 34 % for a very short time period
and Odgen Tank peaked at 100% full for an extended period. This extreme difference between
tanks is due to the increased demand in this system while trying to maintain reasonable pipe size
and location improvements.
A simultaneous fire simulation was performed at hour 57 to ensure that adequate fire protection
under extreme conditions was possible. A 2 hour, 2,000 GPM fire flow was run at the Holly Shelter
school and at the prison. The Holly Shelter Tank emptied by the end of the 2 hour simulation,
however the model results indicated adequate pressures above 50 PSI through the system even
with this extreme demand.
Except for the Dawson tank and Porters Neck Plantation, the tank HGLs are within 14.5 feet of
each other at any given time throughout the day. The level in the Dawson and Porters Neck
Plantation tanks does not follow the same pattern as the other tanks because its level is controlled
by a booster pump.
Available Fire Flow (AFF): 2040
The AFF evaluation used 500 GPM (at 20 PSI, maximum day demand, and with tanks at their
lowest expected level) as the goal for existing hydrants. The AFF goal for hydrants on all future
pipes within the Sidbury and Greenview is 1,500 GPM. AFF with proposed 2040 improvements is
shown in Figure 6.11 in Appendix C. The goal of 1,500 GPM could not be met at the dead-end
piping within the development areas. However, once the development systems include
appropriate pipe looping, the fire goal can be met.
Peak Hour Pressure and Velocity: 2040
Peak hour pressures in 2040 with the recommended improvements are shown in Figure 6.12 in
Appendix C. All nodes have a peak hour pressure of 41 PSI or greater, complying with CFPUA’s
minimum pressure goal of 40 PSI. Peak velocities under 2030 maximum day demand do not
exceed 6 feet per second, outside of WTPs, Booster Pump Stations and the Kerr Waterline
connection to the 36 & 30-inch cross country connection feeder.
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 8 -
Water Age Evaluation: 2040
The 2040 water age evaluation, as with the 2030 evaluation, assumes a significant decrease in
flushing. Automatic flushing locations are still needed and are shown in Figure 6.13 in Appendix
C. In addition, the need for Wrightsboro Tank to be active for storage capacity increases water age
in the surrounding area. This is one of the locations where a flusher is recommended. Water age in
Sidbury and Greenview are reasonable. Actual water age may differ significantly from these
predictions depending on the timing and location of new demand. It will be important for
CFPUA to closely monitor demand patterns, and potentially alter the phasing of distribution
system improvements to manage water age and quality.
Proposed Improvements for 2050
The additional water mains to meet the 2050 Sidbury and Greenview growth demands are shown
in Figure 6.14 in Appendix C. These include the Blue Clay Rd South of Kerr Ave water main and
the equivalent 12-inch piping within development areas.
Elevated Storage Tank Performance: 2050
Figures 6.15 and 6.16 display variation in tank levels and HGLs in the Sweeney/Richardson zone
during a maximum day demand EPS simulation with proposed improvements for 2050. Holly
Shelter Tank dropped as low as 26 % for periods of time and Ogden Tank peaked at 100% full an
extended period. This extreme difference between tanks is due to the increased demand and
trying to maintain reasonable pipe improvements. The model should be refined as the
development occurs and assessments be made to further balance to the system’s tanks.
By 2050 several improvements will have been done to provide additional flow to the Holly Shelter
Tank. However, 26%, is below our goal. To make sure that the system wouldn’t suffer from this
low water level, a simultaneous fire simulation at hour 57 was performed. This was a 2 hour, 2,000
GPM at the school and at the prison. Similarly, to the 2040 multi fire flow analysis, the model
results indicated adequate pressures above 40 PSI, however, the Holly Shelter Tank was empty by
the end of the 2 hours. Although, the tank did empty at the end of the fire demand, the pressures
in the system did not drop below 20 psi, due to the additional water lines to the Holly Shelter
Tank.
Except for Dawson tank and Porters Neck Plantation, the tank HGLs are within 15 feet of each
other at any given time throughout the day. The level in the Dawson and Porters Neck Plantation
tanks does not follow the same pattern as the other tanks because their levels are controlled by
booster pumps.
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 9 -
Available Fire Flow: 2050
The AFF evaluation uses 500 GPM (at 20 PSI, maximum day demand, and with tanks at their
lowest expected level) as the goal for existing hydrants. However, the AFF goal for hydrants on all
future pipes within the Sidbury and Greenview is 1,500 GPM. AFF with proposed 2050
improvements is shown in Figure 6.17 in Appendix C. The goal of 1,500 GPM is met with the
recommended pipe improvements and appropriate pipe looping within the development areas.
Peak Hour Pressure and Velocity: 2050
Peak hour pressures in 2050 with the recommended improvements are shown in Figure 6.18 in
Appendix C. All nodes have a peak hour pressure of 41 PSI or greater, complying with CFPUA’s
minimum pressure goal of 40 PSI. Peak velocities under 2050 maximum day demand do not
exceed 6 feet per second, outside of WTPs, Booster Pump Stations and the Kerr Waterline
connection to the 36 & 30-inch cross country connection feeder.
Water Age Evaluation
The 2050 water age evaluation also assumes further decrease in flushing. Automatic flushing
locations are still needed and are shown in Figure 6.19 in Appendix C. Wrightsboro Tank is
required to meet storage capacity; however, this increases water age in the surrounding area. This
is one of the locations where a flusher is recommended. Water age in the Sidbury and Greenview
areas are reasonable. Actual water age may differ significantly from these predictions depending
on the timing and location of new demand. It will be important for CFPUA to closely monitor
demand patterns, and potentially alter the phasing of distribution system improvements to
manage water age and quality.
Summary
The hydraulic analysis performed evaluated a proposed growth for the Sidbury and Greenview
areas of 1.15 MGD every 10 years. The goal of this study was to recommend improvements to
meet the additional demand and the following goals:
• Hydraulically balance elevated storage tanks,
• Ensure adequate AFF of 1,500 GPM within Sidbury and Greenview
• Maintain peak hour pressures above 40 PSI
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 10 -
• Maintain reasonable water age
• Provide adequate storage, pump and treatment capacity through 2050.
As mentioned in the 2019 Master Plan, Wrightsboro tank can be temporarily taken offline to
improve water age, as it is not needed for storage in 2030. In order to meet the AFF goal in this
area, the Northern Service Area Water Mains improvements and the connected 10-inch pipe
(Chair Rd) and 8-inch pipes (Rockhill Rd) must be in place for this to occur. Once maximum day
demands in the Sweeney zone approach 42.5 MGD, the Wrightsboro tank will need to be brought
back online.
It was also determined that the Castle Hayne Rd South improvement will be needed when
Sidbury Rd average day demands approach 230 GPM. The 2030 demand on Sidbury Rd can be
met with the Castle Hayne Rd South improvement. As demand reaches an additional 75 GPM on
Holly Shelter Rd, the North College Rd improvement will be needed.
Once demand in the joined Sweeney/Richardson zone reaches 42 MGD (80% of the joined WTP
capacity), it is recommended that planning be initiated.
The summary of demand triggers for system infrastructure improvements outside of the Sidbury
and Greenview area are in Table 6.5.
Table 6.5: Demand Triggers for Infrastructure improvement outside of the Sidbury and Greenview
Area
Demand Trigger, mgd Infrastructure Improvement
230 GPM Average Day
Demand on Sidbury Rd 12-inch Castle Hayne Rd South water line
75 GPM Average Day
Demand on Holly Shelter Rd 16-inch North College Rd water line
42 MGD Max Demand Upgrades to either Sweeney or Richardson WTP Plant
42.5 MGD Max Day Demand Reinstate Wrightsboro Tank
The hydraulic modeling results as shown above meet the project goals. It is, however,
recommended that the system be reevaluated as developments are built and more refined
proposed numbers are understood.
6.6 WATER COST OPINION
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 11 -
An opinion of probable cost was prepared to aid in budgeting for the design and construction
phases of the Sidbury-Greenview area water system improvements as follows:
Cost Opinion Methodology
The general methodology implemented for the cost opinion was to divide the project into four
main categories and calculate a cost for each. The categories evaluated were as follows:
• Construction
• Design and Permitting
• Easements
• Construction Administration
The cost of construction was calculated based on five subcategories, including pipe and other
appurtenances; trenchless crossings including HDD and bore and jack; erosion and sediment
control (E&SC); miscellaneous items such as surface restoration, connections to existing water
mains, traffic control, and testing; and mobilization. For each of these subcategories, an estimated
material quantity take-off was developed in units of linear feet based on the proposed alignment
and calculated ratios, which are described in the subsequent paragraphs. Unit prices on a cost per
linear foot basis were applied for each item.
The cost per linear foot (LF) unit prices for E&SC, fittings, and miscellaneous items were
developed using the average of the three lowest actual bid prices from the 2018 Northern Service
Area Water Mains project divided by the total pipe length from that project. The costs for E&SC,
fittings, and miscellaneous items for the proposed water mains were calculated by multiplying the
unit price per linear foot from the Northern Service Mains bid by the total linear feet of each
proposed project. A standard 3% was applied for mobilization.
A different approach was used for the opinion of cost for valves and fire hydrants. Using the same
bid tabulation from the 2018 Northern Service Area Water Mains project, the total number of
valves and fire hydrants were each counted and then divided by the total project pipe length (per
1,000 LF) to develop two ratios: Valves per 1,000 LF and Fire Hydrants per 1,000 LF. In the cost
opinion, these two ratios were multiplied by the total linear feet for each proposed water main to
estimate the quantities of valves and fire hydrants on a linear foot basis. The unit prices per linear
foot applied for valves and fire hydrants are discussed in the following paragraph.
The unit prices utilized for the opinion of cost for pipe, valves, fire hydrants, and HDD and Bore
and Jack trenchless crossings were developed by comparing industry standards to the average of
the three lowest actual bid prices from the 2018 Northern Service Area Water Mains project. The
Technical Memorandum 6.0
Water & Wastewater Recommendations
Sidbury-Greenview Area
Preliminary Engineering Report - 12 -
cost opinion assumes all of the projected routes will use either 12-inch or 16-inch C900 PVC,
dimension ratio 18, for open cut installation. Unit prices for valves vary based on the
corresponding diameter of pipe used on the route. All costs are provided in 2020 dollars with no
escalation factors for inflation or increases in material cost.
Final construction costs will depend on actual labor, material, and equipment costs; competitive
market conditions; actual site conditions; final project scope; implementation schedule; easement
acquisition costs; and other factors that cannot be precisely quantified at the current level of detail.
Based on the level of detail of this preliminary cost estimate and to account for potential variations
in final construction costs, a 20% contingency was included with the construction subtotal.
Industry standard percentages were applied to estimate costs for design (12% of construction),
easement acquisition (0.5% of construction), and construction administration (5% of construction).
Cost Opinion
Table 6.6, Table 6.7, and Table 6.8 provide costs associated with the total preliminary cost
estimates for the 2030, 2040, and 2050 proposed routes for the Sidbury and Greenview Area
Impact to the CFPUA Water System project, respectively. For a detailed breakdown of the cost
estimates below, see Appendix D.
Table 6.6: Preliminary Cost Estimate for Year 2030 Projects
Item
Castle
Hayne Rd
South
Holly
Shelter Rd
2030
North
College Rd
Plantation
Rd West
Plantation
Rd East
Sidbury Rd
West
Sidbury Rd
East
Project
Total $1,816,000 $2,546,000 $1,848,000 $3,208,000 $2,684,000 $3,510,000 $3,540,000
Table 6.7: Preliminary Cost Estimate for Year 2040 Projects
Item Castle Hayne Rd North Holly Shelter Rd 2040
Connection Blue Clay Rd 2040
Project Total $2,853,000 $47,000 $1,866,000
Table 6.8: Preliminary Cost Estimate for Year 2050 Projects
Item Blue Clay Rd 2050
Project Total $1,229,000
END OF TECHNICAL MEMORANDUM
FIGURES
RECOMMENDED WATER SYSTEM IMPROVEMENTSFIG 0.1CFPUA SIDBURY GREENVIEW LEGENDPROJECT AREA2050 PIPE IMPROVEMENTSWATER TANKSERVICE AREA2019 EXISTING PIPES203020402050
RECOMMENDED WASTEWATER SYSTEM IMPROVEMENTS WITH RELATIVE DIAMETER, LENGTH, AND COSTFIG 0.2CFPUA SIDBURY GREENVIEW LEGENDPROJECT AREAFORCE MAINSERVICE AREATO BE PARALLELED IN 2040*
RECOMMENDED WATER SYSTEM IMPROVEMENTS WITH RELATIVE DIAMETER, LENGTH, AND COSTFIG 0.3CFPUA SIDBURY GREENVIEW LEGENDPROJECT AREASERVICE AREA203020402050
KNOWN DEVELOPMENTS AND OTHERLARGE DEVELOPABLE TRACTSFIG 2.1CFPUA SIDBURY GREENVIEWLEGENDPROJECT AREA (16,870 AC)Cameron HoldingsCorbett HoldingsTrask HoldingsHanover ReserveCharleston LakesIsland CreekLee Hills SubdivisionNorthern NHC TractsBlanton Property4908 Blue Clay RoadHanpin Land CoThe Walk at Porters NeckYvonne RoadWild MagnoliaMurrayville RoadStephens Church RoadBlake TractsTract South of I-140Rock ChurchMartin Marietta MaterialsNCDOTElementis ChromiumSeagreen LLCSkipper Family PropertiesHynda DaltonNCSU AgricultureSidbury Farms
EXISTING INFRASTRUCTUREFIG 1.2CFPUA SIDBURY GREENVIEW LEGENDGRAVITY SEWERPROJECT AREAFORCE MAINPUMP STATIONSERVICE AREA
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/ASidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Existing Pipes
DAWSON ST WESTBROOK
CASTLE HAYNE
HOLLY SHELTER
17TH ST
WRIGHTSBORO
PORTERS NECK
OGDEN
PORTERS NECKPLANTATION
SWEENEY WTP
RICHARDSONWTP
¯
Sidbury and Greenview Growth
MGD
0.000 - 0.005
0.006 - 0.010
0.011 - 0.050
0.051 - 0.100
0.101 - 0.190
EXISTING PIPES
Diameter
< 6 inch
6 - 8 inch
8 - 12 inch
12 - 20 inch
> 20 inch012,000Feet
RECOMMENDED WASTEWATER SYSTEM IMPROVEMENTSFIG 3.1CFPUA SIDBURY GREENVIEW LEGENDGRAVITY SEWERPROJECT AREAFORCE MAINPUMP STATIONSERVICE AREA
FIG 3.2CFPUA SIDBURY GREENVIEWLEGENDGRAVITY SEWERPROJECT AREAFORCE MAINPUMP STATIONSERVICE AREARECOMMENDED WASTEWATER SYSTEM IMPROVEMENTS SA-1
FIG 3.3CFPUA SIDBURY GREENVIEWLEGENDGRAVITY SEWERPROJECT AREAFORCE MAINPUMP STATIONSERVICE AREARECOMMENDED WASTEWATER SYSTEM IMPROVEMENTS SA-2
FIG 3.4CFPUA SIDBURY GREENVIEWLEGENDGRAVITY SEWERPROJECT AREAFORCE MAINPUMP STATIONSERVICE AREARECOMMENDED WASTEWATER SYSTEM IMPROVEMENTS SA-3
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-1
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Overview
Proposed Water Mains
¯
0 2,500 5,000 7,50010,000Feet
Legend
Proposed Water Mains 2030
Proposed Water Mains 2040
Proposed Water Mains 2050
CASTLE
HAYNE RD
SOUTH
BLUE CLAY
RD 2050
BLUE CLAY
RD 2040
CASTLE
HAYNE RD
NORTH
HOLLY SHELTER
RD 2030
NORTH
COLLEGE RD SIDBURY RD
WEST SIDBURY RD
EAST
PLANTATION
RD EAST
PLANTATION
RD WEST
HOLLY SHELTER RD
2040 CONNECTION
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-2
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Castle Hayne Rd South
Proposed Water Mains 23RDGARDN
E
R
HERONS VIEW
MARTIN LUTHER KING JR EGRETCROSSINGHANOV
ER
L
AK
E
S
CORNELIUS HARNETT HOLLYBERRY5TH
CO
M
P
T
O
N
PALME
T
T
O
CASTLE
H
A
Y
N
E
6THOSPREY
COVE
MCRAECO
N
T
I
N
E
N
T
A
L
MARTIN LUT
H
E
R
K
I
N
G
J
R TIDALFO
R
E
S
T
KRAUS
S
E
RIVERV
I
E
W
DIVISION PARKAIR
P
O
R
T
DIVISIO
N
SPRI
N
G
A
R
L
ING
TON
PRESERVATION
PO
INT
GORDON
YO
R
K
T
OW
N
BRENTWOODBLUE C
L
A
YGLENDALEVI
C
TO
R
I
A
0 500 1,000 1,500 2,000
Feet
Legend
Proposed Water Main 2030
Trenchless Crossing
Parcels
Existing Watermains
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-3
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
North College Rd
Proposed Water Mains
I-40PARSONS MILLCOLLE
G
E
MI
L
L
H
O
U
S
EPARMELE
PARMELEPER
ENN
IA
LGARDEN
S
HUNTSMANHOUNDSEARCREEKSTONE
LOGAN HOPKIN
SSMALLSTREAMCHERRYGROVEDUTCH
COVE
CHRISBALL
A
R
D
I-40POWERSIRON TREE
PA
R
S
O
N
S
MI
L
L
DEERFIELD
OLD OA
K
L
A
N
D
CAS
T
L
E
H
E
I
G
H
T
S
SADDLEBROOK
TWIN OAKS
RUSTIC ACRES
PLUMTREE¯0 500 1,000 1,500 2,000
Feet
Legend
Proposed Water Main 2030
Trenchless Crossing
Parcels
Existing Watermains
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-4
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Holly Shelter Rd 2030
Proposed Water Mains
HOLLY S
H
E
L
T
E
R
KERRY
PRIVATEDIAMOND SHAMROCKPRIVAT
EPRIVATEBLUE CLAYPRIVATEMCGREGORPRIVAT
E
PRIVAT
E PRIVATEPRIVATEPRIVATEPRIVATEPRIVAT
EPRIVATEIDEAL CEMENTLULA NIXONPRIVATELegend
Proposed Water Mains 2030
Trenchless Crossing
Parcels
Existing Watermains
0 750 1,500 2,250 3,000Feet
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-5
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Sidbury Rd West
Proposed Water Mains
I
-40PRIVAT
E
SUNRAY
ENNIS ACRESWOODHAVEN
SIDBUR
Y
TRANSFORMA
T
I
O
N PRIVATEBLUE CLAYPRIVATEPRIVATECAROLY
N
H
I
L
L
PRIVATEEDNA BUCKPRIVATEPRIVATEPRIVATEDAIR
Y
F
A
RM
PRIVATEHERMITAGE
I
-40BUCKEDUCAT
ION
PASTUR
E
GLAZIER
BROOKDALE
PRIVA
T
E
PROSPERITYGILBERT CURRY PRIVATEPRIVATEPRIVATE
PRIVATE
PRIVATEBLUE CLAYPRIVATE
PRIVATEPRIVATE
0 750 1,500 2,250 3,000Feet
Legend
Proposed Water Mains 2030
Trenchless Crossing
Parcels
Existing Watermains
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-6
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Sidbury Rd East
Proposed Water Mains
Military
C
ut
off
Hampst
ea
d
By
p
ass FARMMARKE
T
MARKE
T
STEPH
E
N
S
CHUR
C
HPRIVATEISLAND CREEKPRIVAT
E
SCOTTSHILLMEDICAL
PRIV
A
T
E
PRIVATEPRIVATESIDBURY
PRIVATECROOKED PINEPRIVA
T
E
ISLAND
C
R
E
E
K
PRIVA
T
E
PRIVA
T
E
P
R
I
V
A
T
E
PRIVATE
PRIVATE
PRIVATE
0 750 1,500 2,250 3,000Feet
Legend
Proposed Water Mains 2030
Trenchless Crossing
Parcels
Existing Watermains
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-7
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Plantation Rd West
Proposed Water Mains Military CutoffHampsteadBypassMilitary
C
u
t
o
f
fHampst
e
a
d
B
y
p
a
s
s
Mili
ta
ry
Cu
to
f
fHampstead
Bypa
s
s
BRITTANY
POINTER
WOODBU
R
NEASTB
O
U
R
NE
WOODBERRYPRIVATEDUCKSBI
L
L
CREEK RIDGE
NEW
TOWN
BIGHORNBASSET
HABERDEE
NBLUETICKCOVEYCOCKER
PEPPERCORNRICE
GATE
TORCHW
O
O
DBIRDDOGSPRINGER
HALLS
T
E
A
DMU
R
R
A
Y
F
A
RM
S
NORTH
C
H
A
S
E CROOKED PINEIRI
S
H
CAMERON
TRACE
ENTERPRISE COURTNEYPINESFIVE ACRESHENANDOAHFLUSHINGMAPLERIDGECRICKET
NEILTRAPPERRETRIEVER
MURRAYV
I
L
L
E
Q
U
A
I
L
W
O
O
D
S
MISTY OAKFERNDALE ALAMANCEBRITTAN
Y
LAK
E
S STONEWOODYELLOW BELLSPRINGWATERIVOR
YMABEE RABBITHOLLOWSHIRESTONEHAVEN WOODHALLLURAYSHEFFIELDAMESBURYWELCHJACKSONSRIDGEE
N
G
L
I
S
H
STILLCREEKPRIVATEWHITNEY NEWB
U
RY
CAMPAGNAGREGORYSP
A
N
I
E
L
LAURENPLACETHETFORDPOINTINGGRIFFONWHITE
THURGOODMEADOWV
I
E
W
CANEY
BRANCH DOVE FIELDPRI
V
A
T
E
SETTERDOGWHISTLECOLLEGE ROCKWELLVALORBROOKSIDEGARDENSWILLIAMSBURG RABBITHOLLOWSHERMAN
OAKS POINTERSPE
A
R
O
W
BRITTANYPRIVATE FOREST
B
E
N
DPRIVATE
POTOMAC
I-
4
0
GOLDEN
G
R
O
V
E
PLANTATION
PRIVATECORPORATEPRIVAT
E
I-
4
0
I-140
WILD MAGNOLIA
I-140¯0 750 1,500 2,250 3,000Feet
Legend
Proposed Water Mains 2030
Trenchless Crossing
Parcels
Existing Watermains
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-8
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Plantation Rd East
Proposed Water MainsMilitary CutoffHampstead BypassAMBERLEIGHCOUNTRY HAVENALEXANDER AMBERLEIGHRAINT
R
E
E
G
R
A
Y
S
T
O
N
E
CHERA
W
ARCH
D
A
L
E
AL
E
X
A
N
D
E
R SANDERLINGMONARCHKEYS
T
O
N
E CYPRESS POND
BU
M
P
A
L
O
N
G
PENCADE KOONCESANSBERRYPRIVATEBEAUF
O
R
T
TRACE
L
O
O
S
E
S
T
R
I
F
E
HAZELTONYVONNEELMHURSTMEND
E
N
H
A
L
L
MARSH OA
K
S
MARYM
O
U
N
T
OLDE
P
O
N
D
HAY
S
MARKE
TSANCTUARYCOUNTRY
LAKES
MAPLERIDGEBE
AW
O
O
D MARSH REACHTREASUREBAYFI
E
LDLILLY POND
PLACID
PRIV
A
T
E
PLANTATION
PORTERS
NECK
GR
O
U
N
D
W
A
T
E
R SWEETWATER
BRISTLECONEGABLE RUNRED COCKADEDM
C
C
O
RM
I
C
K
0 500 1,000 1,500 2,000Feet
Legend
Proposed Water Mains 2030
Parcels
Existing Watermains
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-9
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Castle Hayne Rd North
Proposed Water Mains
C
A
S
T
L
E
H
A
Y
N
ECASTLEHOLLYSHELTERCOLLEGECOLE
B
A
V
A
R
I
A
N
CASTLE
HAYNE
CA
S
T
L
E
H
A
Y
N
E
GOFF
OLD
AN
T
H
O
N
Y
RO
N
A
L
D
BLOSSOM
ASHBI
R
D
S
VI
E
WCHERRYHICKORY MARY
PARMELEGARDENPLACESONDEYCASTLE LAKES SIMMONSHEIGHTSBOWMANWEDGEWOOD
WOODC
R
E
S
T
SYCAMORE
PRIVATEHYACINTH
EGGERT
CHIPP
E
W
A STRICKSTRADING
POSTLYNNMICHAELMADELINE TRASKMCDOU
G
A
L
D
CROW
A
T
A
NTOM
JE
S
S
I
C
AHAWKS NESTASHLY
N
MA
Z
U
RHUBERTB
R
O
O
K
G
R
E
E
N
CHIP
PELLA
N
DPRINCE GEORGECASTLE COVEHERMITAGECHESTERFIE
L
D
PETER SPRING
MARATHON¯0 500 1,000 1,500 2,000
Feet
Legend
Proposed Water Main 2030
Proposed Water Main 2040
Trenchless Crossing
Parcels
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-10
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Holly Shelter Rd
2040 Connection
Proposed Water Mains
HOLLY SHELTER
PRIVATE0 75 150 225 300Feet
Legend
Proposed Water Main 2040
Trenchless Crossing
Parcels
Existing Watermains
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-11
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Blue Clay Rd 2040
Proposed Water Mains
ANSWORTH BRUCEMONTREMINGTONNORTHCHASEBIG FIEL
D
CALADA
N
NEEDLERUSHLEONAR
AM
G
A
T
E
CHANDLERLAKEMO
O
RPECKHAM PREMIER
RUSSELLBOROUGHCARVEROLD MILLBARRO
W
HIGHG
A
T
E
CABOT
MONTI
C
EL
L
O
SKY
TEDDYWHITEWOOD
TANDEM
KERR CAESARHEA
TH
ER
R
IDG
E
NO
R
T
H
CO
U
N
T
Y
DULWIC
H
COMMO
N
BRINKMANBRAMB
L
E
FLIGHT PAT
H
EXPORTPARAMOU
N
T
DALTO
N
ELLISCASTLE HAYNECLAYMORETER
E
S
A
DAMONTODDALEX TRASK ASPENPRIVATEH
O
L
L
Y
WOOLWIT
C
H
RI
T
T
E
R
GALWAY
PRIVA
T
E
PRIMR
O
S
E
NEVAN
EDWAR
D
HYDEMODAWG LAGAR
PROVINC
E
HE
M
L
O
C
K
BOUNDA
RYCOMMERCE KI
T
T
Y
H
AW
K
O
R
V
I
L
L
E
W
R
I
G
H
TMUTU
A
L AMMONSFAIRFO
R
D
B
R
I
D
G
E
P
O
R
TBLUE BONNETJUVENILECENTERCOLLEGEI-140
I-140
BLUE C
L
A
Y
OA
K
L
E
Y
WEATHERBYHOLLANDSWA
R
T
V
I
L
L
E
SAN
D
Y
LAU
R
E
L
LON
G
L
E
A
F
ARLE
N
E
PE
N
N
I
N
G
T
O
N
¯
Legend
Proposed Water Main 2040
Trenchless Crossing
Parcels
Existing Watermains
0 500 1,000 1,500 2,000Feet
CAPE FEAR PUBLIC UTILITIES AUTHORITY
NORTH CAROLINA
March 2020
32270-023
N/A
1-12
Sidbury and Greenview Area
Impact to CFPUA Water System
DATE:
HAZEN NO.:
CONTRACT:
FIGURE NO.:
Blue Clay Rd 2050
Proposed Water Mains
NASSAU
NASSAUCARL SE
ITTER
CASTLE
H
A
Y
N
E
HERITAGE PARKIMPORTBLUE CL
A
Y
SPRING
HALLOLD WRIGHTSBOROCASTLE
CREEKHARNETTCOMMERCEFULBR
I
G
H
T
MUTU
A
L
ACORN BR
A
N
C
HFAIRFIELDBERMUDA
GARD
NER
KE
R
R
JAMAICAPILGR
IM
0 250 500 750 1,000Feet
Legend
Proposed Water Mains 2050
Trenchless Crossing
Parcels
Existing Watermains
APPENDIX A
SIDBURY ROAD TRACT
Y
N
E
5
Wilmington, NC
PRELIMINARY MASTER PLAN
QUAD TOWNHOMES
TOWNHOMES = 104 UNITS (4 UNITS / BUILDING)
BUILDING SIZE: 96' x 65'
WETLAND AREA, TYPICAL
SINGLE FAMILY LOTS (55' x 120')
TOTAL LOTS = 332 LOTS
GARDEN APARTMENTS (150' x 70'')
TOTAL APARTMENTS = 288 UNITS (24 UNITS / BUILDING)
APARTMENT AMENITY SPACE
PROPERTY LINE, TYPICAL
(TAKEN FROM NHC GIS)Licence #C-36411429 ASH-LITTLE RIVER RD. NW
ASH, NC 28420
PHONE (910) 287-5900
NORRIS & TUNSTALL
CONSULTING ENGINEERS P.C.
1900 EASTWOOD RD., SUITE #11
WILMINGTON, NC 28403
PHONE (910) 343-9653
SITE DATA TABLE
PROJECT #19146
APPENDIX B
Table 4.6 – Comparison of Required and Existing Elevated Storage - 2030
Sweeney Richardson Monterey
Heights
Required Equalizing Storage
Average Day Demand (mgd) 18.83 3.23 0.70
Maximum Day Demand (mgd) 30.82 5.58 1.12
Equalizing Percentage 17% 11% 11%
Equalizing Volume (MG) 5.24 0.61 0.12
Required Fire Storage
Needed Fire Flow (gpm) 3,500 3,500 2,500
Duration (hours) 3 3 2
Fire Storage Volume (MG) 0.63 0.63 0.30
Duration (hours)
Required Elevated Storage (Equalizing + Fire Storage)
(MG) 5.87 1.24 0.42
Existing Elevated Storage Capacity (MG)
Dawson St Tank 1.50
17th St Tank 1.50
Westbrook Tank 2.00
Porter's Neck Tank 0.50
Ogden Park Tank 0.60
Porters Neck Plantation 0.80
Castle Haynes Tank 0.50
Holly Shelter School Tank 0.50
Wrightsboro Tank (temporarily offline)
Veterans Park Tank 0.50
Total existing capacity 6.00 1.90 0.50
Excess (or deficit) capacity (MG) 0.13 0.66 0.08
Table 4.7 – Comparison of Required and Existing Elevated Storage - 2040
Sweeney/
Richardson
Monterey
Heights
Required Equalizing Storage
Average Day Demand (mgd) 25.21 0.76
Maximum Day Demand (mgd) 41.46 1.21
Equalizing Percentage 17% 11%
Equalizing Volume (MG) 7.05 0.13
Required Fire Storage
Needed Fire Flow (gpm) 3,500 2,500
Duration (hours) 3 2
Fire Storage Volume (MG) 0.63 0.30
Duration (hours)
Required Elevated Storage (Equalizing + Fire Storage) (MG) 7.68 0.43
Existing Elevated Storage Capacity (MG)
Dawson St Tank 1.50
17th St Tank 1.50
Westbrook Tank 2.00
Porter's Neck Tank 0.50
Ogden Park Tank 0.60
Porters Neck Plantation 0.80
Castle Haynes Tank 0.50
Holly Shelter School Tank 0.50
Wrightsboro Tank (temporarily offline)
Veterans Park Tank 0.50
Total existing capacity 7.90 0.50
Excess (or deficit) capacity (MG) 0.22 0.07
Table 4.8 – Comparison of Required and Existing Elevated Storage – 2050
Sweeney/
Richardson
Monterey
Heights
Required Equalizing Storage
Average Day Demand (mgd) 28.05 0.82
Maximum Day Demand (mgd) 46.04 1.31
Equalizing Percentage 17% 11%
Equalizing Volume (MG) 7.83 0.14
Required Fire Storage
Needed Fire Flow (gpm) 3,500 2,500
Duration (hours) 3 2
Fire Storage Volume (MG) 0.63 0.30
Duration (hours)
Required Elevated Storage (Equalizing + Fire Storage) (MG) 8.46 0.44
Existing Elevated Storage Capacity (MG)
Dawson St Tank 1.50
17th St Tank 1.50
Westbrook Tank 2.00
Porter's Neck Tank 0.50
Ogden Park Tank 0.60
Porters Neck Plantation 0.80
Castle Haynes Tank 0.50
Holly Shelter School Tank 0.50
Wrightsboro Tank (returned to service) 0.50
Veterans Park Tank 0.50
Total existing capacity 8.40 0.50
Excess (or deficit) capacity (MG) (0.06) 0.06
Table 4.9: Comparison of Required and Existing Emergency Storage: 2030-2050
Capacity (MG) 2030 2040 2050
Average Day Demand (mgd) 22.75 25.97 28.87
Total Emergency Storage Required
(75% of Average Day Demand) 17.06 19.48 21.65
Existing Emergency Storage Capacity
Sweeney Clearwell 16.00 16.00 16.00
Richardson Clearwell 2.00 2.00 2.00
Total Elevated Storage (without
Dawson and Porters Neck Plantation) 6.10 6.10 6.60
Total Existing Capacity 24.10 24.10 24.60
Total Elevated Storage Excess (Deficit) 7.04 4.62 2.95
Table Error! No text of specified style in document..10: Existing Pump and Treatment Capacity
Assessment – 2030
Sweeney Richardson
Pump Capacity Required
Maximum Day Demand (mgd) 30.82 5.58
Existing Firm Pump Capacity
Sweeney WTP (mgd) 50.80
Richardson WTP (mgd) 9.00
Monterey Heights Wells (mgd)
Total (mgd) 50.80 9.00
Excess (Deficit) Pumping Capacity (mgd) 19.98 3.42
Existing Plant Capacity
Sweeney WTP (mgd) 35.00
Richardson WTP (mgd) 6.00
Monterey Heights Wells (mgd) (Safe Yield)
Total (mgd) 35.00 6.00
Excess (Deficit) Plant Capacity (mgd) 4.18 0.44
Table Error! No text of specified style in document..11: Existing Pump and Treatment Capacity
Assessment – 2040 & 2050
2040 2050
Pump Capacity Required
Maximum Day Demand (mgd) 41.3 46.0
Existing Firm Pump Capacity
Sweeney WTP (mgd) 50.8 50.8
Richardson WTP (mgd) 9.0 9.0
Monterey Heights Wells (mgd)
Total (mgd) 59.8 59.8
Excess (Deficit) Pumping Capacity (mgd) 18.5 13.8
Existing Plant Capacity
Sweeney WTP (mgd) 44.0 44.0
Richardson WTP (mgd) 9.6 9.6
Monterey Heights Wells (mgd) (Safe Yield)
Total (mgd) 53.6 53.6
Excess (Deficit) Plant Capacity (mgd) 12.3 7.6
APPENDIX C
Figure 6.1: 2030 Maximum Day Demand EPS Tank Water Levels in the Sweeney Zone, with
Proposed Improvements
Figure 6.2: 2030 Maximum Day Demand EPS Tank HGLs in the Sweeney Zone, with Proposed
Improvements
Figure 6.3: 2030 Maximum Day Demand EPS Tank Water Levels in the Richardson Zone, with
Proposed Improvements
Figure 6.4: 2030 Maximum Day Demand EPS Tank HGLs in the Richardson Zone, with
Proposed Improvements
Figure 6.9: 2040 Maximum Day Demand EPS Tank Water Levels in the Sweeney/Richardson
Zone, with Proposed Improvements
Figure 6.10: 2040 Maximum Day Demand EPS Tank HGLs in the Sweeney Zone, with Proposed
Improvements
Figure 6.15: 2050 Maximum Day Demand EPS Tank Water Levels in the Sweeney/Richardson
Zone, with Proposed Improvements
APPENDIX D
Table 6.6: Preliminary Cost Estimate for Year 2030 Projects
Item
Castle
Hayne Rd
South
Holly
Shelter Rd
2030
North
College
Rd
Plantation
Rd West
Plantation
Rd East
Sidbury
Rd West
Sidbury
Rd East
Pipe and
Appurtenances $748,000 $1,404,000 $1,146,000 $1,734,000 $1,755,000 $2,077,000 $2,024,000
Trenchless
Crossings $442,000 $251,000 $65,000 $365,000 $0 $227,000 $276,000
Erosion and
Sediment Control $28,000 $47,000 $29,000 $57,000 $44,000 $54,000 $65,000
Miscellaneous $30,000 $50,000 $31,000 $61,000 $47,000 $57,000 $70,000
Mobilization - 3% $38,000 $53,000 $39,000 $67,000 $56,000 $73,000 $74,000
Contingency - 20% $258,000 $361,000 $262,000 $455,000 $381,000 $498,000 $502,000
Construction Total $1,544,000 $2,166,000 $1,572,000 $2,729,000 $2,283,000 $2,986,000 $3,011,000
Design and
Permitting - 12% of
Construction
$186,000 $260,000 $189,000 $328,000 $274,000 $359,000 $362,000
Easements - 0.5% of
Construction $8,000 $11,000 $8,000 $14,000 $12,000 $15,000 $16,000
Construction
Administration -
5% of Construction
$78,000 $109,000 $79,000 $137,000 $115,000 $150,000 $151,000
Project Total $1,816,000 $2,546,000 $1,848,000 $3,208,000 $2,684,000 $3,510,000 $3,540,000
Table 6.7: Preliminary Cost Estimate for Year 2040 Projects
Item Castle Hayne Rd North
Holly Shelter Rd 2040
Connection Blue Clay Rd 2040
Pipe and Appurtenances $1,585,000 $29,000 $1,172,000
Trenchless Crossings $290,000 $0 $33,000
Erosion and Sediment Control $42,000 $1,000 $38,000
Miscellaneous $45,000 $1,000 $40,000
Mobilization - 3% $59,000 $1,000 $39,000
Contingency - 20% $405,000 $7,000 $265,000
Construction Total $2,426,000 $39,000 $1,587,000
Design and Permitting - 12%
of Construction $292,000 $5,000 $191,000
Easements - 0.5% of
Construction $13,000 $1,000 $8,000
Construction Administration -
5% of Construction $122,000 $2,000 $80,000
Project Total $2,853,000 $47,000 $1,866,000
Table 6.8: Preliminary Cost Estimate for Year 2050 Projects
Item Blue Clay Rd 2050
Pipe and Appurtenances $529,000
Trenchless Crossings $276,000
Erosion and Sediment Control $19,000
Miscellaneous $20,000
Mobilization - 3% $26,000
Contingency - 20% $174,000
Construction Total $1,044,000
Design and Permitting - 12% of Construction $126,000
Easements - 0.5% of Construction $6,000
Construction Administration - 5% of Construction $53,000
Project Total $1,229,000