January 15, 2025
Ray Griswold
Fire Marshal, Deputy
New Hanover County – Fire Rescue
230 Government Center Drive, Suite 130
Wilmington, NC 28403
RE: Wilmington Trade Center Buildings 4 & 7
Hydraulic Analysis of Required Fire Flow
Dear Mr. Griswold:
Along with representatives from Cape Fear Public Utility Authority and New Hanover County Fire
Services, Odyssey Fire Protection conducted a hydrant flow test near the above referenced site. As
shown on the attached exhibit map, the hydrant flow test was conducted at existing hydrants along US
Highway 421 adjacent to the above referenced site.
Based on the results hydrant flow test, Paramounte Engineering, Inc. (PEI) completed hydraulic
analysis of required fire flow using WaterCAD software. Detailed results of this analysis are enclosed.
As shown in the enclosed Required Fire Flow Calculation Per 2018 NCFSC Appendix B, the minimum
fire flow required is 1,500 gpm. The enclosed results of the hydraulic analysis show this flow to be
maintained throughout the proposed system.
We appreciate the opportunity to provide this service for you and your project. Please feel free to
contact me if you have any questions or require additional information.
Sincerely,
Paramounte Engineering, Inc.
Jeremy R. Blair, PE
Enclosure: as noted
N O R T H CAROLIN
A
PR O FESSION
ENGIN E E R
SEAL
A
L
J
E
R
EMY R . B L A IR
0 2 8 8 5 2
1/15/24
1 2 2 C I N E M A D R I V E, W I L M I N G T O N , N C 2 8 4 0 3
P H : ( 9 1 0 ) 7 9 1 - 6 7 0 7 F A X : ( 9 1 0 ) 7 9 1 - 6 7 6 0
REQUIRED FIRE FLOW CALCULATION PER 2018 NCFSC APPENDIX B
Project: Wilmington Trade Center Buildings 4 & 7
Location: 3930 N. US Highway 421, Wilmington, NC
Fire Flow Calculation Area: 152,880 Sq. Ft.
Construction Type: II-B
Buildings will be outfitted with ESFR sprinkler system.
Per Table B105.2, for a building of this type with an automatic sprinkler system, the Minimum Fire-
Flow required will be 25% the value in Table B105.1(2). Flow Duration will be the value in Table
B105.1(2) at the reduced flow rate.
Based on the Fire Flow Calculation Area and Construction Type provided above, Table B105.1(2)
indicates:
Fire Flow = 4,250 gpm x 0.25 = 1,062.5 gpm (20 PSI)
[NOTE: Reduced Fire Flow shall not be less than 1,500 gpm, so Fire Flow required is
1,500 gpm]
Flow Duration = 4 hours at 1,500 gpm
ODYSSEY FIRE PROTECTION
Fire Flow Report
Date Time
12/21/2023 9:15
Fire Flow @ 20psi Fire Flow @ 10psi
Qr Flow in GPM
Cd Friction loss Coefficient
D diameter of opening in inches
Pp Pressure on Pitot in psi
Qf Fire flow in GPM at 20psi Static Pressure Residual Pressure
Ps Static Pressure in psi
Pr Residual Pressure in psi
Hyd #Port #D Cd Pp Qr
1 4.5 0.89 0 0
2 2.5 0.9 46 1138
1 2.5 0.9 0
2 2.5 0.9 0
1 2.5 0.9 0
2 2.5 0.9 0
1138
Ray Griswold - De[puty F.M. & Jr. w/ CFPUA
Total GPMs flowed in test
1
2
3
Person Conducting Test
Jeff Tippett - OFP
68 61
Witness:
Test Hydrant Information
Location
Hyd. #2719 & # 2928- HWY. 421 North
3,219 3,565
Legend
0
500
1000
1500
2000
2500
3000
3500
4000
10 20 30 40 50 60 70 80 90 100
GP
M
PSI
Total Fire Flow
12/21/2023
1000 ft
N
➤➤
N
16" Water Main
Flow Hydrant:
- Revised Location
- New Fire Hydrant, recently added onto the16" Water Main
- Fire Hydrant Tag #2928.
Static/Residual Pressure Hydrant:
- Fire Hydrant Tag #2719
Scenario: Fire Flow
P-
8
P
-
9
P-1 0
P-1 1
P -1 2
P -1 3
P -1 5
P
-1
6
P
-
1
7
P
-1
8
P -1 4(1)
P-1 4 (2 )
P
-
1
9
P-20
WTC - Fireflow.wtg
Bentley Systems, Inc. Haestad Methods Solution
Center
WaterCAD
[24.00.00.26]
1/15/2025 76 Watertown Road, Suite 2D Thomaston, CT
06787 USA +1-203-755-1666
Page 1 of 1
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
Fire Flow Node FlexTable: Fire Flow Results Table
Label Flow (Total
Needed)
(gpm)
Flow (Total
Available@20psi)
(gpm)
Pressure
(Calculated
Residual @ Total
Flow Needed)
(psi)
J-7 1,500 3,118 55
J-8 1,500 3,023 53
J-9 1,500 2,871 53
J-10 1,500 2,757 52
J-11 1,500 2,743 52
J-12 1,500 2,641 51
J-13 1,500 2,641 51
J-14 1,500 2,210 44
J-15 1,500 1,886 36
J-16 1,500 1,564 23
J-17 1,500 2,666 51
J-19 1,500 1,923 38
J-20 1,500 1,891 37
J-21 1,500 1,648 27
WTC - Fireflow.wtg
Bentley Systems, Inc. Haestad Methods Solution
Center
WaterCAD
[24.00.00.26]
1/15/2025 76 Watertown Road, Suite 2D Thomaston, CT
06787 USA +1-203-755-1666
Page 1 of 1
FlexTable: Junction Table
Label Elevation
(ft)
J-7 17.00
J-8 20.00
J-9 18.00
J-10 16.50
J-11 16.50
J-12 17.00
J-13 17.00
J-14 18.00
J-15 19.00
J-16 20.00
J-17 17.00
J-19 16.50
J-20 16.50
J-21 19.00
WTC - Fireflow.wtg
Bentley Systems, Inc. Haestad Methods Solution
Center
WaterCAD
[24.00.00.26]
1/15/2025 76 Watertown Road, Suite 2D Thomaston, CT
06787 USA +1-203-755-1666
Page 1 of 1
FlexTable: Pipe Table
Label Length
(ft)
Diameter
(in)
Material Hazen-Williams C Has User
Defined Length?
P-8 1 99.0 PVC 130.0 True
P-9 43 16.0 PVC 130.0 False
P-10 299 12.0 PVC 130.0 False
P-11 534 12.0 PVC 130.0 False
P-12 454 12.0 PVC 130.0 False
P-13 61 12.0 PVC 130.0 False
P-14(1)345 12.0 PVC 130.0 False
P-14(2)119 12.0 PVC 130.0 False
P-15 90 12.0 PVC 130.0 False
P-16 371 8.0 PVC 130.0 False
P-17 453 8.0 PVC 130.0 False
P-18 733 8.0 PVC 130.0 False
P-19 848 8.0 PVC 130.0 False
P-20 54 8.0 PVC 130.0 False
P-21 517 8.0 PVC 130.0 False
WTC - Fireflow.wtg
Bentley Systems, Inc. Haestad Methods Solution
Center
WaterCAD
[24.00.00.26]
1/15/2025 76 Watertown Road, Suite 2D Thomaston, CT
06787 USA +1-203-755-1666
Page 1 of 1
Pump Definition Detailed Report: Test Hydrant
Element Details
ID 49 Notes
Label Test Hydrant
Pump Curve
Flow
(gpm)
Head
(ft)
0 157.10
500 153.60
1,000 144.40
1,500 130.10
2,000 111.10
2,500 87.60
3,000 59.70
3,500 27.60
Pump Efficiency Type
Pump Efficiency Type Best Efficiency
Point
Motor Efficiency 100.0 %
BEP Efficiency 100.0 %Is Variable Speed Drive?False
BEP Flow 0 gpm
Transient (Physical)
Inertia (Pump and Motor)0.000 lb·ft²Specific Speed SI=25,
US=1280
Speed (Full)0 rpm Reverse Spin Allowed?True
WTC - Fireflow.wtg
Bentley Systems, Inc. Haestad Methods Solution
Center
WaterCAD
[24.00.00.26]
1/15/2025 76 Watertown Road, Suite 2D Thomaston, CT
06787 USA +1-203-755-1666
Page 1 of 2
Pump Definition Detailed Report: Test Hydrant
WTC - Fireflow.wtg
Bentley Systems, Inc. Haestad Methods Solution
Center
WaterCAD
[24.00.00.26]
1/15/2025 76 Watertown Road, Suite 2D Thomaston, CT
06787 USA +1-203-755-1666
Page 2 of 2