HomeMy WebLinkAboutGE Aerospace_ESC Design Narrative_R1 GE Aerospace – North Gate Improvements Project No. 6260230100 WSP April 4, 2025 Page i GE AEROSPACE – NORTH GATE IMPROVEMENTS EROSION AND SEDIMENT CONTROL PLAN GE AVIATION WILMINGTON, LLC ISSUED FOR PERMIT WSP PROJECT NO.: 6260230100 DATE: APRIL 04, 2025 WSP USA, INC. 5710 OLEANDER DRIVE, SUITE 110 WILMINGTON, NC 28403 T: (910) 452-1185 WSP.COM WSP USA, Inc 5710 Oleander Drive, Suite 110 Wilmington, North Carolina 28403 Tel (910) 452-1185 WSP www.wsp.com April 4, 2025 Licensure: NC Engineering F-0165 Page ii April 04, 2025 Prepared By: WSP USA, Inc. 5710 Oleander Drive. Wilmington, NC 28403 Prepared For: GE Aviation Wilmington, LLC 3905 Castle Hayne Road Castle Hayne, NC 28429 WSP Project No.: 6260230100 Ryan Spiker, PE Senior Civil Engineer GE Aerospace – North Gate Improvements WSP Project No. 6260230100 Page iii TABLE OF CONTENTS EROSION CONTROL DESIGN NARRATIVE ........... 1 Background Information ........................................................ 1 Project Description .................................................................. 1 Erosion and Sedimentation Control Narrative ........................ 2 Erosion Control Devices Notes ................................................. 2 General Notes ............................................................................. 2 Standards .................................................................................... 3 Seeding ........................................................................................ 3 Construction/Erosion Control Sequence ................................. 4 CONSTRUCTION AND EROSION CONTROL STAGE 1: ................................... 4 CONSTRUCTION AND EROSION CONTROL STAGE 2: ................................... 4 CONSTRUCTION AND EROSION CONTROL STAGE 3: ................................... 4 APPENDICES APPENDIX A – SITE LOCATION MAP APPENDIX B - USGS MAP APPENDIX C – USDA SOIL SURVEY MAP APPENDIX D – NOAA ATLAS 14 RAINFALL DATA APPENDIX E – DRAINAGE AREA MAPS APPENDIX F – CALCULATIONS APPENDIX G – PROPERTY DEED GE Aerospace – North Gate Improvements WSP Project No. 6260230100 Page 1 EROSION CONTROL DESIGN NARRATIVE BACKGROUND INFORMATION As part of the land separation between GE Aerospace and GE Vernova, GE Aerospace plans to redevelop the existing north gate entrance of their facility to enhance traffic flow and comply with the requirements as part of the separation. The redevelopment will include the creation of a dedicated truck lane, a new visitor parking lot, and the relocation of the existing key card reader closer to the guard house. The project is located at 3905 Castle Hayne Road in New Hanover County, North Carolina. It is located 0.32 miles north of the Castle Hayne Road and Interstate I-140 overpass. Access to the site will be via the existing site entrance from Castle Hayne Road. The proposed improvements as shown in these drawings will further support the compliance requirements between GE Aerospace and GE Vernova. The limits of disturbance for the project area falls entirely within Industrial District (I-2) zoning according to New Hanover County Geographical Information Systems (GIS). A copy of the United States Geological Survey (USGS) map is attached (Appendix B) indicating the project vicinity and general drainage patterns in the area. The United States Department of Agriculture (USDA) soil survey map (Appendix C) indicates the underlying soils within the project area are predominantly Onslow Loamy Fine Sand (On) and Urban Land (Ur). The Hydraulic Soil Group Classification of Onslow Loamy Fine Sand is A. Stormwater runoff from the site discharges to an existing NPDES permitted outfall 15 (NPDES Permit NCS000617) prior to discharging to Prince George Creek (Stream Index: 18-74-53, water surface classification C, Sw), which is located within the Cape Fear River Basin. PROJECT DESCRIPTION The intent of this project is to redevelop the existing north gate entrance, parking lot and add a dedicated truck lane to improve the traffic conditions entering and exiting the site. The project is located at GE Aerospace in New Hanover County, North Carolina.  Total Proposed Limits of Disturbance: 1.29 acres GE Aerospace – North Gate Improvements WSP Project No. 6260230100 Page 2 EROSION AND SEDIMENTATION CONTROL NARRATIVE The E&SC measures for this project involve the placement of a variety of erosion and sediment control devices at strategic locations throughout the area. These measures include: 1) Construction Entrance 2) Temporary Silt Fence 3) Rock Pipe Inlet Protection 4) Wattle/ Check Dam 5) Rip Rap Apron 6) Sediment Tube Inlet Protection 7) Seedbed and Seeding Specifications 8) Tree Protection Signage 9) Tree Protection Fencing These measures are to be installed and maintained prior to any disturbance. Additional control devices may be required during work in order to control erosion and/or offsite sedimentation. All temporary control measures shall be removed once construction is complete and the site is stabilized. EROSION CONTROL DEVICES NOTES 1) Placement of the erosion and sediment control measures shall be as indicated on the plans and in accordance with the details. 2) Erosion and sediment control measures shall be constructed and maintained per the details and NCDEQ Regulations. GENERAL NOTES 1) All work and materials shall comply with all GE Aerospace, New Hanover County standards, state and federal regulations and codes, and O.S.H.A. standards. 2) The contractor shall assume sole and complete responsibility for job site conditions during the course of construction of this project, including safety of all persons and property; this requirement shall apply continuously and is not limited to normal working hours. 3) Contractor is responsible for placing barricades, using flagmen, etc. as necessary to ensure safety to the public. 4) The contractor shall maintain an ongoing dust control program, including watering of disturbed areas as needed, in order to conform with the latest state and federal air pollution regulations. 5) Contractor shall schedule work and material deliveries so that stored material quantities on the job site shall be minimized. 6) All trenches shall be properly backfilled at the end of each workday. The contractor shall be responsible for the daily removal of all construction materials spilled on paved streets, onsite, and offsite. GE Aerospace – North Gate Improvements WSP Project No. 6260230100 Page 3 7) The contractor shall at all times during construction, protect from damaging existing improvements on and around the site, including, but not limited to, asphalt pavements, overhead power lines and other utilities within the project area. 8) All erosion control measures shall be constructed in accordance with North Carolina Department of Environmental Quality (NCDEQ) regulations. 9) Contractor to verify the location of all existing utilities prior to beginning construction. Any utilities damaged during construction shall be repaired immediately with no additional cost to the owner. Contractor to call NC 811 or their successors at 1-800-632- 4949 prior to excavation. Contractor shall notify GE Aerospace and engineer immediately in the event any underground obstacle requiring deviation from the plan is encountered. 10) Contractor shall exercise caution in working around overhead lines, as lines may be energized during construction. 11) Contractor shall provide proper secondary containment for any fuel stored on-site. Construction equipment shall be placed on proper and adequate containment when not in use. 12) Surplus excavated soil material to be removed from site and disposed of by contractor in accordance with applicable rules and regulatory requirements. 13) Temporary storage of contaminated soil shall be on 10-mil thick plastic and bermed to prevent runoff. A plastic cover of at least 10-mil shall be used to eliminate the generation of leachate. 14) All disturbed areas shall be smoothly graded to promote positive drainage and stabilized with topsoil, seed, and mulch. If settlement occurs, topsoil, seeding, and mulch shall be repeated until settlement subsides. (See erosion and sediment control details and specifications.) 15) The contractor shall verify horizontal and vertical survey control prior to staking out construction. Any discrepancies shall be brought to the attention of the engineer and GE Aerospace prior to proceeding with work. 16) Any property line monumentation disturbed during construction shall be replaced solely at the contractor's expense. 17) There are no known wetlands present within the project LOD and no wetland impacts are proposed. STANDARDS Erosion and sedimentation control measures shall be in accordance with the North Carolina Sedimentation Pollution Control Act of 1973. Construction details and specification within this plan were derived from the erosion and sediment control planning and design manual dated May 2013, prepared by the North Carolina Sedimentation Control Commission, North Carolina Department of Environmental Quality (NCDEQ) And North Carolina Agricultural Extension Service (NCAES). SEEDING 1) See seeding details and specifications on Plan Sheet C11.0. 2) Temporary and permanent seeding shall be performed as per NCDEQ requirements within 14 calendar days of completion of grading. Areas that fall under more stringent criteria shall be stabilized within seven calendar days. GE Aerospace – North Gate Improvements WSP Project No. 6260230100 Page 4 CONSTRUCTION/EROSION CONTROL SEQUENCE CONSTRUCTION AND EROSION CONTROL STAGE 1: 1) Obtain all necessary permit approvals prior to any land disturbance activity. 2) Schedule a pre-construction meeting at least 48 hours prior to the start of any construction activities with New Hanover County erosion control inspector, GE Aerospace, and engineer of record prior to the commencement of land disturbing activity. 3) The contractor shall clearly demarcate the limits of disturbance with stakes, ribbons, or other appropriate visual marking devices. The limits of disturbance shall be maintained for the duration of the project. No land disturbance shall occur outside the limits of disturbance indicated on the drawings. 4) Install temporary construction entrances, silt fence, tree protection fencing and inlet protection as shown in the drawings. 5) Commence demolition. Any fence noted as demolition must have the new fence installed during the same working day. In no case will the site be left unsecured without the new fencing installed. 6) Commence grading operations for dedicated truck lane. 7) Upon completion of grading operations, contractor shall pave the truck lane. CONSTRUCTION AND EROSION CONTROL STAGE 2: 1) Maintain erosion control measures from stage 1 into stage 2 as shown. 2) Install 12" RCP pipe collar and extend storm as shown in the drawings. 3) Commence grading operations of the parking lot and install proposed pavement, striping, and wheel stops. 4) Remove existing guard shack, and relocate existing key card reader. 5) Perform a mill and overlay on Thomas Edison as shown in the drawings. 6) Establish permanent ground cover and stabilize disturbed areas. CONSTRUCTION AND EROSION CONTROL STAGE 3: 1) After site is permanently stabilized, contact the erosion control inspector prior to removal or modification of erosion control devices. 2) Remove all temporary erosion control measures and provide permanent seeding where temporary measures have been removed and ground cover is not adequate. 3) Contact DEMLR for a close out inspection once all erosion control measures have been removed and the site has been permanently stabilized. Contractor demobilizes from site. 4) When the project is complete, the permittees shall contact DEMLR to close out the E&SC plan. After the DEMLR informs the permittee of the project close out, via inspection report, the permittee shall visit deq.nc.gov/NCG01to submit an electronic Notice of Termination (E-NOT). A $120 annual general permit fee will be charged until the E-NOT has been filled out. APPENDIX SITE LOCATION MAP APPENDIX USGS MAP APPENDIX USDA SOIL SURVEY MAP APPENDIX NOAA ATLAS 14 RAINFALL DATA APPENDIX DRAINAGE AREA MAPS LOD LOD L O D LOD LO D LOD PROJECT AREA CA S T L E H A Y N E R D CENTENNIAL DR HERMITAGE RD HWY-1 4 0 GE AEROSPACE FACILITY TOTAL DA: 496.18 ACRES ON-SITE DA: 89.41 ACRES (WITHIN GE AEROSPACE BOUNDARY) OFF-SITE DA:406.77 ACRES (INLCUDING GE VERNOVA) CH A I R R D GLADIOLUS RD SLED G E R D POTENTIAL INTERMITTENT STREAM (H) POTENTIAL PERENNIAL STREAM (I) DRAINS TO PRINCE GEORGE CREEK APPROXIMATE LOCATION OF EXISTING NPDES OUTFALL 15 AND 15i 20 20 40 4040 40 40 40 40 40 40 4 0 404040 ISSUE/REVISION DESCRIPTIONYREVDM DR.ENG. SCALE HORIZONTAL: SCALE VERTICAL: SHEET TITLE: PROJECT: DATE: SHEET NO. REVISION NO. PROJECT NO.: APPROVED BY: RS D 04.04.2025 GE AEROSPACE NORTH GATE IMPROVEMENTS WILMINGTON, NORTH CAROLINA 6260230100 DRAWN BY: CP REVIEWED BY: RS SEAL:SEAL: WSP USA INC. 5710 OLEANDER DRIVE, SUITE 110 WILMINGTON, NC 28403 TEL:(910) 452-1185 LICENSURE: NC ENG: F-0165 NC GEOLOGY: C-557 ENGINEER:CLIENT: 3905 CASTLE HAYNE RD. CASTLE HAYNE, NC 28429 FOR REVIEW ONLY - NOT FOR CONSTRUCTION FOR REVIEW ONLY - NOT FOR CONSTRUCTION EX. 1 N/A 1"=20' 0 SCALE: 1"=400' (Horiz.) 800'400'400' LEGEND: DRAINAGE AREA BOUNDARY SURVEYED WETLANDS SURVEYED STREAMS PROPERTY LINE LIMITS OF DISTURBANCELODLOD DRAINAGE AREA MAP - EXHIBIT 1 9039927.43 9264128.47S.MH 9264227.60S.MH 92801 N: 210305.828' E: 2324675.097' EL:27.950' TRV FLY 92802 N: 210301.245' E: 2324835.038' EL:27.658' TRV FLY 92803 N: 209994.221' E: 2324893.750' EL:27.924' TRV FLY 9310227.30BUSH 9310327.05BUSH 9310427.06BUSH 9310527.16BUSH 9312028.82SP 9313529.03LSA 9313628.81LSA 9313728.89LSA 9313828.96LSA 9323429.52LSA 9323529.75LSA 9323629.65LSA 9323729.81LSA 9327529.67STMP X X X X X X X X X X X X X 22" OAK 16" OAK 30" OAK 18" SYCAMORE 18" GUM 36" OAK 26" SYCAMORE 30" SYCAMORE 20" MAGNOLIA 26" MAGNOLIA 20" GUM 32" PINE 24" GUM 24" OAK 8" OAK 26" OAK 28" OAK 32" OAK 10" SYCAMORE 8" SYCAMORE THOM A S E D I S O N A V E N U E CA S T L E H A Y N E R O A D 4 - 4 8 " C M P ' S 30 28 2 7 2728 2 6 29 2020 251919 2 1 2 2 2 3 24 26 27 28 20 20 25 25 30 21 21 22 22 23 23 24 24 26 26 27 27 28 28 2 9 29 28 GUARD HOUSE 9039927.43 9264128.47S.MH 9264227.60S.MH 92801 N: 210305.828' E: 2324675.097' EL:27.950' TRV FLY 92802 N: 210301.245' E: 2324835.038' EL:27.658' TRV FLY 92803 N: 209994.221' E: 2324893.750' EL:27.924' TRV FLY 9310227.30BUSH 9310327.05BUSH 9310427.06BUSH 9310527.16BUSH 9312028.82SP 9313529.03LSA 9313628.81LSA 9313728.89LSA 9313828.96LSA 9323429.52LSA 9323529.75LSA 9323629.65LSA 9323729.81LSA 9327529.67STMP X X X X X X X X X X X X X 22" OAK 16" OAK 30" OAK 18" SYCAMORE 18" GUM 36" OAK 26" SYCAMORE 30" SYCAMORE 20" MAGNOLIA 26" MAGNOLIA 20" GUM 32" PINE 24" GUM 24" OAK 8" OAK 26" OAK 28" OAK 32" OAK 10" SYCAMORE 8" SYCAMORE THOM A S E D I S O N A V E N U E CA S T L E H A Y N E R O A D 4 - 4 8 " C M P ' S 29 2 9 2 9 29 29 28 27 2 6 2 7 2 8 29 > > > > >> > > >> > > >> > > 30 30 29 29 28 28 28 29 2 8 2 9 28 28 29 FLOWS TO NPDES PERMITTED OUTFALL 15 (NCS000617) FLOWS TO NPDES PERMITTED OUTFALL 15 (NCS000617) 4 - 4 8 " C M P ' S 28 29 30 31 3 0 2 5 21 2 9 28 TP T P TP LOD LOD LO D LO D LOD L O D L O D L O D L O D L O D L O D LOD LOD LOD LOD LOD LOD LOD LOD LOD L O D L O D L O D L O D SF SF S F S F S F S F S F S F S F SF SF SF SF LOD LOD LOD LOD LOD LOD LOD S F S F SF SF SF SF SF SF SF SF SF SF SF SF S F DRAINAGE AREA DA-6 AREA = 0.153 ACRES DRAINAGE AREA DA-5 AREA = 0.52 ACRES DRAINAGE AREA DA-4 AREA = 0.069 ACRES DRAINAGE AREA DA-1 AREA = 0.232 ACRES DRAINAGE AREA DA-2 AREA = 0.044 ACRES DRAINAGE AREA DA-3 AREA = 0.263 ACRES POA-02 CUMULATION OF DA-2 & DA-3 POA-01 CUMULATION OF DA-1, DA-4, & DA-5 18" RCP (87LF @ 0.50%) 18" RCP (157LF @ 0.50%) POTENTIAL INTERMITTENT STREAM (STREAM H) POTENTIAL PALUSTRINE FORESTED WETLAND (WETLAND A) ISSUE/REVISION DESCRIPTIONYREVDM DR.ENG. SCALE HORIZONTAL: SCALE VERTICAL: SHEET TITLE: PROJECT: DATE: SHEET NO. REVISION NO. PROJECT NO.: APPROVED BY: RS - 04.04.2025 GE AEROSPACE NORTH GATE IMPROVEMENTS WILMINGTON, NORTH CAROLINA 6260230100 DRAWN BY: CP REVIEWED BY: RS SEAL:SEAL: WSP USA INC. 5710 OLEANDER DRIVE, SUITE 110 WILMINGTON, NC 28403 TEL:(910) 452-1185 LICENSURE: NC ENG: F-0165 NC GEOLOGY: C-557 ENGINEER:CLIENT: 3905 CASTLE HAYNE RD. CASTLE HAYNE, NC 28429 FOR REVIEW ONLY - NOT FOR CONSTRUCTION FOR REVIEW ONLY - NOT FOR CONSTRUCTION EX. 2 N/A 1"=20' 0 SCALE: 1"=20' (Horiz.) 40'20'20' LEGEND PROPERTY LINE EXISTING STORM PIPE NOTES: ·RUNOFF FROM PROPOSED SITE FLOWS TO NPDES PERMITTED OUTFALL 15 (NCS000617) PROPOSED MAJOR CONTOUR PROPOSED MINOR CONTOUR PROPOSED STORM PIPE EXISTING MAJOR CONTOUR EXISTING MINOR CONTOUR 20 19 20 19 DRAINAGE FLOW ARROW DRAINAGE AREA - SILT FENCE DRAINAGE AREA - INLETS DRAINAGE AREA MAP - EXHIBIT 2 APPENDIX CALCULATIONS PROJECT: 4/3/2025 DESCRIPTION: RRAP-1 GE AEROSPACE ENGINEER: CP RS PROJECT NO. US-EI-6260-23-0100 RS Outlet Flowrate 7.12 cfs Pipe Diameter 18 inches Outlet Pipe Slope 0.5 percent Des. flow velocity 4.45 ft/sec Zone from graph above =1 Outlet Pipe Diameter 18 in.Length =6.0 ft. Outlet Flowrate 7.1 cfs Width =4.5 ft. Outlet Velocity 4.5 ft/sec Max. Stone Dia =6 in. Material =Class A Thickness =9 in. Zone Material Max Stone Dia.Thickness Length Width 1 Class A 6 9 4 x D(o) 3 x D(o) 2 Class B 12 18 6 x D(o) 3 x D(o) 3 Class I 17 26 8 x D(o) 3 x D(o) 4 Class II 23 35 10 x D(o) 3 x D(o) Notes: 1. Calculations based on NY DOT method - Section 8.06.05 through 8.06.06 in NCDENR ESC Manual. CHECKER: DATE PREPARED: GE AEROSPACE NORTH GATE IMPROVEMENTS ENERGY DISSIPATOR DESIGN WORKSHEET WSP USA, Inc. ORIGINATOR: ENGINEER: PREPARED FOR : 4.5 ft/sec 0 5 10 15 20 25 0 1 2 3 4 5 6 7 8 9 10 Ve l o c i t y ( f t / s e c ) Pipe diameter (ft) Figure 8.06.b.1 Zone 1 Zone 2 Zone 3 Zone 4 Zone 5 Zone 6 Zone 7 Page 1 of 1 PROJECT:DATE PREPARED: 4/1/2025 DESCRIPTION: PREPARED FOR :GE AEROSPACE ENGINEER: PREPARED BY :CP PROJECT NO. REVIEWED BY: RS SILT FENCE Drainage 10-Yr Intensity C Value Q 10 Velocity4 No. Area ac inches/hour cfs ft % ft/sec ft SF-1 0.26 7.69 0.75 1.52 296 0.50%0.45 YES 0.58 YES SF-2 0.04 7.69 0.75 0.25 62 1.60%0.44 YES 0.24 YES SF-3 0.15 7.69 0.30 0.35 357 0.50%0.41 YES 0.13 YES SF-4 0.30 7.69 0.75 1.73 130 2.80%0.88 YES 0.44 YES Notes: 1. Calculation taken from Section 6.62 of the NCDENR ESC Manual. 2. Flow Depth taken from Section 6.62 of the NCDENR ESC Manual. 3. Flow Velocity check per Appendix 8, Table 8.05d of the NCDENR ESC Manual. 4. Velocity calculated per Manning's Equation. 5. Flow Depth calculated per Manning's Equation. Depth < 1.5'?Flow Depth5 SILT FENCE SILT FENCE CALCULATION TABLE WSP USA Inc. GE AEROSPACE NORTH GATE IMPROVEMENTS Silt Fence Calculations US-EI-6260-23-0100 Longitudinal Slope of Silt Fence (CAD) Silt Fence Length (CAD) Velocity < 2.5 fps?3 APPENDIX PROPERTY DEED