HomeMy WebLinkAboutBond EstimateSidbury Station, Phase 2B
Engineer's Bond Estimate
63 Lots
3/18/2025
vj MCKIM&CREED
Item
Unit
Qty
Unit Cost
Cost
Sidewalks
SF
20210
$6
$121,260.00
ADA Mats
EA
16
$325
$5,200.00
Street Trees
EA
108
$250
$27,000.00
Street Signs
EA
1
$8,000
$8,000.00
Utilities - Pump Station Startup
EA
1
$10,000
$10,000.00
Erosion Control - Seeding
AC
5
$3,200
$16,000.00
Asphalt
SY
10783
11.68
$125,945.44
Sub -Total $313,405.44
10% Contingency $31,340.54
Total $344,745.98
SEAL 25503