HomeMy WebLinkAboutThe Covenant Senior Housing - TRC Comments 4.30.2021 The Covenant Senior Housing – TRC Review Page | 1 To: Shane Lippard, PE – Right Angle Engineering, PC (raepcsl@bellsouth.net) Keith Walker – The Covenant Senior Housing, LLC (kwalker@eccdi.com) Pastor Robert L. Campbell – New Beginning Christian Church (nbcexec@gmail.com) From: Brad Schuler Senior Planner Date: April 30, 2021 Subject: The Covenant Senior Housing – Major Site Plan – TRC Review The following comments have been received for the May 5, 2021 TRC meeting. Additional comments may be made upon further review of subsequent revisions. Please note: following the TRC meeting, a revised preliminary plan addressing each of the below items must be resubmitted prior to receiving plan approval. Planning, Brad Schuler 910-798-7444 1. Please update the plan with the following general corrections: a. Please label the parking space length on the site plan. b. Please add a drive aisle/parking cross section to the site plan. 2. Please add the parking calculations to the plan (1.5 spaces per 1-bedroom units, and 2 spaces per 2+ bedroom units). Also, the UDO has recently been updated to provide addition flexibility in the required minimum parking standards. If needed, parking can be reduced via a parking demand study. See Section 5.1.3 for more information. 3. Please add the required recreation space calculation to the site plan and delineate those areas on the site plan. 4. A 50-foot building setback and 40-foot buffer is required along the southern and eastern property lines abutting the Rachel’s Place subdivision. 5. Prior to any land disturbance activities, a tree removal permit is required for any regulated trees proposed to be removed. Please provide a tree removal plan listing all regulated trees to be removed. Removal of significant or specimen trees will require mitigation. 6. Please add the calculations on the landscape plan for street yard, parking lot interior, and foundation plantings. Per the approved SUP plan, the primary street yard was to be applied along Holland Drive and secondary street yard was to be applied along Alex Trask Drive. 7. The existing vegetation within the street yard and buffer areas can be credited toward the required plantings. Additional plantings will be required in the areas where the existing vegetation does not comply with the landscaping standards. 8. Please note the type and height of the dumpster screening. 9. The bufferyard landscaping along buildings 1 and 2 is not required. The Covenant Senior Housing – TRC Review Page | 2 10. All exterior lighting in the project shall be designed not to exceed 0.5 foot candles when measured at the property lines abutting the existing single-family developments and 2.0 foot candles at the property lines abutting all other uses (see Section 5.5). Please provide documentation to confirm compliance with this regulation. 11. Please include the roadway connection to Blue Clay Road including the connection to the road stub in the Rachel’s Place subdivision. A cross section of this road was included on the approved SUP plan. Installation of this road can be bonded. 12. Per the SUP for the project, a 20-foot pedestrian access easement must be dedicated along Blue Clay Road for the purposes of installing a future multi-use path. 13. Section 5.3.4.C of the UDO requires a minimum of 15 trees at least 2” DBH must be retained or planted on the parcel where development occurs for each acre or proportionate area disturbed. Landscaping required to comply with other sections of the ordinance (streetyard, buffering, etc.) can be credited to meet this standard. Fire Services, Ray Griswold 910-798-7448 1. Are the buildings sprinklered? If so FDC's are required within 100 feet of fire hydrants. 2. No Gates / Traffic Calming Devices allowed unless approved by the TRC 3. Section 510 study is required per the 2018 NC Fire Code for first responder radio coverage 4. Please follow the guidelines of the 2018 NC Fire Code Appendix J - Building Information Signs NHC Engineering, Galen Jamison 910-798-7072 1. A land disturbing permit and a modification to the stormwater system authority to construct (ATC #574-03/08/13) is required for this project. Please submit for permits as the design is completed. 2. Any offsite drainage routed through the site to the east will need a drainage easement to assist with the mission of new Stormwater Services department starting in July. The previously permitted project’s easement doesn’t appear to be recorded. 3. The proposed roadway appears to be a combination of crowned roadway and depressed center as some drop inlets are located at the end of parking stalls. To avoid grading contractor confusion, please indicate all transitions between spill and catch curb. Cape Fear Public Utility Authority, Bernice Johnson 910-332-6620 1. CFPUA plan review required. 2. CFPUA water and sewer available. 3. CFPUA Meter Sizing Form will be required. Environmental Health, Marie Hemmen 910-798-6664 This property will be served by CFPUA water and sewer. Per Env. Health Records and a review of the aerial of the site, it does not appear that any private water supply wells or septic systems will be affected by the proposed development. NCDOT, Patrick Wurzel 910-398-9100 These preliminary comments and are based on the plans as submitted for the proposed site and are subject to further review upon receipt of any additional information. Subsequently, additional comments and/or requirements may be necessary for this site. 1. A NCDOT Driveway Permit is required. Submit a plan in accordance with pages 14 and 15 of the Policy on Street and Driveway Access to North Carolina Highways to include access locations The Covenant Senior Housing – TRC Review Page | 3 within 500’ of the proposed access on both sides of the State road. Submit to the local NCDOT District Engineer’s Office. 2. A NCDOT Encroachment Agreement is required for any utility connections or installation within NCDOT right-of-way. 3. NCDOT Driveway Permits are now submitted through the NCDOT Driveway website. https://connect.ncdot.gov/municipalities/Utilities/Pages/help.aspx WMPO, Kayla Grubb 910-341-7890 1. NCDOT Projects: a. Tip Projects in the Area: U-5863 i. Project Description: NC 133 (Castle Hayne Road) from I-140/US 17 (WILMINGTON BYPASS) TO SR 1310 (DIVISION DRIVE) IN WILMINGTON. WIDEN TO MULTI-LANES ii. Construction Date: 2026 2. WMPO 2045 Projects: a. Projects in the area: RW-26 i. Project Description: The purpose of this project is to improve safety on Blue Clay Road between North Kerr Avenue and US117/NC132/North College Road and bring the roadway up to current design standards. 3. TIA: A TIA will not be required. Planning (Addressing), John Townsend 910-798-7443 1. Unduplicated street name needed for addressing. a. Have several road name options. 2. Number of units per building and by floor will be needed for unit assignment. a. Unit numbers assigned by Planning staff. 3. Contact planning staff for street name approval and addressing. Comments not received at this time from: Emergency Services & E911, Steve Still NCDEQ, Chad Coburn New Hanover Soil & Water, Dru Harrison USACE, Rachel Capito NCDEMLR, Dan Sams DCM, Tanya Pietila New Hanover County Schools, Laura Severt