Legacy Landing Phase 2 – Major Subdivision – TRC Review
Page | 1
To: Marlowe Foster, Cape Fear Habitat for Humanity, marlowefoster@capefearhabitat.org
From: Ryan Beil, Development Review Planner
Date: June 18, 2025 TRC Review
PID#: R02500-003-097-000
Egov# SUBPP-25-0025
Subject: Legacy Landing Phase 2- Preliminary Plan TRC Review
The following comments have been received for the June 18, 2025, TRC meeting. Additional comments
may be made upon further review of subsequent revisions.
Please note: following the TRC meeting, a revised preliminary plan addressing each of the items below
must be resubmitted before receiving preliminary plan approval.
Planning, Ryan Beil 910-798-7444
1. General Comments
a. Currently Conditionally Zoned R-10, housing type proposed are single-family detached
and single-family attached.
b. Phase II is a performance subdivision.
i. Density for Performance Residential: 3.1 dwelling units per acre within R-10 in a
Performance Residential Subdivision.
ii. There are no Class IV soils or wetlands on the property.
iii. Density calculations:
1. Total site acreage = 7.65 acres
2. R-10 Zoning District allows maximum 3.1 dwelling units per acre under
performance residential subdivision.
3. Developable site acreage (7.65) * zoning density (3.1) = 24 units
c. As this project was part of a conditional rezoning, the conditions on the site are as follows:
i. A six foot tall solid wood privacy fence shall be installed along the eastern
boundary of 1716 Rockhill Road also identified as New Hanover County Tax Parcel
ID R02500-003-102-000
ii. The permitted density range is 0 dwelling units per acre to a maximum of 3.1
dwelling units per acre. Planning staff is authorized to administratively approve
reductions in density within the permitted range.
Legacy Landing Phase 2 – Major Subdivision – TRC Review
Page | 2
iii. The housing types in the development shall be limited to detached single-family
dwellings and dual unit attached dwellings as defined in Section 2.3 of the Unified
Development Ordinance.
d. Staff recommend including the location of traffic calming devices on the preliminary
plans. Installation of traffic calming devices are not required, but including potential
locations on the plan ensures the future HOA / owners will have the opportunity to install
them without conducting a traffic study.
2. UDO Section 5.1, Parking and Loading
a. Per table 5.1.2.A in the County UDO, there are 2 off street parking spots required for each
dwelling, which the site plan shows meaning the requirement is met.
3. UDO Section 5.2, Traffic, Access and Connectivity
a. Please note that no building permit for any structure shall be issued which requires
NCDOT approval for a Driveway Permit until NCDOT has issued the permit approval.
Evidence of approval shall accompany the application for building permit.
4. UDO Section 5.3, Tree Retention
a. Note: Land disturbance permits can be issued by county Engineering before a Tree
Removal Permit is approved by Planning. However, any trees removed before the Tree
Removal Permit is issued may result in enforcement action under Section 5.3.2 of the
Unified Development Ordinance to include prohibiting any development of the site for 3
to 5 years.
b. Are any trees planned to be removed for this project? If so, please apply for a Tree
Removal Permit: https://www.nhcgov.com/DocumentCenter/View/1239/Tree-Removal-
Permit-PDF
5. UDO Section 5.4, Landscaping and Buffering
a. Landscaping and buffering are only required for the amenity areas, however a listed
condition from this conditional rezoning requires a six foot tall solid wood privacy fence
shall be installed along the eastern boundary of 1716 Rockhill Road also identified as New
Hanover County Tax Parcel ID R02500-003-102-000.
b. Please show the location of the fence on the site plan to ensure the condition is met.
6. UDO Section 5.5, Lighting
a. Please note under 5.5.2.A that a lighting plan is not required for single-family residential
projects and the county does not require streetlights however a lighting plan is required
for any amenity area, if any lighting is planned there.
Legacy Landing Phase 2 – Major Subdivision – TRC Review
Page | 3
7. UDO Section 5.6, Signs
a. There appears to be an area of open space near the entrance, please confirm if this will
be where the sign is placed.
8. UDO Section 5.7, Conservation Resources
a. Per the New Hanover County Conservation Resource Map there are no Conservation
Resources present on this property.
9. UDO Section 5.8, Open Space Requirements
a. There is .967 of an acre, or 42,129 square feet, of open space provided. The open space
requirement from our UDO in performance residential development is 20% of acreage,
which in this circumstance would equate to 24,219 square feet or .56 acres, meaning the
open space requirement has been met.
10. UDO Article 6, Subdivision Design and Improvements.
a. R-10 developments require sidewalks with a 5’ minimum width, please label them
sidewalks on the site plan.
b. Block length is below listed maximum of 1,000 ft.
c. Per the County UDO any subdivision shall achieve a connectivity ratio of no less than 1.40.
11. UDO Article 9, Flood Damage Prevention
a. No part of the property is in a flood zone.
NHC Fire Services, Ray Griswold 910-798-7448
1. Fire finals required
2. County Fire approves site plan
NHC Soil & Water Conservation, Dru Harrison 910-798-7135
1. Comments attached
NHC Engineering, Galen Jamison 910-798-7072
1. A land disturbing permit issued by the County is required for this project since the anticipated
limits of disturbance is greater than 1 acre. Please digitally submit the permit application
documentation with requisite review fees for County issued permit directly to
gjamison@nhcgov.com. Application and forms can be found at
https://www.nhcgov.com/249/Sediment-Erosion-Control.
Legacy Landing Phase 2 – Major Subdivision – TRC Review
Page | 4
2. A revision to County stormwater permit STMW-21-0003 will be required for this project. Please
digitally submit the permit applications documentation with requisite review fees to the COAST
online permit portal (https://newhanovercountync-
energovpub.tylerhost.net/apps/selfservice#/home). Applicable forms can be found at
https://www.nhcgov.com/251/Stormwater however the application form is not required as the
information will be gathered by the COAST portal.
3. Please contact the State for their stormwater permit requirements. A high density permit is
anticipated.
NHC Environmental Health, Dustin Fenske 910-798-6732
1. Site plan reflects connection to public water. Proposed infrastructure does not violate setbacks
to any surrounding properties drinking water wells.
NHC Addressing, McCabe Watson 910-798-7068
1. Each dwelling will need its own individual address.
2. Please contact me for address assignments following TRC approval.
Cape Fear Public Utility Authority, Bernice Johnson 910-332-6620
1. CFPUA TRC Comments provided are preliminary comments only.
2. Utility Plan review will be required by CFPUA. CFPUA is moving toward becoming paperless.
When ready to submit plan review package, upload all documents to
https://www.cfpua.org/FormCenter/Engineering-3/Engineering-Plan-Review-103.
3. CFPUA sewer is available
4. CFPUA water and sewer are available via a mainline extension.
5. Capacity is dependent on the analysis of the pipe collection system (gravity and force mains).
6. A capacity determination can be provided upon submittal of the NC DWQ FTA/FTSE Application
Form and a Preliminary Plan, this determination does not guarantee capacity.
7. Capacity is issued to projects on a first come, first serve basis, when capacity is available, the
plans meet Authority requirements, and the NC DWQ FTA/FTSE forms are signed by the
Authority.
NCDOT, Nick Drees 910-343-3915
1. Comments attached
WMPO, Caitlin Cerza 910-341-0107
1. Comments attached
Legacy Landing Phase 2 – Major Subdivision – TRC Review
Page | 5
Army Corps of Engineers, Brad Shaver 910-251-4611
1. The Corps does not have any records on this site. Please reach out to the ACOE if there are
wetlands impact questions.
Project information also provided to the following state agencies and non-development regulatory local
agencies for their awareness:
New Hanover County Emergency Management
New Hanover County Schools
NC Department of Environmental Quality (DEQ)
NC DEQ Division of Coastal Management
NC DEQ Division of Energy, Mineral, and Land Resources
United States
Department of
Agriculture
A product of the National
Cooperative Soil Survey,
a joint effort of the United
States Department of
Agriculture and other
Federal agencies, State
agencies including the
Agricultural Experiment
Stations, and local
participants
Custom Soil Resource
Report for
New Hanover
County, North
Carolina
Natural
Resources
Conservation
Service
Map Unit Legend (1728 Rockhill Rd)
Map Unit Symbol Map Unit Name Acres in AOI Percent of AOI
Ls Lynchburg fine sandy loam, 0 to
2 percent slopes, Atlantic
Coast Flatwoods
0.1 2.5%
On Onslow loamy fine sand 1.8 56.8%
Wo Woodington fine sandy loam 1.3 40.8%
Totals for Area of Interest 3.1 100.0%
Custom Soil
Resource Report Soil
Map (1728 Rockhill
Rd)
38
0
0
07
0
38
0
0
09
0
38
0
0
110
38
0
0
13
0
38
0
0
15
0
38
0
0
17
0
38
0
0
19
0
38
0
0
21
0
38
0
0
23
0
38
0
0
25
0
38
0
0
07
0
38
0
0
09
0
38
0
0
110
38
0
0
13
0
38
0
0
15
0
38
0
0
17
0
38
0
0
19
0
38
0
0
21
0
38
0
0
23
0
38
0
0
25
0
229
510
229
530
229
550
229
570
229
590
229
610
229
630
229
650
229
510
229
530
229
550
229
570
229
590
229
610
229
630
229
650
34° 18'
30'' N
77
°
56
'
21
'
'
W
34° 18'
30'' N
77
°
56
'
15
'
'
W
34° 18'
23'' N
77
°
56
'
21
'
'
W
34° 18'
23'' N
77
°
56
'
15
'
'
W
N Map projection: Web Mercator
Corner coordinates: WGS84
Edge tics: UTM Zone 18N WGS8490270Feet010204060
Meters
45 1800
MAP INFORMATION
The soil surveys that comprise your AOI were mapped at
1:15,800.
Warning: Soil Map may not be valid at this scale.
Enlargement of maps beyond the scale of mapping can cause
misunderstanding of the detail of mapping and accuracy of soil
line placement. The maps do not show the small areas of
contrasting soils that could have been shown at a more detailed
scale.
Please rely on the bar scale on each map sheet for map
measurements.
Source of Map: Natural Resources Conservation Service Web
Soil Survey URL:
Coordinate System: Web Mercator (EPSG:3857)
Maps from the Web Soil Survey are based on the Web Mercator projection, which
preserves direction and shape but distorts distance and area. A projection that preserves
area, such as the Albers equal-area conic projection, should be used if more accurate
calculations of distance or area are required.
This product is generated from the USDA-NRCS certified data as of the version date(s)
listed below.
Soil Survey Area: New Hanover County, North Carolina Survey Area Data: Version
26, Sep 9, 2024
Soil map units are labeled (as space allows) for map scales
1:50,000 or larger.
Date(s) aerial images were photographed: Nov 8, 2022—Dec 1, 2022
The orthophoto or other base map on which the soil lines were compiled and digitized
probably differs from the background imagery displayed on these maps. As a result,
some minor shifting of map unit boundaries may be evident.
TO: New Hanover County Planning Department, New Hanover SWCD, May 12th, 2025
FROM: Dru Harrison, Director
RE:
I HAVE REVIEWED THIS PLAN AS REQUESTED AND HAVE THESE COMMENTS: The
soils are predominantly Lynchburg fine sandy loam (Ls), Onslow loamy fine sand (On), and
Woodington fine sandy loam (Wo).
According to the booklet, “Wilmington/New Hanover Classification of soils for Septic Tank
Suitability Lynchburg, Onslow, and Woodington are Class II soils.
The Soil Survey of New Hanover County lists Lynchburg, Onslow as somewhat poorly drained,
and Woodington as poorly drained.
Woodington is on the New Hanover County Hydric Soils A list which means they are possibly
wetland areas and subject to regulation under the Clean Water Act. Lynchburg is on the Hydric
Soils B list, which means it may contain areas of wetland. It should be noted, according to the
Soil Survey of New Hanover County, the limitation for dwellings with or without basements and
for small commercial buildings is severe for all of the soils on this site. The limitations are due to
flooding and/or wetness. An adequate drainage and maintenance plan is needed for suitable
housing.
The U.S. Army Corps of Engineers has federal jurisdiction over 404 Permits and the
NCDEHNR, Dept. of Water Quality, has state jurisdiction over 401 Permits under the Clean
Water Act. Before disturbing possible wetland areas, developers should contact these agencies to
stay in compliance with State and Federal regulations.
STATE OF NORTH CAROLINA
DEPARTMENT OF TRANSPORTATION
JOSH STEIN J.R. “JOEY” HOPKINS
GOVERNOR SECRETARY
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
DISTRICT 3 ENGINEER’S OFFICE
5911 OLEANDER DRIVE, SUITE 101
WILMINGTON, NC 28403
04-11-03 COURIER
Telephone: 910-398-9100
Customer Service: 1-877-368-4968
Website: ncdot.gov
Location:
5911 OLEANDER DRIVE, SUITE 101
WILMINGTON, NC 28403
Memorandum
To: New Hanover County Technical Review Committee
Date: June 4, 2025
Subject: Lagacy Landing II – 1728 Rockhill Road
________________________________________________________________________
These are preliminary comments and are based on the plans as submitted for the proposed
site. They are subject to further review upon receipt of any additional information.
Subsequently, additional comments and/or requirements may be necessary for this site.
General Comments:
NCDOT Driveway Permits, and Encroachments are submitted through the NCDOT
Online Portal.https://connect.ncdot.gov/municipalities/Utilities/Pages/help.aspx
You can coordinate with the district office with any questions 910-398-9100.
NCDOT Driveway Permit:
An NCDOT Driveway Permit is required. Submit plans in accordance with pages 14 and
15 of the Policy on Street and Driveway Access to North Carolina Highways to include
access locations within 500’ of the proposed access on both sides of the State Road.
Submit to the local NCDOT District Engineer’s Office.
• Refer to the NCDOT checklist (included) for required documents and site plan
information.
NCDOT Encroachment Agreement:
An NCDOT Encroachment Agreement is required for any utility connections or
installations within the NCDOT right-of-way (form 16.6).
• Refer to the NCDOT UAM Manual and the NCDOT encroachment checklist for
required documents and site plan information.
An NCDOT Encroachment Agreement is required for any sidewalk or multi-use paths
installed within the NCDOT right-of-way (form 16.6).
Mailing Address:
NC DEPARTMENT OF TRANSPORTATION
DISTRICT 3 ENGINEER’S OFFICE
5911 OLEANDER DRIVE, SUITE 101
WILMINGTON, NC 28403
04-11-03 COURIER
Telephone: 910-398-9100
Customer Service: 1-877-368-4968
Website: ncdot.gov
Location:
5911 OLEANDER DRIVE, SUITE 101
WILMINGTON, NC 28403
Site Plan Comments:
Include/update the NCDOT Standard Drawings (2024) that are applicable to the
development.
Sight Triangles and Sight Distance:
• Show and label the 10’ X 70’ NCDOT sight triangles.
o No obstructions shall be placed within the NCDOT sight triangles.
• Show and label the stopping sight distance.
o No obstructions shall be placed within the stopping sight distance.
Identification Signing and Landscaping:
• Identification signing or landscape vegetation within the median and the sight
distance triangle must not obstruct the driver’s line of sight. No landscaping or
signing will be allowed to exceed 42 inches in height, measured from the Edge of
Pavement (EOP) within the median or sight triangle.
• All pylon signs in the median or sight distance triangle must provide a vertical
clear sight zone between 3 feet-6 inches and 10 feet-0 inches measured from the
EOP. Signing located within a clear recovery area shall be of a “breakaway
design.”
• Only low growing shrubbery, consistent with the NCDOT’s landscaping policies,
as contained in the publication “Guidelines for Planting Within Highway Right of
Way,” will be allowed within a landscaped median and the sight distance triangle
at the entranceway to a development, whether the street or driveway connection to
the State Highway System is designated as a public facility or not. Landscaping
within the right-of-way and sight distance triangles may require additional
approval by the District Engineer.
Label the radii for the driveway proposed driveway/driveways.
• Make sure to accommodate the largest proposed vehicle.
Label the internal protection stem length for the proposed driveway connection.
• Measured from the right-of-way line.
NCDOT | Division 3 | District 3 Project Name:_____________________________ Date:_______________
Applicant
Checklist NCDOT Checklist
Driveway Application Process and Site Plan Requirements
ALL APPLICATIONS SHALL BE ACCOMPANIED BY COMPLETE AND DETAILED SITE PLANS THAT ADHERE TO THE POLICIES LISTED IN THE POLICY ON STREET AND
DRIVEWAY ACCESS TO NORTH CAROLINA HIGHWAYS AND THIS DOCUMENT. FAILURE TO ADHERE TO THESE POLICIES WILL RESULT IN THE RETURN OF THE
APPLICATION TO THE APPLICANT FOR REVISION.
***THE NCDOT WILL NOT BEGIN THE REVIEW PROCESS ON INCOMPLETE APPLICATIONS***
Electronic Pre-Submittals
In an effort to save time and resources, we are happy to provide an initial assessment of a driveway permit submittal’s plans via email to
identify any major issues up front. This initial assessment can be followed up with a submittal of one digital copy of the plans along with all
other required documents.
All Permit applications shall be submitted through the online portal https://connect.ncdot.gov/site/Permits/Pages/default.aspx
In the notify email section of the portal application please include the District Office email (Div3Dist3@ncdot.gov). See the last pages for further instruction.
Online resources:
•NCDOT Policy on Street and Driveway Access to North Carolina Highways:
https://connect.ncdot.gov/projects/Roadway/RoadwayDesignAdministrativeDocuments/Policy%20on%20Street%20an
d%20Driveway%20Access.pdf
•NCDOT Policies and Procedures for Accommodating Utilities on Highway Rights of Way:
https://connect.ncdot.gov/municipalities/Utilities/Pages/UtilitiesManuals.aspx
•Electronic Forms Database:
https://connect.ncdot.gov/Pages/default.aspx
1)
a.Cover Letter
Include contact information for applicant and engineer, including email address, mailing address, and phone
number. Include the parcel number(s), description of all phases of the development and future land uses to be
served by the permit, and a description of the adjoining land owned or controlled by the applicant.
b.NCDOT Street and Driveway Access Permit Application (form downloadable via link below)
https://connect.ncdot.gov/resources/BusinessForms/TEB-65-04.doc
c.$50.00 Inspection Fee Per Access Point
Attach to Permit Application form (not applicable for municipalities, churches, and schools)
d.NPDES Stormwater Permit Compliance Certification (form downloadable via link below)
https://connect.ncdot.gov/municipalities/Utilities/EncroachmentForms/NPDESstatement.doc
e.Verification of Compliance with Environmental Regulations (form downloadable via link below)
https://connect.ncdot.gov/municipalities/Utilities/EncroachmentForms/VCER-1.pdf
f.Site Plans (to include the “Master Plan” of a tract even if only a small portion is being developed first) Additional
site plan requirement details can be found in section 2 of this document.
g.Design Plan Requirements for projects involving roadway improvements
If roadway improvements are required as part of the permit, then roadway plans, pavement marking plans,
signing plans, and traffic control plans will be required - See Section 6 for more information
Y N n/a
Engineering Studies
The applicant may be required by the District Engineer to submit studies based on, but not limited to, the parameters outlined
herein. If study requirements of the local government agency are more restrictive than the NCDOT requirements, then local
government requirements will govern. However, this does not imply that the NCDOT is obligated to approve entrance designs
that are too constrictive to allow smooth and safe traffic flow. All studies including, but not limited to, Traffic Impact Analyses
(TIA), traffic signal studies, and drainage studies, must be prepared under the direct charge of and sealed by a North Carolina
licensed Professional Engineer.
Section 1: Requi
red Documents
|Required documents to accompany all Initial Driveway Application Submittals
Please note that these are the minimum requirements of all driveway permit applications.
All required documentation shall be submitted through the online portal as PDF files, with the exception of the
Performance and Indemnity Bond and the $50 Inspection Fee(s), these should be mailed or delivered to 5501
Barbados Blvd, Castle Hayne, NC 28429.
If a Traffic Impact Analysis and/or roadway improvements are deemed necessary as a condition of the permit, there
may be additional submittal materials required.
State of North Carolina | Department of Transportation | Division 3 | District 3
5501 Barbados Blvd, Castle Hayne, NC 28429
Form Updated 10/15/2021 (910) 398-9100 T NCDOT Permit #___________________
Y N n/a
Section 1: Required Documents (continued)
2)Required documents to accompany all Driveway Applications PRIOR TO FINAL APPROVAL
a.Site Plans
One (1) digital copy (PDF) unless otherwise requested by the District Office. Additional site plan requirement
details can be found in section 2 of this document.
b.Performance and Indemnity Bond Information/Forms
See last page of document for bond information and forms
c.Performance and Indemnity Bond Amount
100% of the cost of the work within NCDOT Right-of-Way (R/W) based on the attached estimate determined by
the applicant's engineer and approved by the District Engineer. Bond hold letter required for for municipalities,
churches, and schools. See pages 101-105 in the Policies and Procedures for Accommodating Utilities on Highway
Rights of Way for acceptable bond types
d.Radius Encroachment Letter (if applicable)
If driveway radius encroaches on the frontage of an adjacent property, a Radius Encroachment will be required
e.Hold Harmless Letter (if applicable)
If the Permit is within the limits of an active NCDOT project, a Hold Harmless letter from the NCDOT contractor will
be required. If the project is in preconstruction, coordinate with the Department's Project Development Unit
Section 2: General Site Plan Requirements | All site plans shall include and show, at a minimum, the items listed below
Page numbers reference the NCDOT Policy on Street and Driveway Access to North Carolina Highways
1)Drawn to a scale of 20, 30, 40, or 50 feet per inch and the scale shall be shown
2)North arrow, vicinity map, date of plan, and date of most-recent revision if applicable
3)Contact information of applicant and engineer, including mailing address, phone number, and email address
4)Show R/W lines, highway control of access, and property lines
5)All existing utilities (including handholes) and easements
6)R/W width
7)Existing posted speed limit(s) and design speed limit(s)
8)Show all property lines, intersections, signals, signal loops, railroads, or crossovers within 500’ in all directions of
the property lines of the proposed development
9)Show location of sidewalks, crosswalks, greenways, multi-use paths, curb ramps, railroads, bus stops, and any
other relevant transportation facilities in the development area
10)Include a plan sheet showing full site build-out and land use
11)Buildings shown with “gross leasable area”
12)Width of property frontage
13)Distance from R/W to buildings and gasoline service islands
14)Distance from R/W to existing/proposed Edge of Pavement (EOP) (pages 32 & 34)
15)All streams, bridges, retaining walls, signs, or other fixed objects such as trees, utility poles, traffic signals, etc.
Section 3: Driveway Plan Requirements
|
All driveway plans shall include and show, at a minimum, the items listed below
1)Provide comprehensive survey within the existing R/W on both sides of the road for a distance of 500’ in all
directions from the development’s property lines. Provide additional hydraulic survey data to the nearest storm
water inlet/outlet including ditch lines and storm water pipes, if located outside of the 500' distance.
2)Lane configurations and widths of all existing and proposed driveways, roadways, and adjacent roadways
3)All driveway widths (2-way: 20’ minimum, 36’ maximum | 1-way: 12’ minimum, 24’ maximum | with island: 14'
ingress, 18' egress) (pages 50 & 77)
4)Driveway Profile - In shoulder sections, maintain minimum 2% fall from edge of travel way for required
shoulder width distance Primary: 8’ minimum | Secondary: 6’ minimum
5)All existing and/or proposed driveway radii (20’ minimum, 50’ maximum, 30’ typical) (pages 34 & 51)
In curb and gutter sections, use City of Wilmington flare (SD 3-03.3) - (see attached)
In shoulder sections, show grades at the EOP and centerline
6)No curbing is allowed within NCDOT R/W along shoulder sections except as part of a driveway island (page 31)
7)Driveway angles of approach to existing roadway (90° preferred, 75°-90° required for 2-way driveways, 45°-90°
allowed for right-in/right-out on a case-by-case basis) (page 51)
8)Driveway Profile (pages 42- 43)
Y N n/a Y N n/a
□□ □□ □ □
Y N n/a Y N n/a
Y N n/a Y N n/a
Section 3: Driveway Plan Requirements (continued)
9)Driveway Pavement Cross Section (to be in place from EOP to edge of R/W)
Asphalt: 8” ABC stone and 1.5” S9.5B
Concrete: 6” of concrete
10)Driveway Offset (driveway EOP to property line; page 75): Minimum: 20’
11)Corner Clearance (radius point to radius point; page 52)Minimum: 50’ Desirable: 100’ or Municipal std.
12)Minimum 10’x70’ sight triangles at driveways (measured from and along the R/W line) (page 31)
13)Sight Distance (length of sight-distance in both directions shown for each driveway; pages 27-29)
14)Driveways should be aligned with existing opposing driveways or correct offset should be provided (pages 40-41)
15)Distance between driveways being requested (if applicable; page 51)
16)Minimum internal storage areas with specified queues (pages 31-33)
17)Minimum protected driveway stem(s) provided and indicated (pages 33-34)
18)Indicate any gated entrances (100’ minimum setback from R/W required) - traffic queuing study may be required
|
Section 6: Roadway
Plan Requirements
If off-site improvements are required, roadway plans shall show, at a minimum, the items below
1)Full width typical sections must be shown (paved shoulders to match the typical section of the adjacent roadway)
2)Minimum Asphalt Typical Section (for turn lanes and/or paved shoulders)
Adjacent recently-completed or upcoming TIP projects w/ different typical sections may supersede those below
•Primary Routes (US & NC) and Secondary Routes with Annual Average Daily Traffic (AADT) ≥10,000
5.5” B25.0C, 3” I19.0C, 1.5” S9.5C; any overlay of existing pavement is to be a minimum of 1.5” S9.5C
•Secondary Routes with AADT<10,000
5.5” B25.0C, 1.5” S9.5B; any overlay of existing pavement is to be a minimum of 1.5” S9.5B
3)Pavement overlay is required if modification of existing pavement markings and/or lanes is necessary
The grinding of pavement markings will not be allowed
4)Shoulder Widths (Paved + Unpaved) Primary: 8’ minimum | Secondary: 6’ minimum
5)Ditch Slopes - front and back slopes - minimum 3:1 or flatter
6)Indicate existing roadway grade
7)All taper lengths and deceleration lengths should be appropriately designed for the given design speed (page 78)
8)All turn lanes should be designed according to the Driveway Manual and Roadway Standard Drawings (page 79)
See 1205.04 Sheets 1 & 2 and 1205.05 Sheet 1 of the Roadway Standard Drawings for details
9)Pavement marking and signing plans are required - plans must be approved by Division Traffic Services
10)Traffic control plans are required - Detailed phasing plans may be required based on project type and location
11)New and/or revised signal plans must be included for new installations and if signal modifications are required
All signal plans must be reviewed and approved by Division Traffic Services and the Signal Design Unit. A Traffic
Agreement must be completed to facilitate the review. Contact Division Traffic Services at (910) 341-2200.
|
Section 4: Drainag e Requirements
All drainage features on NCDOT Right-of-Way shall adhere to, at a minimum, the items listed below
Section 5: Internal Circ ulation Requirements
|All internal circulation details shall adhere to, at a minimum, the items listed below
1)Interior driveway channelization stems
Minimum 100’ from the ROW or at the discretion of the District Engineer
2)Traffic flow pattern
3)Traffic control devices
4)Pavement Markings
Y N n/a Y N n /a
Y N n/a Y N n/a
Y N n/a Y N n/a
Y N n/a Y N n/a
1)Pipe Cover Minimums (measured from top of pipe to subgrade)
High Density Polyethylene (HDPE): 24” | Corrugated Aluminum (CAP): 12” | Reinforced Concrete (RCP): 12”
2)Pipe End Treatment (see Roadway Design Manual 5-20, B-2)
Pipes ≤24" on multilane highways posted above 45mph require Parallel Pipe End Sections See 310.02 and
310.04 of the Roadway Standard Drawings for details
Pipes >30" on multilane highways posted above 45mph require guardrail
Pipes ≥36" require an endwall on the inlet end
3)All proposed Drainage is to be provided inside existing R/W. Otherwise, additional R/W or a permanently
dedicated drainage easement will be required to accommodate the proposed project drainage
4)All sizes, types, and invert elevations of existing/proposed pipes and drainage structures must be shown
(see Sec.3 #1 for survey requirements)
5)Provide spot elevations along frontage of driveway (at EOP and centerline)
6)Provide grades and spot elevations for existing and proposed ditches
7)Show how drainage will be accommodated along property frontage(District Engineer may require applicant to provide drainage calculations when warranted)
C/L
EOTEOP
P/L
R/WR/W
R/W
EOP
EOP
EOP
EOP
NTS
R/W
P/L
DRAINAGE FLOW
DRAINAGE FLOW
DRAINAGE FLOW
SHOULDER WIDTH
SHOULDER WIDTH
SHOULDER WIDTH
SHOULDER WIDTH
S IGH T T R IAN G LE
10 ' B Y 70 'S I GH T T R I AN G L E10' B Y 70'
DRIVEWAY
RR MIN. 30'MIN. 30'
NO ROADWAY IMPROVEMENT
COMMERCIAL DRIVEWAY WITH
NORMAL CROWN ROADWAY
6" LOWER THAN THE EDGE OF PAVEMENT
MIN 2% FALL AWAY or
20' AWAY FROM THE PROPERTY LINE
DRIVEWAY SHALL BE LOCATED AT LEAST
PIPE/TYPE/SIZE
WIDTH
CON
CR
ET
E
/ASP
HA
LT
LOCAL NAME ROAD POSTED SPEED ( ) MPH WIDTH WIDTHSR NUMBER
SITE ADDRESS:TAX PARCEL #
20191115
PARALLEL END S.D. 310.02
INVERT ELEVATION
PARALLEL END S.D. 310.02
INVERT ELEVATION
20' AWAY FROM THE PROPERTY LINE
DRIVEWAY SHALL BE LOCATED AT LEAST
OR 500' OF XYZ SURVEY DATA PAST THE PROPERT LINE
NEAREST OUTFALL ELEVATION
OR 500' OF XYZ SURVEY DATA PAST THE PROPERT LINE
NEAREST OUTFALL ELEVATION
MEMORANDUM
To: New Hanover County Technical Review Committee
Date: June 5, 2025
Subject: Legacy Landing Phase 2 – 1728 Rockhill Road (SUBPP-25-0025)
NCDOT Projects:
N/A
WMPO 2045 MTP Projects:
N/A
New Hanover County Projects:
N/A
TIA: Based on the 11th edition ITE Trip Generation Manual, a TIA is not required.
Land Use (ITE Code) Intensity Unit 24 Hour
Volumes
AM Peak
Hour Trips
PM Peak
Hour Trips
Single Family Attached
Housing (215) 14 DU 56 2 4