Northside Baptist Church Office Building – 2510 N College Rd – TRC Review
Page | 1
To: Clyde Holley, Northside Baptist Church
From: Zach Dickerson, Senior Planner
Date: September 17, 2025 Technical Review Committee (TRC)
PID#: R03400-001-013-005
Egov# SITECN-25-000096
Subject: 2510 N College Rd – Northside Baptist Church Office Building - TRC Review
Technical Review Committee (TRC) General Information
The TRC is a staff-level group of local government officials that reviews projects for compliance with
the local regulations administered by each respective review agency. Voluntarily participating state
agencies may also provide comments. And general information and non-binding recommendations
about the site may also be provided by government agencies.
The TRC meetings are considered staff meetings and are not public hearings. The TRC meeting is an
opportunity for applicants to speak with county staff and any voluntarily participating state or federal
agencies about the review comments they have been provided.
No voting is involved in the TRC process, and no final approvals or denials are made at the TRC
meetings. Following the TRC meeting, applicants are responsible for updating their plans to address
review comments. Those revised plans need to be resubmitted to the assigned case planner. The case
planner will facilitate additional reviews until all comments have been addressed, and the necessary
departments have stated the plans comply with the applicable minimum requirements for
development.
Following any future TRC approval, the project is required to obtain additional permits to include a
zoning compliance permit for the site. Applicants are also responsible for coordinating with state and
federal agencies for compliance with any additional requirements. Any activity on the property that is
not approved as part of the TRC review and zoning compliance permit will be considered a violation
of the UDO and subject to enforcement action under Article 12 Violations and Enforcement.
The following comments have been received for the September 17, 2025, TRC meeting. Additional
comments may be made upon further review of subsequent revisions.
Northside Baptist Church Office Building – 2510 N College Rd – TRC Review
Page | 2
Planning, Zach Dickerson 910-798-7450
Compliance with local zoning requirements
1. General Comments
a. Zoning district is PD (Planned Development), tied to rezoning case Z22-13.
b. As stated in the application the intended use is Offices for Private Business and
Professional Activities & Religious Assembly. The Unified Development Ordinance
(UDO) defines the use as
i. Offices for Private Business and Professional Activities: Establishments
primarily engaged in the day-to-day administrative or clerical services for
businesses or other organizations that provide professional or other services
to the general public on a walk-in or appointment basis in an office setting.
*Note, these offices are tied to the regular use of Northside Baptist Church.
ii. Religious Assembly: A facility or area for people to gather together for public
worship, religious training, or other religious activities including a church,
temple, mosque, synagogue, convent, monastery, or other structure, together
with its accessory structure(s), including a parsonage or a rectory. This use
does not include home meetings or other religious activities conducted in and
ancillary to a privately occupied residence. Accessory uses may include
meeting rooms and childcare provided for persons while they are attending
assembly functions. Schools and other childcare services are not accessory
uses and shall require approval as separate principal uses.
iii. Note about the above, rezoning Z22-13 permits the use of school on this
property. This TRC review is for a church office building and some youth space.
c. The Planning and Land Use Department’s review of the site is for compliance with the
UDO and use specific requirements of the specified land use. Any other activity that
might occur on the property beyond the definition above should be noted on the
application and site plan for additional review and comment.
d. Conditions approved as part of the Z22-13 rezoning:
i. Prior to the approval of any future phase of this project or expansion of school
beyond 400 students, required NCDOT road improvements, as included in the
TIA, must be completed.
ii. The Terms & Conditions document shall be revised to clarify the process for
approval of future development. Section 1A shall be revised as follows: “Phase
1 on the Master Plan to be completed upon approval of rezoning to Planned
Northside Baptist Church Office Building – 2510 N College Rd – TRC Review
Page | 3
Development. Phases 2 thru 4 are listed as future development and cannot be
started without an approved modification to the Planned Development
District.”
e. The Office building was approved as part of Phase 1, so this building is okay under the
rezoning conditions.
f. This building is allowed under the minor deviation determination from New Hanover
County Planning & Land Use Staff, attached to these comments.
2. UDO Section 5.1, Parking and Loading
a. Offices for Private Business and Professional Activities require 2.5 spaces per 1,000 ft
of use. For the purposes of this TRC review, the parking calculations will be run for the
office use of the 5,800 sq ft building: 15 parking spaces required.
b. Because this is part of the Northside Baptist Church campus, it will share parking with
the other church uses.
c. Do you know how many parking spaces there are total on the campus? If we have
those calculations, we can run numbers of what’s there vs. the current uses and make
sure there are enough for this use.
3. UDO Section 5.2, Traffic, Access and Connectivity
a. Please note that no building permit for any structure shall be issued which requires
NCDOT approval for a Driveway Permit until NCDOT has issued the permit approval.
Evidence of approval shall accompany the application for building permit.
4. UDO Section 5.3, Tree Retention
a. Note: Land disturbance permits can be issued by county Engineering before a Tree
Removal Permit is approved by Planning. However, any trees removed before the Tree
Removal Permit is issued may result in enforcement action under Section 5.3.2 of the
Unified Development Ordinance to include prohibiting any development of the site for
3 to 5 years.
b. It does not appear that any trees are being removed for this project. Please confirm.
5. UDO Section 5.4, Landscaping and Buffering
a. This new building will require foundation plantings for the southern-facing portion of
the building, adjacent to the parking lot.
b. The sq footage of foundation plantings is calculated at 12% of the area of the first floor
building face.
Northside Baptist Church Office Building – 2510 N College Rd – TRC Review
Page | 4
i. How tall is the building? We can run this calculation.
6. UDO Section 5.5, Lighting
a. Please note that a lighting plan is not required for TRC approval but will be required
prior to issuance of construction plan approvals.
b. Is any new lighting proposed for the site?
7. UDO Section 5.6, Signs
a. Are any new signs proposed for this building?
b. For any signs on the site, a separate sign permit must be submitted and reviewed by
the county for compliance with Section 5.6 of the UDO for standards at or after the
submittal of the separate zoning compliance and construction permits for the primary
building or use.
8. UDO Section 5.7, Conservation Resources
a. Per the New Hanover County Conservation Resource Map, there are no conservation
resources on this property.
9. UDO Article 9, Flood Damage Prevention
a. None of the buildings on this campus or in the proposed new building area are in the
floodplain.
NHC Fire Services, David Stone 910-798-7458
Compliance with NC Fire Code
1. No comments
Northside Baptist Church Office Building – 2510 N College Rd – TRC Review
Page | 5
NHC Engineering, Galen Jamison 910-798-7072
Stormwater management and land disturbance
1. Please submit for a permit revisions to County stormwater permit ATC# 250-09/12/07.
Please digitally submit the permit applications documentation with requisite review fees to
the COAST online permit portal (https://newhanovercountync-
energovpub.tylerhost.net/apps/selfservice#/home.
2. A County land disturbing permit is required for this project. Please digitally submit the
permit applications documentation with requisite review fees to the COAST online permit
portal (https://newhanovercountync-energovpub.tylerhost.net/apps/selfservice#/home).
Applicable forms can be found at https://www.nhcgov.com/249/Sediment-Erosion-
Controlhowever.
3. Please contact the State for their stormwater permit requirements. It is anticipated a
modification to permit SW88001241 will be required.
NHC Environmental Health, Dustin Fenske 910-798-6732
Septic tanks and wells
1. Site plan reflects access to public water and sewer. Proposed buildings and added
infrastructure do not violate setbacks to any surrounding well or septic systems.
NHC Addressing, McCabe Watson 910-798-7068
Street naming and property address
1. The proposed building will need its own individual address.
2. Please contact me for address assignment following TRC approval.
Cape Fear Public Utility Authority, Bernice Johnson 910-332-6620
Public water and sewer
1. CFPUA TRC Comments provided are preliminary comments only.
2. CFPUA is moving toward becoming paperless. When ready to submit plan review package,
upload all documents to https://www.cfpua.org/FormCenter/Engineering-3/Engineering-Plan-
Review-103.
3. CFPUA water and sewer are available.
Northside Baptist Church Office Building – 2510 N College Rd – TRC Review
Page | 6
4. Project is currently in CFPUA Plan Review.
NCDOT, Nick Drees 910-398-9100
Driveway access and state road improvements
1. No comments.
WMPO, Luke Hutson 910-343-3915
New Hanover County contracted traffic engineering services comments:
1. Please see attached comments.
Army Corps of Engineers, Brad Shaver 910-251-4611
Requirements if wetlands are impacted
1. No comments
Project information also provided to the following state agencies and non-regulatory local
agencies for their awareness:
New Hanover County Emergency Management
New Hanover County Schools
NC Department of Environmental Quality (DEQ)
NC DEQ Division of Coastal Management
NC DEQ Division of Energy, Mineral, and Land Resources
New Hanover County Sustainability Manager
NHC Soil & Water Conservation
MEMORANDUM
To: New Hanover County Technical Review Committee
Date: September 3, 2025
Subject: Northside Baptist Church
Comments:
• Please confirm that the proposed building will not exceed the daily trips as generated
below.
NCDOT Projects:
• HS-2003AI – US 117/NC 132 (College Road) – SR 2160 (Long Ridge Road) intersection.
Install traffic signal with pedestrian accommodation.
WMPO 2045 MTP Projects:
• HS-2003AI – US 117/NC 132 (College Road) – SR 2160 (Long Ridge Road) intersection.
Install traffic signal with pedestrian accommodation.
New Hanover County Projects:
• N/A
TIA: Based on the 11th edition ITE Trip Generation Manual, a TIA is not required.
Land Use (ITE Code) Intensity Unit 24 Hour
Volumes
AM Peak
Hour Trips
PM Peak
Hour Trips
General Office (710) 5,880 Square
Feet 64 9 8