HomeMy WebLinkAboutTarin Woods II Phase 5 TRC Compiled Comments Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 1 To: James Yopp, Hoosier Daddy LLC, james@rockfordpartners.net From: Zach Dickerson, Senior Planner Date: November 19, 2025 TRC PID#: Several- See Application for list Egov# SUBPP-25-0032 Subject: Tarin Woods II- Preliminary Plan TRC Review Technical Review Committee (TRC) General Information The TRC is a staff-level group of local government officials that reviews projects for compliance with the local regulations administered by each respective review agency. Voluntarily participating state agencies may also provide comments. And general information and non-binding recommendations about the site may also be provided by government agencies. The TRC meetings are considered staff meetings and are not public hearings. The TRC meeting is an opportunity for applicants to speak with county staff and any voluntarily participating state or federal agencies about the review comments they have been provided. No voting is involved in the TRC process, and no final approvals or denials are made at the TRC meetings. Following the TRC meeting, applicants are responsible for updating their plans to address review comments. Those revised plans need to be resubmitted to the assigned case planner. The case planner will facilitate additional reviews until all comments have been addressed, and the necessary departments have stated the plans comply with the applicable minimum requirements for development. Following any future TRC approval, the project is required to obtain additional permits to include a zoning compliance permit for the site. Applicants are also responsible for coordinating with state and federal agencies for compliance with any additional requirements. Any activity on the property that is not approved as part of the TRC review and zoning compliance permit will be considered a violation of the UDO and subject to enforcement action under Article 12 Violations and Enforcement. Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 2 The following comments have been received for the November 19, 2025, TRC meeting. Additional comments may be made upon further review of subsequent revisions. Planning, Zach Dickerson 910-798-7450 Compliance with local zoning requirements 1. General Comments a. The zoning is R-15, with single-family housing proposed. b. This is a performance residential subdivision. i. R-15 allows a maximum 2.5 dwelling units per acre in a performance residential subdivision. ii. It does appear that there are some Class IV soils on this site. Staff understands there may be some documentation provided in the past that there are no longer Class IV soils on this site- this will get expanded upon more in the Conservation Resources section. iii. Density Calculations 1. Total site acreage = 16.3 acres 2. See above note about Class IV soils and below about Conservation Resources. None are noted as being conserved on this site per the application. 3. Zoning District allows maximum 2.5 dwelling units per acre under performance residential subdivision. 4. Developable site acreage * zoning density = 41 maximum dwelling unit count. This is reflected in the application. c. Staff recommend including the location of traffic calming devices on the preliminary plans. Installation of traffic calming devices are not required, but including potential locations on the plan ensures the future HOA / owners will have the opportunity to install them without conducting a traffic study. d. Some of the lots shown in this preliminary plan already exist: i. Section C: 9 Lots ii. Section D: 6 Lots Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 3 2. UDO Section 5.1, Parking and Loading a. Detached single-family homes require a minimum of two parking spaces per unit. If ultimately constructed, the parking for each lot will be verified during zoning compliance and building permit review as homes are constructed. 3. UDO Section 5.2, Traffic, Access and Connectivity a. Please note that no building permit for any structure shall be issued which requires NCDOT approval for a Driveway Permit until NCDOT has issued the permit approval. Evidence of approval shall accompany the application for building permit. b. Per the application, these new lots are covered under the existing Tarin Woods II TIA. 4. UDO Section 5.3, Tree Retention a. Note: Land disturbance permits can be issued by county Engineering before a Tree Removal Permit is approved by Planning. However, any trees removed before the Tree Removal Permit is issued may result in enforcement action under Section 5.3.2 of the Unified Development Ordinance to include prohibiting any development of the site for 3 to 5 years. b. Tree Removal Permit application received, but the total amount of inches being removed in the application states “n/a.” Are there are any trees being removed for these new lots and the requisite infrastructure? If not, a new tree removal permit is not needed. 5. UDO Section 5.4, Landscaping and Buffering a. Landscaping and buffering are only required for the amenity areas, which are not part of this application and would be reviewed as a separate TRC item. 6. UDO Section 5.5, Lighting a. Please note under 5.5.2.A that a lighting plan is not required for single-family residential projects and the county does not require streetlights, however a lighting plan is required for any amenity area. 7. UDO Section 5.6, Signs a. For any signs on the site, a separate sign permit must be submitted and reviewed by the county for compliance with Section 5.6 of the UDO for standards at or after the submittal of the separate zoning compliance and construction permits for the primary building or use. Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 4 8. UDO Section 5.7, Conservation Resources a. Per the New Hanover County Conservation Resources Map, there are some areas of Pocosin Conservation Resource on this property. b. The Conservation Resource Standards for Pocosin do not apply unless that Pocosin is underlaid with Class IV soils. c. As noted above, it does appear that there is some Pocosin Conservation Resource which is underlaid by Class IV soils. Please see clips below. Conservation Resources Soils Pocosin Conservation Resource d. As also noted above, there may have been documentation provided to staff in the past that indicated that Class IV soils are no longer present on this site. Please confirm if this is the case. Pamlico Muck Soil (Class IV) Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 5 9. UDO Section 5.8, Open Space Requirements a. Open space requirements for performance residential developments is 20% of the total site acreage. b. 16.3 acres * 20% = 3.26 acres of open space. c. Site plan notes 3.26 acres of open space provided, but it’s a little unclear where this is on the site- can you please clarify where the open space is located? 10. UDO Article 6, Subdivision Design and Improvements. a. R-15 zoning requires sidewalks on one side of the street. Please indicate where the sidewalks will go on this site plan. b. The block going through areas C & D (Shiloh Drive) appears to be approximately 1,300 ft long, which is too long. UDO Section 6.2.2.A.2.b states that blocks shall not exceed 1,000 feet in length. This can be broken up with open space. c. This phase of the development will connect in with the existing Tarin Woods neighborhood. Links and nodes appear sufficient. d. New Hanover County Private Roadway Design standards require a minimum 24’ width travelway in new roads. It appears roads C & D meet this standard, whereas A & B do not. 11. UDO Article 9, Flood Damage Prevention a. None of this phase of Tarin Woods is in a Flood Hazard area. NHC Fire Services, David Stone 910-798-7458 Compliance with the NC Fire Code 1. No comments. Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 6 NHC Engineering, Galen Jamison 910-798-7072 Stormwater management and land disturbance 1. Please submit for permit revisions to all existing applicable County stormwater permit for the Tarin Woods development. Please digitally submit the permit applications documentation with requisite review fees to the COAST online permit portal (https://newhanovercountync- energovpub.tylerhost.net/apps/selfservice#/home) using the referenced permit numbers. 2. All conveyance calculations will need to be updated per the latest NHC stormwater design manual. 3. A land disturbing permit issued by the County is required for this project. Please digitally submit the permit application documentation with requisite review fees to the COAST online permit portal (https://newhanovercountync-energovpub.tylerhost.net/apps/selfservice#/home). Applicable forms can be found at https://www.nhcgov.com/249/Sediment-Erosion- Controlhowever. 4. Please contact the State for their stormwater permit requirements. NHC Environmental Health, Dustin Fenske 910-798-6732 Septic tanks and wells 1. Site plan reflects connection to public water and sewer. Proposed infrastructure does not appear to violate any septic system or well setbacks to surrounding properties. NHC Addressing, McCabe Watson 910-798-7068 Street naming and property address 1. Please contact me for address assignments following TRC approval. Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 7 Cape Fear Public Utility Authority, Bernice Johnson 910-332-6620 Public water and sewer 1. CFPUA TRC Comments provided are preliminary comments only. 2. CFPUA is moving toward becoming paperless. When ready to submit plan review package, upload all documents to https://www.cfpua.org/FormCenter/Engineering-3/Engineering- Plan-Review-103. 3. CFPUA water and sewer available via mainline extensions. 4. Capacity is dependent on the analysis of the pipe collection system (gravity and force mains). 5. A capacity determination can be provided upon submittal of the NC DWQ FTA/FTSE Application Form and a Preliminary Plan, this determination does not guarantee capacity. 6. Capacity is issued to projects on a first come, first serve basis, when capacity is available, the plans meet Authority requirements, and the NC DWQ FTA/FTSE forms are signed by the Authority. NCDOT, Nick Drees 910-343-3915 Driveway access and state road improvements 1. If the development does fall in line with the approved TIA, they will just need to meet those requirements. 2. If a driveway connection is needed or utilities are being installed in the right of way they will need to obtain permits. WMPO, Luke Hutson 910-473-5130 New Hanover County contracted traffic engineering services comments: 1. See attached. Tarin Woods II Phase 5– Major Subdivision – TRC Review Page | 8 Project information also provided to the following state agencies and non-regulatory local agencies for their awareness: New Hanover County Emergency Management New Hanover County Schools NC Department of Environmental Quality (DEQ) NC DEQ Division of Coastal Management NC DEQ Division of Energy, Mineral, and Land Resources New Hanover County Sustainability Manager New Hanover County Soil & Water Conservation Army Corps of Engineers MEMORANDUM To: New Hanover County Technical Review Committee Date: November 12, 2025 Subject: Tarin Woods II Phase 5 NCDOT Projects: • N/A WMPO 2045 MTP Projects: • N/A New Hanover County Projects: • N/A TIA: A TIA for the proposed Tarin Woods II Development was approved with conditions by the WMPO on August 27, 2025. All improvements outlined in the approved TIA are required. Please reach out to Caitlin Cerza (Caitlin.Cerza@wilmingtonnc.gov) if any questions arise related to the TIA. Trip generations based on the 11th edition ITE Trip Generation Manual are shown below for the proposed development. Land Use (ITE Code) Intensity Unit 24 Hour Volumes AM Peak Hour Trips PM Peak Hour Trips Single Family Detached (210) 41 Dwelling Units 444 33 43