HomeMy WebLinkAbout2026-01-14 USACE CSRM Update PresentationSAW Project Status Updates
14 January 2026
Wilmington District
WILMINGTON / NEW HANOVER COUNTY
PORT, WATERWAY, & BEACH COMMISSION
2
North Carolina
Virginia
South Carolina
CHARLESTONDISTRICT(SAC)
WILMINGTONDISTRICT(SAW)
Wilmington Harbor
(7.1M/$13.8B)
NOT TO SCALE
Atlantic Ocean
COASTAL PORTFOLIOWILMINGTON DISTRICT
SOUTH ATLANTIC DIVISION (SAD) U.S. ARMY CORPS OF ENGINEERS
LEGEND
4 Constructed Beach Segments
Flood Risk Management
2 Deep Draft Harbors
Navigation
1 Top 10 SAD Harbor (Tonnage/Cargo Value)
Shallow Draft Projects Not Illustrated
West Virginia
Carolina Beach & Vicinity (Carolina Beach)
Wrightsville Beach
Ocean Isle Beach
Carolina Beach & Vicinity (Area South)
Morehead City Harbor
Atlantic Intracoastal Waterway
Over 1500 Miles of Navigable Channels
300 miles of Atlantic Intracoastal Waterway
7 Shallow Draft Inlets
2nd Largest Ferry System in the Nation
3WILMINGTON DISTRICT (SAW) PROJECT UPDATES
Kure Beach Carolina Beach
•Wilmington Harbor – Maintenance Dredging Contracts
•AIWW – Snow’s Cut Shoreline Erosion Protection Project
•AIWW Inlet Crossing Maintenance Dredging Contract
•Carolina Beach Inlet Maintenance Dredging (Government Plant)
•Carolina Beach & Vicinity, NC CSRM Project
4WILMINGTON HARBOR (O&M), NC
MAINTENANCE DREDGING CONTRACTS
5
Wilmington Harbor Project
Authorized Depth(s):
•The channel is 44 feet deep through the ocean bar and the
entrance channel, changing to 42 feet deep extending to just
downstream of the Cape Fear Memorial Bridge at Wilmington, NC;
•Upstream of this point, the channel is 32 feet deep to the Hilton
Bridge over the Northeast Cape Fear;
•And 25 feet deep from the Hilton River Bridge to a point
approximately 2 miles above.
Typical O&M Maintenance Dredging Contracts:
•Anchorage Basin Contract: Dredged annually with the non-
beach compatible material placed in an upland disposal facility.
•Mid-River Contract: Normally dredged every two years,
opposite the Inner Ocean Bar contract. Non-beach compatible
material is placed in the ODMDS, with any beach compatible
material placed in upland disposal facilities for future use.
•Inner Ocean Bar Contract: Normally dredged every two years,
opposite the Mid-River Contract. This beach compatible material
is placed on adjacent beaches.
•Outer Ocean Bar Contract: Dredged annually with the non-
beach compatible material placed in the ODMDS
6FY26 WILMINGTON HARBOR
INNER OCEAN BAR
LOCATION:
Brunswick County, North Carolina
DREDGE TYPE: Pipeline
PLACEMENT: Beach
EST. DREDGE QUANTITY: 1,300,000 CY
Base: 700,000 CY
Option: 600,000 CY
DEPTH: 44 feet
AWARD: May 15, 2025 (Norfolk Dredging Co.)
Total Contract Cost: $25,188,315
Base (Fed Funding): $18,645,765
Options (Oak Island): $ 6,542,550
START DREDGING: November 2025
DREDGE COMPLETE: January 31, 2026
WORK RESTRICTIONS/WINDOW:
November 16 – April 30 (Beach Placement)
BALD HEAD
ISLAND
OAK ISLAND
ATLANTIC
OCEAN
Dredge Areas
Awarded
7SNOW’S CUT SHORELINE EROSION
PROTECTION PROJECT
8HISTORIC SHORELINE
9PROPOSED PROJECT
10AIWW INLET CROSSING MAINTENANCE
DREDGING CONTRACT
11FY25/26 ATLANTIC INTRACOASTAL WATERWAY
LOCATION:
Carteret, Onslow, New Hanover,
and Brunswick Counties, North Carolina
DREDGE TYPE: Pipeline
PLACEMENT: Beach
EST. QUANTITY: 685,000 CY (Total Contract)
75,000 CY (Figure Eight Island)
275,000 CY (CB (Freeman Park))
DEPTH: 12 feet
AWARD: September 19. 2025
(Southwind Construction Corp)
START DREDGING: November 16, 2025
DREDGE COMPLETE: April 30, 2026
WORK RESTRICTIONS/WINDOW:
November 16 – April 30 (Beach)
ATLANTIC
OCEAN
MOREHEAD
CITY
WILMINGTON
JACKSONVILLE
Note: AIWW locations included in this solicitation are as follows:
Browns Inlet Crossing, Mason’s Inlet Crossing, Carolina Beach Inlet Crossing,
Snow’s Cut, Lockwoods Folly Inlet Crossing, and Shallotte Inlet Crossing.
Dredge Sites
Awarded
12FY-26 AIWW INLET CROSSING CONTRACT (MASON INLET)
13FY-26 AIWW INLET CROSSING CONTRACT (CB INLET)
14CAROLINA BEACH INLET, NC
(GOVERNMENT PLANT)
15CAROLINA BEACH INLET SURVEY (OCTOBER 2025)
16CAROLINA BEACH & VICINITY, NC
COASTAL STORM RISK MANAGEMENT (CSRM)
17
FY25/26 CAROLINA BEACH / KURE BEACH, NC
COASTAL STORM RISK MANAGEMENT (CSRM)
LOCATION: New Hanover County, NC
DREDGE TYPE: Pipeline
BEACH FILL QUANTITY: 1,557,000 CY
Carolina Beach: 800,000 CY
Kure Beach: 757,000 CY
AWARD: May 8, 2025 (Norfolk Dredging Co.)
Total Contract Cost: $23,480,000
Carolina Beach: $9,758,250
Kure Beach: $13,721,750
START DREDGING: November 16, 2025
DREDGE COMPLETE: April 30, 2026
ENVIRONMENTAL WINDOW:
November 16 – April 30 (Beach Placement)
Awarded
LOCATION: New Hanover County, NC
DREDGE TYPE: Pipeline
BEACH FILL QUANTITY: 1,790,000 CY
Carolina Beach: 920,000 CY
Kure Beach: 870,000 CY
AWARD: May 8, 2025 (Norfolk Dredging Co.)
Total Contract Cost: $26,239,000
Carolina Beach: $10,748,250
Kure Beach: $15,490,750
START DREDGING: November 16, 2025
DREDGE COMPLETE: April 30, 2026
ENVIRONMENTAL WINDOW:
November 16 – April 30 (Beach Placement)
18
19CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
20CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
21CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
22CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
AREA B
Atlantic Ocean
CAROLINA BEACH PORTION (14,000 FEET)
Salt Marsh Lane
N.Carolina Avenue
CAROLINABEACHINLETAND BORROW AREA
NOT TO SCALE
LOCATION
Borrow Sources
CBRA Zones
STA.0+00
STA.0+180 Surfrider Circle
ESTIMATED NOURISHMENT VOLUMES/FREQUENCY:~757,000 cubic yards with
a 3-year periodic nourishment schedule over a total length of 18,000 feet.
DUNE WIDTH:
►25-foot berm at 12.5 Feet NAVD88;dune extends approximately 18,000 feet
from Stations 0+00 to 180+00.
STORM BERM WIDTH:
►50-foot berm at 8.0 Feet NAVD88;berm extends approximately 18,000 feet
from Stations 0+00 to 180+00
CONSTRUCTION BERM WIDTH:
►105-foot berm at 5.5 Feet NAVD88; berm extends approximately18,000 feet
from Stations 0+00 to 180+00.
BORROW SOURCES:Borrow Area B.
SPECIAL CONSIDERATIONS:The project has a 1,500-foot transition between Stations 165+00 and 180+00.
*SLA:Submerged Lands Act Boundary Line (delineates state and federal waters)
U.S.ARMY CORPS OF ENGINEERS |WILMINGTON DISTRICTCAROLINABEACHANDVICINITY(AREA SOUTH PORTION)COASTAL STORM RISK MANAGEMENT PROJECT
Local Sponsor: Town of Kure Beach |End of Federal Participation:2047
AREA A
AREA SOUTH PORTION (18,000 FEET)
STA.0+165
TYPICAL CROSS SECTION (NAVD88)CONSTRUCTION
BASELINE 220’
5H:1V20
-20
10
0
-10
0 300
CONSTRUCTION BERM
STORM BERM
MHW (+1.4’NAVD88)
EXISTING GROUND
EL+5.5’DUNE
25’45’25’
EL+12.5’
EL+8.0’
EL
E
V
A
T
I
O
N
I
N
FE
E
T
100 200
DISTANCE IN FEET FROM BASELINE
RT
.
ED
G
E
CO
N
S
T
.
BE
R
M
105’
Refer to Text for Station References
24CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
25CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
26CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
27CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
28CAROLINA BEACH & VICINITY, NC CSRM PROJECT
Kure Beach Carolina Beach
29
Link: Carolina / Kure Beach Sand Placement Tracker
WILMINGTON DISTRICT POINT OF CONTACT
Project Point of Contact E-Mail
Carolina Beach & Vicinity, NC CSRM Project Kent Tranter Kent.Tranter@usace.army.mil
SAW Shallow-Draft Program Adam Faircloth adam.g.faircloth@usace.army.mil
AIWW - Snow's Cut Shoreline Protection Project Ronnie Smith ronnie.d.smith@usace.army.mil
Civil Works PM Branch Bob Keistler robert.w.keistler@usace.army.mil