HomeMy WebLinkAbout2026-02-11 USACE WH 403 PresentationLETTER REPORT & ENVIRONMENTAL IMPACT STATEMENT
Presented by: SAW Team
U.S. Army Corps of Engineers
Wilmington District
February 11th, 2026
NEW HANOVER PORT, WATERWAY
& BEACH COMMISSION
WATER RESOURCES DEVELOPMENT ACT OF 2020 (WRDA) SECTION 403
INTRODUCTION
FEB 2020 - North Carolina State Ports Authority (NCSPA) Section 203 Feasibility Study
✓Tentatively Selected Plan recommended deepening to 47 feet
✓Submitted to the ASA(CW) in February 2020 for Review
DEC 2020 – Water Resources Development Act (WRDA 2020)
✓Congress authorized the navigation project, at a total cost of $834,093,000 through Section 403 of Water Resources Development Act (WRDA)
2020. WRDA 2020 included a requirement that a final assessment address the concerns, recommendations, and conditions identified by the
ASA (CW).
MAY 2020 – Assistant Secretary of the Army (Civil Works) ASA (CW) Review Assessment
✓Transmitted to Congress with unresolved comments including:
- Reframe assumptions and screening of alternatives
- Perform economic analysis using USACE methodology at multiple depths
- Conduct National Environmental Policy Act (NEPA) analysis including supporting engineering modeling and appropriate sea level rise
- Finalize a mitigation plan and a real estate plan
- Conduct Independent External Peer Review (IEPR)
OCT 2023 – Section 403 Letter Report and Environmental Impact Statement
❑The Wilmington District was tasked with producing a Letter Report and Environmental Impact Statement to address issues from the Review
Assessment through a cost-share agreement with the NCSPAN
PURPOSE AND NEED:
•Describes the what and why for the proposed action
•Informs the development of alternatives
WILMINGTON HARBOR 403 PURPOSE AND NEED
•PURPOSE. Contribute to national economic development (NED)
by addressing transportation inefficiencies for the forecasted
vessel fleet, consistent with protecting the Nation’s
environment.
•NEED. A ddress the constraints that contribute to inefficiencies
in the existing navigation system’s ability to safely serve
forecasted vessel fleet and cargo types and volumes.
NEPA PROCESS
June 7-July 22, 2024Notice of Intent
(Summer 2024)
Public Review and Comment Period
(Fall 2025)
Issue Final EIS
(Summer 2026)
DESCRIPTION OF ALTERNATIVES
•Depth increased from -42’ to -47’ MLLW with 2’
stepdown at Battery Island
•Side Slopes.
•3:1 (horizontal to vertical) from
Anchorage Basin to Lower Swash
•5:1 from Battery Island to Baldhead
Reach 4
•2’ allowable overdepth authorized
•Where hard-rock present, 1’ additional over-
depth
•9.1 mi channel extension from BH Reach 3
•Widen areas identified in the 203 Report (Table
1)
•Depth -42’ MLLW
•Side Slopes: 3:1 (horizontal to vertical)
•Depth increased from -42’ to -46’ MLLW with 2’
stepdown at Battery Island
•Side Slopes.
•3:1 (horizontal to vertical) from
Anchorage Basin to Lower Swash
•5:1 from Battery Island to Baldhead
Reach 4
•2’ allowable overdepth authorized
•Where hard-rock present, 1’ additional over-
depth
•9.1 mi channel extension from BH Reach 3
•Widen areas identified in the 203 Report (Table
1)
The action alternatives will be compared to the No Action alternative to form the basis for engineering, environmentalBACKGROUND.
and economic analysis, and decision-making for the Wilmington Harbor Section 403 effort.
DESCRIPTION OF ALTERNATIVES
REACH
WIDTH DEPTH - MEAN LOWER LOW WATER (MLLW)
Exist. Channel Width
Proposed Channel
Width
Future
Without Project 46 FT ALT 47 FT ALT
(ft)(ft)(ft)(ft)(ft)
AN
C
H
O
R
A
G
E
BA
S
I
N
Anchorage Basin - 0+00 to 8+00 448-548 625 - 1509 38
46 47
Anchorage Basin - 8+00 to 84+85 547-1200 625 - 1509
42
Between Channel 500-545 625
Fourth East Jetty 455-550 550
Upper Brunswick 400-775 500
Lower Brunswick 400-775 500
MI
D
RI
V
E
R
Upper Big Island 540-700 660
42 46 47
Lower Big Island 507-695 500
Keg Island 400-695 500
Upper Lilliput 400-610 500
Lower Lilliput 600 600
Upper Midnight 600 600
Lower Midnight 600 600
Reaves Point 400-600 500
Horseshoe Shoal 400-607 500
Snows Marsh 400-607 500
Lower Swash 400-820 800 - 500
OC
E
A
N
B
A
R
IN
N
E
R
Battery Island 500-820 800 - 1300
44 48 49
Southport 500 800
OU
T
E
R
Baldhead - Caswell 500-646 800
Smith Island Channel 650-895 900
Baldhead Shoal - Reach 1 775-900 750
Baldhead Shoal - Reach 2 900 900
Baldhead Shoal - Reach 3 500 600 - 900
Offshore Extension (New Reach 4)NA 600
Conditionally AuthorizedPreliminary 2nd Action Alt.
Standardizing the width of the channel
ODMDS
PRELIMINARY ALTERNATIVES ARRAY
Wideners proposed TABLE 1.
-52
-51
-50
-49
-48
-47
-46
-45
-44
-43
-42
-41
-40
-39
-38
-37
-36
-35
-34
-33
-32
-31
-30
-29
-28
-27
-400 -375 -350 -325 -300 -275 -250 -225 -200 -175 -150 -125 -100 -75 -50 -25 0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400
El
e
v
a
t
i
o
n
,
M
L
L
W
f
e
e
t
Distance (ft)
Authorized - NAA
Allowable Overdepth - NAA
47-FT ALT
Allowable Overdepth
Bathymetry (example)
47FT Alternative - Allowable 2' Overdepth for Payment During Construction and Maintenance (-49' MLLW)
47FT Alternative - Depth (-47' MLLW)
Allowable 2' Overdepth for Payment during Maintenance (-44 MLLW)
NON-ROCK CROSS-SECTION (FWOP & 47’ ALT)
WILMINGTON HARBOR 403
LETTER REPORT & ENVIRONMENTAL IMPACT STATEMENT
FWOP
NOTE: The vertical and horizontal scales are not the same
FWOP
LEGEND
TYPICAL 3:1 SIDE SLOPE TYPICAL 5:1 SIDE SLOPE
-52
-51
-50
-49
-48
-47
-46
-45
-44
-43
-42
-41
-40
-39
-38
-37
-36
-35
-34
-33
-32
-31
-30
-29
-28
-27
-400 -375 -350 -325 -300 -275 -250 -225 -200 -175 -150 -125 -100 -75 -50 -25 0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 400
El
e
v
a
t
i
o
n
,
M
L
L
W
f
e
e
t
Distance (ft)
Authorized - NAA
Allowable Overdepth - NAA
47-FT ALT
Initial Deepening Required Rock Overdepth
Initial Deepening Allowable Rock Overdepth
Allowable Overdepth
Bathymetry (example)
Allowable 2' Overdepth for Payment during Maintenance (-44 MLLW)
Authorized Depth / Federal Project Depth (-42' MLLW)
47FT Alternative - Allowable 2' Overdepth for Payment During Maintenance (-49' MLLW)
47FT Alternative - Depth (-47' MLLW)
47FT Alternative - Initial Required 1' Rock Clearing Overdepth (-48' MLLW)
47FT Alternative - Allowable 2' Overdepth for Payment During Initial Rock Clearing (-50' MLLW)
ROCK CROSS-SECTION (FWOP & 47’ ALT)
WILMINGTON HARBOR 403
LETTER REPORT & ENVIRONMENTAL IMPACT STATEMENT
(Maintenance)
FWOP
FWOP
LEGEND
BENEFICIAL USE SITES
INITIAL PLACEMENT AND O&M
➢15 intertidal mudflat
creation/renourishment
o Around marshes and bird
islands
➢2 beaches in New Hanover County
o Masonboro &Carolina Beach
➢3 beaches in Brunswick County
o Oak Island, Caswell, Bald Head
➢2 bird islands
o Ferry Slip & South Pelican
➢1 offshore fisheries structure made
of rock
Brackish
Habitats/Marsh
High Saline
Habitats/Marsh
MITIGATION – WETLAND PRESERVATION
WILMINGTON HARBOR 403
Eagle Island.
Restoration and enhancement of approximately 120 acres of
phragmites australis and brackish marsh wetlands
Wetland Preservation.
Preservation of approximately 550 acres of high-quality
forested freshwater wetlands
LD2 EXISTING CONDITIONFISH HABITAT MITIGATION
WILMINGTON HARBOR 403
Aquatic Habitat.
To compensate for the loss of aquatic habitat, fish
passage improvement projects would be constructed
at Lock and Dams 1 and 2 on the Cape Fear River to
enable anadromous fish to access quality habitat
upstream of those facilities.
ECONOMIC ASSUMPTIONS
WILMINGTON HARBOR 403
LETTER REPORT & ENVIRONMENTAL IMPACT STATEMENT
•The action alternatives would not increase the volume of cargo differently than
the without project scenario; the same amount of cargo will be moved more
efficiently (NED Benefits).
•Wilmington Harbor Design Vessel: Post-Panamax Generation III
‒1,200 to 1,220 feet length over all (LOA)
‒44 1,200-foot LOA calls in 2021
‒168 feet beam (Max. for expanded Panama Canal locks)
•Ability to move the same amount of cargo using larger ships = fewer trips – fewer
vessel trips = lower transportation costs (benefits)
•Due to the current channel’s configuration, light loading practices continue as
the least-cost alternative to intermodal shifts in cargo
–Overall vessel fleet composition will remain much the same as it is today
–Bulker and Chemical Tanker fleet mix will not incorporate new, larger classes, but shift
towards larger end of existing fleet, and remain draft constrained
–Asian container shippers will not fully utilize the available fleet of Post-Panamax Generation
III vessels and retain smaller vessels
–A smaller share of the South/Central American container cargo is shifted to the light-loaded,
Post-Panamax Generation I fleet, resulting in smaller vessels continuing to call on Wilmington
‒51 feet draft
‒Nominal 20’ Equivalent (TEU) intake of
~ 10,000 to 15,000 TEUs
23% potential
cost decrease
compared with a
12,500 TEU
container ship
COST PER TEU PER DAY AT SEA
12,500 TEU
18,000 TEU
22,000 TEU
24,000 TEUSource: Van Marle (2013)
AA2 (-46’)AA1 (-47’)
Project First Cost (FY25 Price Levels)$ 968,199,000 $ 1,140,270,000
IDC $ 76,318,000 $ 89,882,000
Economic Cost $ 1,044,518,000 $ 1,230,152,000
Annual O&M $ 12,965,000 $ 14,420,000
Average Annual Equivalent (AAEQ) Costs $ 41,524,000 $ 48,970,000
•Annualized using FY25 Current Discount Rate of 3.0%
SE
C
T
I
O
N
4
0
3
PROJECT COST COMPARISON.
AVERAGE ANNUAL COSTS
•Compensatory mitigation costs are included in this cost
•The environmental impacts of the action alternatives are
similar nature and magnitude relative to benefits
AA2 (-46’)AA1 (-47’)
AAEQ Benefits (slide 6)$71,189,000 $83,278,000
AAEQ Costs (slide 9)$53,561,000 $62,230,000
Net Benefits $17,628,000 $21,048,000
Net Benefit diff (%)
19%
BCR @ 3.0% 1.3 1.3
SE
C
T
I
O
N
4
0
3
(Conditionally Authorized)
•>1.0 Benefit to Cost Ratio = Federal Interest
•The NED Plan must reasonably maximize Net Economic
Benefits
•AA1’s (-47) Net Benefits are 19% greater than AA2’s (-46’)
•AA2 & AA1 have 1.3 Benefit to Cost Ratio
•Conditionally authorized plan (AA1) (-47’) is the Recommended
Plan and National Economic Development Plan.
NATIONAL ECONOMIC DEVELOPMENT
PLAN SELECTION.
Action Alternative RESULTS.
VISUALIZATION.
Figure (right) shows project impacts in red and sea level impacts in
yellow under existing (SLC0) conditions for each action alternative.
Acres converted with AA1 under existing sea level
conditions~1071
Acres converted with AA2 under existing sea level
conditions~ 971
Action alternatives would result in up to 1,071 acres of freshwater
forested wetlands being converted to brackish wetlands
Total area of each salinity zoneWETLANDS IMPACTS
AQUATIC HABITAT SUITABILITY IMPACTS
WILMINGTON HARBOR 403
LETTER REPORT & ENVIRONMENTAL IMPACT STATEMENT
•Indicator species selected:
‒Atlantic sturgeon
‒Blueback herring
‒Striped Bass
‒Southern flounder
‒Previous studies: redfish, white shrimp
•Example Model Inputs:
‒Temperature, dissolved oxygen, salinity, depth
•Different species models analyze different portions
of the water column
•Conditions with and without the project can be
compared to assess changes in habitat quality due to
the project
•Results are expressed in habitat units (HUs)
‒Eastern oyster
‒American shad
‒Spot
HABITAT SUITABILITY INDEX (HSI) MODELS were applied to identify potential indirect impacts to fish and fish habitat
associated with each alternative. An example map of results is shown below.
GROUNDWATER MODEL RESULTS
WILMINGTON HARBOR 403
LETTER REPORT & ENVIRONMENTAL IMPACT STATEMENT
MODELING CONCLUSIONS.
•Deepening the channel will not introduce new flows of salinity from
the Cape Fear River into the aquifers used for drinking water
specifically within the Carolina, Baldhead, and Kure Beach
communities.
•Significant danger of saltwater intrusion without the deepening
project, especially in coastal areas (i.e. Carolina and Kure Beach)
where heavy groundwater pumping is already occurring.
•Sea level rise and, especially, pumping, are far more impactful to
saltwater intrusion than the deepening project.
•An analysis of gradient changes due to the deepening at known
groundwater contamination sites showed no major impacts to the
movement of groundwater contaminant plumes near the Cape Fear
River.
Grid Cross-Section, Showing Hydrogeologic Layering
17
N
PIANC FORMULA
0
200
400
•Clear decrease in overall bottom stress when going
from FWOP to either alternative
•A lower number of vessel passages, not
bathymetry, create the greatest decrease in
bottom stress/erosion potential
•Alternative 1 (-47’) does a slightly better job than
Alternative 2 (-46’) at decreasing bottom stress
RESULTS.
REACH
% DELTA IN BOTTOM STRESS (FWOP -ALT 1 (47’) @ MLLW
SP
X
1
Pa
n
a
m
a
x
PP
X
G
e
n
I
PP
X
G
e
n
I
I
PP
X
G
e
n
I
I
I
GP
T
a
n
k
e
r
MR
T
a
n
k
e
r
LR
T
a
n
k
e
r
Ve
r
y
S
m
a
l
l
Bu
l
k
e
r
Sm
a
l
l
Bu
l
k
e
r
Me
d
i
u
m
Bu
l
k
e
r
La
r
g
e
Bu
l
k
e
r
Ve
r
y
L
a
r
g
e
Bu
l
k
e
r
AN
C
H
O
R
A
G
E
BA
S
I
N
Anchorage Basin
Between Channel
Fourth East Jetty
Upper Brunswick
Lower Brunswick
MI
D
RI
V
E
R
Upper Big Island
Lower Big Island
Keg Island
Upper LIlliput
Lower Lilliput
Upper Midnight
Lower Midnight
Reaves Point
Horseshoe Shoal
Snows Marsh
Lower Swash
OC
E
A
N
B
A
R
IN
N
E
R
Battery Island
Southport
OU
T
E
R
Baldhead - Caswell
Smith Island Channel
Baldhead Shoal - Reach 1
VESSEL FLEET FORECAST
FWOP - ALT 1 (47')
ECONOMIC ANALYSIS: FORECASTED VESSEL TRIPS (2036, 2056, 2085)
8 Vessel types
with negligible changes
in bottom stresses
2 Vessel types
with small decreases
in bottom stresses
3 Vessel types
with moderate
decreases
in bottom stresses
FWOP (42’) 2036
FWOP (42’) 2056
FWOP (42’) 2085
AA1 (47’) 2036
AA1 (47’) 2056
AA1 (47’) 2085
•AA2 (46’) 2036
•AA2 (46’) 2056
•AA2 (46’) 2085
1
-0.625
-2.25
-3.875
-5.5
-7.125
-8.75
-10.375
-12
VESSEL WAKE FOR THE
FORECASTED FLEET
Gates and Herbich
SEDIMENT QUALITY TESTING
WHEN WILL SEDIMENT BE TESTED?
•Before dredging, during the Pre-Construction Engineering and Design (PED) phase
WHAT TYPE OF TESTS WILL TAKE PLACE?
Engineering. To determine the visual classification (USCS symbol) and grain sizes of unconsolidated sediments we will
perform the following three tests:
•ASTM D6913, Particle-Size Distribution of Soils Using Sieve Analysis
•ASTM D2487, Standard Practice for Classification of Soils for Engineering Purposes
•Visual, volumetric percentage of shell and rock fragment determination.
•Additional tests as needed for consolidated sediments
Environmental. Testing requirements for compliance with Clean Water Act and other environmental laws will be
coordinated with state and federal agencies, such as the North Carolina Department of Environmental Quality and
U.S.Environmental Protection Agency.
DESCRIPTION OF ALTERNATIVES
QUESTIONS?
For more project information please visit:
https://wilmington-harbor-usace-saw.hub.arcgis.com/